Consultations
Open and recent consultations across Ofgem, NESO, and DESNZ.
Closing soon (10)
Ofgem consults on draft determination for NGET's RIIO-2 Visual Impact Mitigation re-opener to underground transmission lines in the Cotswolds AONB. Closes 28 April 2026.
CMP445 proposes amending the CUSC so generators pay TNUoS on a pro-rated basis from their Charging Date during the first year of connection, rather than the full annual charge. Code Administrator Consultation closes 29 April 2026. Three solutions presented: Original plus two Alternatives.
NESO invites stakeholder feedback on draft early competition documents for Competitively Appointed Transmission Owners (CATOs): Project Appraisal Method, Tendered Scope of Works, Pre-qualification Questionnaire, and ITT Evaluation Criteria. Responses due by 30 April 2026.
NESO consults on a roadmap to gain operational visibility and dispatch access to distributed energy resources (DERs) and consumer energy resources (CERs) — commercial batteries, small-scale wind, EVs, rooftop solar, and home batteries. The consultation closes 30 April 2026 and seeks feedback on ambition, practicality, and completeness of proposed capabilities and data requirements. This is the system operator's bid to extend its operational reach below the transmission-distribution boundary.
Ofgem proposes strategic planning-led interconnector development where NESO identifies projects and government sets delivery and financing arrangements. The consultation closes 1 May 2026. This shifts from developer-led merchant models to centrally planned interconnection aligned with wider system needs.
DESNZ launches consultation on non-pipeline transport for CCUS, covering ship and truck transport of CO2 where pipelines are unviable. Consultation closes 1 May 2026 with policy decisions to follow. Targets waste management, bioenergy and power sectors requiring CCUS but lacking pipeline access.
Ofgem consults on National Gas Transmission's re-opener application to modify outputs, delivery dates, and allowances for the Peterborough compressor emissions programme under RIIO-GT2 Special Condition 3.11. Consultation closes 5 May 2026.
Ofgem: Ofgem proposes adapting the energy price cap wholesale allowance methodology to accommodate Market Wide Half-Hourly Settlement (MHHS), which changes how suppliers are settled when purchasing electricity to match customer demand. The consultation seeks views on setting wholesale allowances that track efficient costs, accounting for cost differences across customer groups, and developing time-of-use price cap variants. Responses are due by 5 May 2026. Elexon: Market-Wide Half-Hourly Settlement systems went live in September 2025, with first Wave 1 participants completing qualification and beginning migration of 30 million supply points. The programme transitions from implementation to business-as-usual operation of settlement systems and the Data Integration Platform. Elexon served as Implementation Manager rather than Ofgem leading directly, coordinating industry delivery through working groups and volunteer early adopters.
Ofgem invites comment on draft guidance for the Warm Home Discount scheme 2026-2031, following government expansion of the WHD. Closes 8 May 2026. Targeted at obligated suppliers.
Ofgem proposes standardised reporting requirements for network companies to disclose procurement practices, local content, and supplier details for electricity network equipment and services. The consultation closes 10 May 2026 and explores potential adjustments to encourage greater domestic supply chain participation within existing regulatory frameworks. This follows Great Britain's planned network expansion requiring unprecedented equipment procurement.
Open (19)
Ofgem: RIIO-2 Regulatory Instructions and Guidance and Regulatory Reporting Packs; Notice of proposed modifications to the Regulatory Financial Performance Reporting template and guidance for RIIO-2 (2026)
Ofgem consults on modifications to RIIO-3 associated documents, including crossover guidance for GD2/GD3 and GT2/GT3 adjustments, plus NGET PCD reporting requirements. Closes 13 May 2026.
Ofgem is consulting on reintroducing the Market Stabilisation Charge licence condition into supplier licences, creating a ready-made mechanism to impose switching charges if wholesale prices fall sharply. The MSC would require any supplier gaining a customer to compensate the losing supplier for stranded energy purchase costs. This is a preparatory step — the licence condition would sit dormant until activated by a future consultation and decision.
Ofgem consults on transitional measures to move BSC and REC governance to the new framework under the Energy Act 2023. This covers code text changes, licence revocation terms, and amended conditions for phase 1 code manager candidates.
DESNZ: Eskdalemuir seismic array: revised approach to managing onshore wind turbine interference; Eskdalemuir seismic array: managing onshore wind turbine interference
Ofgem calls for stakeholder input on NESO's Business Plan 3 performance for 1 April 2025 to 31 March 2026, the final year of RIIO-2. Assessment moves to a Below/Meets/Exceeds Expectations grading across two components: delivery of business plan aims (via Success Measures) and value for money. Responses due 18 May 2026; final decision summer 2026.
Ofgem consults on the ED2 Strategic Innovation Fund allocation. Closes 19 May 2026.
Ofgem consults on reforming the Relative Price Control (RPC) for Independent Gas Transporters, which sets floor and ceiling limits on gas transportation charges. The consultation runs until 22 May 2026 and proposes changes to current pricing arrangements alongside improved reporting requirements.
DESNZ: Whole energy cyber resilience requirements: reshaping cyber regulation in downstream gas and electricity; Reshaping Cyber Regulation in Downstream Gas and Electricity
Ofgem consults on 13 Capacity Market rule change proposals (CP382-CP394). Proposals cover Independent Technical Expert definitions, termination reasons, load-following obligation calculations, metering test processes, and other operational rules. Consultation closes 24 May 2026.
Ofgem sets out five options for redesigning transmission network charges to steer investment towards Strategic Spatial Energy Plan locations, ranging from tweaking existing TNUoS to auctioning connection capacity by zone. Charges would apply to new generators, demand, and storage. Responses by 26 May 2026, reforms targeted for 2029.
Ofgem consults on the second preliminary Strategic Direction Statement, which sets binding priorities for how GB industry codes must develop under the Energy Act 2023 governance reforms. The SDS categorises policy areas requiring code changes and proposes converting from a preliminary to a hybrid document once BSC and REC are designated by end-2026. Responses due 28 May 2026.
DESNZ: Nuclear Third Party Liability for Advanced Nuclear Technologies; Nuclear Third Party Liability for Advanced Nuclear Technologies: call for evidence
DESNZ consults on siting and investment levers under Reformed National Pricing (RNP), the programme that replaces REMA after ministers rejected zonal pricing. Closes 2 June 2026. Ofgem runs a parallel Call for Input on network and connections charging to 26 May. Together these set how much new generation and storage pay, and where.
The RNP Delivery Plan landing page. Frames the 21 April DESNZ consultation and confirms REMA is closed. Substantive response window is the companion siting-and-investment consultation.
DESNZ proposes to simplify UK ETS permitting for cross-boundary CCS pipelines by reducing the number of permits required from multiple regulators to a maximum of two. Current rules require separate permits from each jurisdiction a pipeline crosses (England, Scotland, Wales, Northern Ireland, and offshore), plus monitoring infrastructure at each boundary. The consultation runs until 4 June 2026.
DESNZ proposes new permitted development rights for non-domestic wind turbines up to 30m tip height and 200m² swept area, allowing single turbines on farms, businesses and public sites without planning applications. The proposal requires prior approval from local planning authorities for siting and amenity impacts, with buffer distances of tip height plus 10% from site boundaries and ten times rotor diameter from neighbouring homes. Consultation closes 10 June 2026 with policy expected in autumn.
The UK ETS Authority consults on treatment of sustainable aviation fuels within the UK emissions trading scheme, seeking alignment with the SAF Mandate that began January 2025. The consultation examines expanding eligible fuel types beyond biofuels, adjusting emissions saving thresholds from 65% to 40%, and moving from zero-rating SAF to lifecycle assessment approaches.
Ofgem reviews the temporary debt cost allowance it added to the energy price cap between April 2022 and June 2025, comparing actual supplier debt costs against the allowances received. The consultation closes 16 June 2026 and focuses specifically on whether the temporary allowance was set correctly, with potential price cap adjustments if not. The review excludes broader debt strategy considerations.
Recently closed (10)
Ofgem proposes updating typical domestic consumption values for electricity and gas that underpin the price cap methodology. The consultation closes 20 April 2026. These values help households estimate their energy usage and affect how the price cap is calculated.
Ofgem proposes removing distribution network operators' reporting requirements under Standard Licence Condition 31E, transferring responsibility to Elexon as Market Facilitator from April 2027. The modification eliminates DNO obligations to report flexibility service procurement data to Ofgem. Statutory consultation follows in June 2026 with final decision by August 2026.
NESO consults on updates to the methodology for compensating interconnector owners when Net Transfer Capacity restrictions limit cross-border electricity flows. The proposed changes are largely housekeeping — rebranding from ESO to NESO, deduplicating content, correcting legacy errors (removing a scarcity adjustment never used, switching from mean to median clearing prices), and reorganising the document chronologically. The substantive content is the methodology's treatment of intraday versus day-ahead restrictions and the refusal to expand compensation beyond congestion revenue to cover knock-on losses in capacity markets or frequency response.
Government proposes using new statutory powers to accelerate grid connections for strategic demand projects, including data centres and AI Growth Zones, through queue management reforms, capacity reservation, and reallocation mechanisms. The proposals would impose higher financial requirements on data centres to address speculation in the 125GW demand queue, while creating prioritisation systems for government-identified strategic projects. Consultation closes 15 April 2026.
Ofgem is consulting on Early Construction Funding for Scottish Power Transmission's Denny to Wishaw 400kV reinforcement project under the ASTI re-opener mechanism. The consultation closes 15 April 2026 with responses to be submitted to transmission.acceleration@ofgem.gov.uk. This follows SPT's application for accelerated funding to begin construction ahead of the normal RIIO price control cycle.
DESNZ proposes mandatory technical standards for heat networks through a Heat Network Technical Assurance Scheme covering governance, assurance processes, and technical requirements. The consultation runs until 15 April 2026. This applies to heating infrastructure, not electricity generation or grid systems.
NESO launches a call for input on Reformed National Pricing (RNP) proposals to reform dispatch arrangements and electricity market design, with responses due 14 April 2026. The RNP programme aims to strengthen investment signals, improve operational efficiency, and reduce constraint costs within Great Britain's retained single national wholesale market. Government will provide legislation as required for timely delivery.
Ofgem consults on cost recovery mechanisms for heat networks regulation, proposing to collect fees bi-annually from heat network suppliers serving end consumers, with a de minimis threshold exempting smaller networks. The consultation covers fee apportionment based on customer numbers, payment frequency aligned with gas and electricity markets, and blended cost recovery across all three sectors. Responses close 2 April 2026.
DESNZ opens consultation on CfD contract changes to implement Clean Industry Bonus reforms for Allocation Round 8. The consultation closes on 1 April 2026. This follows earlier announcements of the Clean Industry Bonus mechanism designed to incentivise domestic supply chain investment.
Elexon has published draft governance frameworks for Smart Secure Electricity Systems (SSES) and extended the consultation deadline to 31 March 2026. The framework establishes enduring governance arrangements for smart secure electricity systems in Great Britain, including bilateral agreements with cross-references to BSC provisions.
No closing date (355)
Ofgem has published a call for input on the future regulatory framework for electricity interconnection, covering route to market, competition models, financing structures, and treatment of Offshore Hybrid Assets. This accompanies DESNZ's policy paper on interconnection's role in a strategically planned system. GB currently has 10.3 GW of operational interconnector capacity with 1.4 GW in construction and 8.9 GW in development under existing approvals.
Ofgem policy update on early competition in onshore electricity transmission networks. Progresses the framework for competitively tendering new onshore transmission projects instead of defaulting to incumbent TOs.
Ofgem's initial project assessment for the third cap and floor window for electricity interconnectors. Assesses new interconnector projects seeking the regulated revenue framework that guarantees a minimum return while capping upside.
Ofgem's initial project assessment of Offshore Hybrid Asset pilot projects. OHAs combine offshore wind connections with interconnector functionality, allowing cross-border power flows on the same infrastructure.
DESNZ proposes changes to the Capacity Market to maintain security of supply while enabling unabated gas plants to decarbonise. The consultation combines proposals for rule changes with a call for evidence on future market design. No specific mechanisms or parameters are detailed in this announcement.
DESNZ launches a review of Ofgem's role and powers, citing consumer protection concerns and the need for higher standards in energy markets. The review will examine the regulator's functions and delivery mechanisms. No specific timeline or scope limitations are provided.
DESNZ opens consultation on National Policy Statement EN-7, which will set planning policy for nuclear power stations deploying after 2025. The NPS replaces outdated planning guidance and determines how Planning Inspectorate assesses Development Consent Orders for new nuclear projects. This affects all nuclear development beyond current committed projects like Hinkley Point C and Sizewell C.
DESNZ proposes relaxing CfD eligibility to allow offshore wind projects without full planning consent to bid in AR7, opening summer 2025. The consultation considers extending CfD contract terms beyond the current 15 years and giving the Secretary of State greater visibility over sealed bid information to set budgets. AR7 budget allocation will use different criteria for fixed-bottom offshore wind.
DESNZ consults on streamlining land rights and consents processes for electricity network infrastructure to enable faster deployment. The consultation follows a 2022 call for evidence and targets reducing costs, complexity and delays that currently hinder network projects. Minor changes to existing infrastructure will be fast-tracked to free resources for complex cases requiring detailed scrutiny.
DESNZ proposes changes to Capacity Market rules affecting CfD projects, Long Duration Electricity Storage, and delivery assurance ahead of 2026 prequalification. Key changes include allowing CfD units strategic participation in CM, setting LDES Cap and Floor eligibility criteria, and raising termination fees by 30% or simplifying to single £45,500/MW fee. Multiple Price Capacity Market eligibility tightens with higher CapEx thresholds and disconnection certificate requirements.
DESNZ proposes extending CfD eligibility to existing nuclear plants seeking lifetime extensions, requiring legislation changes to enable subsidised investment in plant refurbishments. The consultation runs until early 2025 with no specified implementation timeline. This would apply CfD strike prices to plants that currently operate merchant, potentially covering substantial refurbishment costs at Sizewell B and other AGR stations nearing end of design life.
DESNZ proposes creating a new Load Control Licence regime, making it illegal to control customer electricity loads without Ofgem authorisation from end-2026. The licence covers load controllers and Flexibility Service Providers, with cyber security requirements for the former and consumer protection rules for the latter. A 12-month transition period runs from licence applications opening to enforcement.
DESNZ proposes amending electricity connection rules to prioritise 'strategic demand' including data centres and address speculation in the connection queue. The consultation seeks to create a separate pathway for approved strategic projects. This follows the connection queue growing to over 700GW with significant speculative applications.
NESO consults on guidance for secondary generators — those with Grid Code obligations but no restoration contract — on how to comply with the Electricity System Restoration Standard (ESRS). The ESRS requires 60% of national demand restored within 24 hours and 100% within five days of a total or partial shutdown, with a compliance deadline of 31 December 2026. The guidance codifies existing Grid Code obligations around 72-hour plant resilience, cold start time declarations, communications testing, and cyber security under the NIS Regulations.
Ofgem consultation on outturn performance metrics for the RIIO-ED2 Distribution System Operator incentive. Assesses how distribution network operators performed against DSO targets for flexibility procurement, data sharing, and network optimisation.
Ofgem consultation on amendments to the Major Connections Governance Document. Proposes changes to how large connection projects are managed and governed within the transmission network.
Ofgem draft determination on NGET's RIIO-2 non-operational IT capex re-opener application. Assesses whether National Grid Electricity Transmission should receive additional funding for IT systems beyond the original RIIO-2 settlement.
Ofgem call for input on affordability and debt in the domestic retail energy market. Examines the scale of energy debt, repayment practices, and support mechanisms.
The BSC Panel is consulting on code changes to establish governance arrangements for the Smart Data Repository, scheduled to launch later in 2026. The repository will centralise smart meter data to support market operations and grid management. This is implementation detail for an already-decided policy rather than a new structural reform.
Elexon consults on the BSC Performance Assurance Framework for 2026/27, which sets standards and monitoring arrangements for balancing settlement compliance. The consultation appears to be routine framework refresh rather than structural reform. Performance assurance creates costs for non-compliant parties through oversight mechanisms and potential sanctions.
DESNZ proposes a transitional support mechanism for large-scale biomass generators converting to BECCS, covering gaps between existing support ending and future BECCS contracts beginning. The mechanism would apply in specific circumstances where generators face interim periods without revenue support. No details provided on mechanism design, duration, or funding source.
DESNZ proposes licensing regime for energy code managers under the Energy Act 2023, requiring Ofgem approval for organisations managing industry codes like the Grid Code and Connection and Use of System Code. The consultation sets out standard licence conditions and selection processes for code managers, with updated text published 24 April 2024 correcting a question on funding mechanisms. This implements the code governance reform framework established in the Energy Act 2023.
DESNZ proposes amending the CfD supplier obligation regulations to enable the electricity supplier levy to fund Dispatchable Power Agreements (DPAs) for power CCUS projects. The amendment would use the existing CfD cost recovery mechanism to collect payments for a new support scheme targeting gas generation with carbon capture. This extends the supplier obligation beyond its original CfD remit.
DESNZ consults on technical and regulatory frameworks to enable flexibility services from domestic devices like EV chargers and heat pumps through the Smart Secure Electricity Systems Programme. The programme aims to unlock demand-side flexibility to support grid balancing and decarbonisation. This represents implementation planning for already-announced flexibility policies rather than new market design.
DESNZ begins scoping for a new Fusion Energy National Policy Statement to streamline planning consent for commercial fusion facilities. This is the first of two consultations, focusing on policy approach before drafting the actual NPS. The consultation runs for 8 weeks from May 2024.
DESNZ proposes reforms to Scotland's electricity infrastructure consenting under the Electricity Act 1989, targeting projects over 50MW onshore and 1MW offshore within 12 nautical miles. The consultation seeks to modernise consent processes and strengthen community involvement requirements. Both UK and Scottish governments agree that removing inefficiencies from the 1989 Act is the primary route to accelerating deployment for Clean Power 2030.
DESNZ proposes additions to CfD contracts to enable the Clean Industry Bonus mechanism, which provides extra revenue to offshore wind projects that meet supply chain sustainability criteria. The draft contract terms set out notice requirements, payment terms, and performance-related adjustments for non-delivery. The bonus operates within the existing CfD structure rather than as a separate support mechanism.
DESNZ proposes changes to Capacity Market rules to improve demand side response (DSR) participation and delivery assurance. The consultation covers DSR technology categorisation and testing processes. The proposals aim to better integrate consumer-led flexibility within existing capacity procurement.
The UK ETS Authority proposes extending the emissions trading scheme beyond its current 31 December 2030 expiry into a Phase II from 1 January 2031. The consultation considers whether to allow banking of emissions allowances between phases and the duration of Phase II. This continues the existing carbon pricing framework that affects all fossil fuel generators in the power sector.
DESNZ seeks views on supporting oil and gas sector transition in the North Sea, framed as a 'managed transition' rather than immediate cessation. The consultation addresses how to balance existing hydrocarbon extraction with offshore wind development using the same seabed and infrastructure. No specific mechanisms or cost allocations are detailed in this initial announcement.
DESNZ consults on revenue support regulations for Greenhouse Gas Removals and Power Bioenergy with Carbon Capture and Storage, covering contracting procedures, information publication, counterparty functions, and eligibility criteria. The consultation targets project developers, carbon market participants, and investors. This follows the government's broader CCUS and negative emissions strategy but provides implementation detail rather than policy direction.
DESNZ consults on mandating solar canopies on new outdoor car parks above an unspecified size threshold, covering public and private sites. The consultation also seeks views on expanding permitted development rights for EV charging infrastructure to reduce planning barriers. The solar mandate would apply to new car parks, with exploration of retrofitting existing facilities.
DESNZ proposes mandatory community benefit funds for low carbon energy infrastructure, requiring developers to provide monetary or in-kind contributions to local communities. The scheme would require primary legislation to grant regulation-making powers. Separately, the consultation reviews whether to exercise existing powers in the Infrastructure Act 2015 to mandate community shared ownership of renewable projects.
DESNZ consults on drafting changes to CfD Standard Terms and Conditions to allow unconsented fixed-bottom offshore wind projects to bid in Allocation Round 7. The changes would relax eligibility requirements that currently require projects to have consents before bidding. AR7 is scheduled to open in summer 2025.
DESNZ proposes updates to technical guidance for assessing wind turbine noise emissions, which local authorities use to evaluate onshore wind planning applications. The guidance aims to align with current evidence, turbine technology developments, and noise assessment methodologies. No specific noise thresholds or assessment parameters are detailed in this preliminary notice.
DESNZ launches consultation on improving visibility of distributed energy assets including EV chargers, solar panels, heat pumps and batteries through better data collection from installation to operation. The consultation seeks views on strategic data flows and options for mandating asset registration. No specific mechanisms or costs are proposed at this stage.
DESNZ proposes to transfer governance of technical and security standards for smart energy devices from government to industry-led arrangements under Elexon's management through Balancing and Settlement Code modifications. The governance would manage requirements for domestic EV chargers, heat pumps, and other flexibility devices. Costs would be recovered through BSC levies on industry participants.
DESNZ proposes reforms to the Clean Industry Bonus (CIB) for CfD Allocation Round 8, introducing workforce protection and skills investment criteria, extending eligibility to onshore wind, and implementing technical improvements. The CIB provides additional revenue to renewable projects that meet domestic supply chain requirements. The consultation seeks views on these changes ahead of AR8.
DESNZ seeks views on allowing hydrogen-to-power generation into the Capacity Market and on revising interconnector de-rating factors. The consultation runs through early 2026 with decisions expected before the next capacity auction. This would expand the technology mix eligible for capacity payments beyond current fossil and renewable generators.
DESNZ proposes changes to Capacity Market prequalification rules for the 2026 auction, aiming to align the scheme with decarbonisation goals and improve functionality. The consultation covers reforms to existing market rules that determine which capacity providers can participate and under what terms. Specific changes are not detailed in the summary provided.
Government proposes switching inflation indexation for Renewables Obligation buy-out prices and Feed-in Tariff rates from RPI to CPI. Both schemes use inflation adjustments to maintain real value of payments over time. The change would reduce annual increases since CPI typically runs 0.5-1 percentage point below RPI.
DESNZ proposes switching from RPI to CPI for inflation indexation of Renewable Obligation buy-out prices and Feed-in Tariff payments. CPI typically runs 0.5-1 percentage point below RPI over time. The change would reduce annual uplifts for both schemes, affecting existing contract holders.
DESNZ proposes urgent changes to Capacity Market Rules regarding locational changes of capacity units, requiring rule modifications as soon as possible. The consultation aims to enhance scheme functionality and strengthen delivery assurance. This follows a separate broader consultation on Capacity Market Rules published recently.
DESNZ proposes mandatory smart functionality for energy smart appliances (ESAs), including minimum requirements for grid stability, cybersecurity, and consumer switching protection. Phase 1 regulations introduce smart mandates for electric heating appliances and consolidate electric vehicle charging point rules into a single ESA framework. Phase 2 regulations, planned for 2027, will add interoperability requirements to prevent consumer lock-in to specific flexibility service providers.
DESNZ proposes eight refinements to Contracts for Difference (CfD) terms ahead of Allocation Round 8, including permanent restrictions on re-bidding surrendered capacity, hybrid metering arrangements to reduce costs, and excluding applications with Gate 1 connection offers. The consultation runs until early 2025 with changes taking effect for AR8. Other proposals include extending floating offshore wind delivery timelines, strengthening enforcement against distribution-connected generators gaming merchant revenues, and creating a new deepwater offshore wind technology category.
DESNZ proposes comprehensive cost recovery fees for energy infrastructure planning applications to replace current non-cost-reflective charges. The fixed fee model aims to generate revenue for resourcing planning decisions, with annual fee reviews and potential indicative timescales for applications without statutory deadlines. Consultation responses are due by spring 2026 with implementation following.
DESNZ proposes contract amendments to implement Clean Industry Bonus reforms for Allocation Round 8, adding workforce protection measures, skills investment criteria, and extending the bonus scheme to onshore wind for AR9. The consultation runs until March 2026 with final contracts expected before AR8 opens. Changes also include hybrid metering contract amendments affecting all CfD agreements.
Ofgem finalises guidance requiring NESO to produce strategic 'Future Energy Pathways' instead of illustrative scenarios, with pathways showing what must happen to meet net zero by 2050. The guidance mandates whole-system modelling including gas constraints, network limitations in the short term, and granular regional data. NESO must publish major pathways every three years to inform the Centralised Strategic Network Plan, with methodology subject to Ofgem approval.
Ofgem consults on draft guidance for AI deployment across energy sector operations, covering safety, security, fairness and sustainability criteria. The guidance aims to streamline regulatory compliance by mapping AI use cases to existing regulatory frameworks rather than creating new rules. Consultation runs until spring 2025 with regulatory laboratory sessions in February.
DESNZ published the outcome of a call for evidence on how CO2 transport and storage networks should evolve from government-backed RAB models toward commercially self-sustaining operations. The call, which closed 31 October 2025, covered capacity booking reform, network utilisation, flexible products, and the future of Revenue Support Agreements and Government Support Packages for T&S operators. It sits alongside parallel workstreams on CO2 storage economic regulation and non-pipeline transport.
DESNZ consults on minimum energy efficiency standard for socially rented homes. 49,000-word consultation on social housing energy performance.
Ofgem consultation on Utilita's SoLR (Supplier of Last Resort) levy true-up claim for Omni Energy customers. Determines the final amount Utilita can recover for taking on Omni's former customers.
Ofgem call for input on reviewing its policy for network company pension cost recovery. Examines how defined benefit pension deficits are treated within RIIO allowances.
Ofgem proposes modifications to the Regulatory Reporting Pack and Regulatory Instructions and Guidance for network companies. Changes reporting requirements under RIIO.
Statutory consultation on Aurora Utilities Limited, likely related to a new supplier licence application or licence modification.
Ofgem draft determination on Cadent's RIIO-2 non-operational IT capex re-opener. Assesses additional IT funding for the gas distribution network operator.
Ofgem proposes changes to National Gas Transmission's Gas Transporter Licence to formalise demand side response arrangements. Embeds DSR procurement rules into the licence.
We are consulting on whether to add the temporary facilitative conditions to all standard licence conditions.
Statutory consultation on proposals to modify the GT2, ET2, ED2 and GD2 Price Control Financial Instruments and licence conditions.
This consultation document builds upon that decision and outlines our initial proposals for the design of the OFTO build model.
The proposed modifications are made for the purpose of clarifying and updating reporting requirements for the first year of RIIO-ED2.
This consultation invites energy sector participants’ and stakeholders’ feedback on Ofgem’s change to the definition of Energy System Data within Data Best Practice (DBP) Guidance.
We are consulting on our minded-to position on the Early Construction Funding submission application for the Hackney Waltham Cross Upgrade North London reinforcement project.
We are consulting on proposed modifications to the Regulatory Financial Performance Reporting template and guidance for gas and electricity transmission networks, gas distribution networks and the Electricity System Operator.
We are now conducting a Statutory Consultation on our minded-to position on modifying the Generation Licence to include Section F.
This statutory consultation explores two avenues for the removal of the Ban on Acquisition-only Tariffs in the coming year.
We are consulting on minor changes to the Renewables Obligation (RO) and Customer Credit Balance ringfencing guidance and templates.
This consultation sets out our rationale and preferred method for setting the increased payment level at £40 per payment.
Proposed licence modifications to award additional allowances to network companies in relation to our Final Determinations on the RIIO-2 Re-opener Applications 2025.
Proposed changes to five associated documents supporting the gas distribution and gas transmission licences.
We are asking for your feedback on policy proposals to equip the OFTO regime for the future.
We are consulting on our project assessment of National Grid Electricity Transmission’s Bramford to Twinstead project.
Invitation for expressions of interest in becoming a code manager candidate for the consolidated Electricity Commercial Code or the Gas Network Code.
We are seeking views on options to develop a safe regulatory environment where energy sector participants can test and trial AI solutions under regulatory oversight.
We are consulting on proposed modifications to the licences for the RIIO-3 Price Control.
We are consulting on proposed Distribution Network Operator (DNO) licence requirements to maintain asset registers which support data exchange.
We are seeking views on our proposals for implementing NESO's enduring regulatory framework, including our proposed modifications to the Electricity System Operator (ESO) licence and the Gas System Planner (GSP) licence.
We are seeking views on our draft determinations and draft direction for National Grid Electricity Transmission’s Electricity Transmission Control Centre project.
We are consulting on our Draft Determinations and draft direction for five Electricity Transmission Medium Sized Investment Project applications.
We want your views on our proposed changes to the energy price cap methodology to reflect proposals to move Warm Home Discount (WHD) scheme costs from the standing charge to the unit rate.
We sought views on our proposed approach to evaluating code manager candidates as part of a competitive licensing assessment. We also requested feedback on the amended draft guidance.
We are seeking views on updated proposals and next steps of the connections end-to-end review of the regulatory framework.
We are consulting on our proposed approach to implementation of a new licensing regime for load control under the Smart Secure Electricity Systems (SSES) programme.
We want to make changes to reduce the risk of consumers having energy debt when they move into a new home.
Our consultation and decision on changes to the RIIO-2 Network Innovation Allowance Governance Document to allow Distribution Network Operators to continue registering projects past 31 March 2026.
We are seeking views on proposed licence changes to facilitate the award of additional Network Innovation Allowance funding to Distribution Network Operators for the final two years of RIIO-ED2.
We are seeking views on a proposal to change the Capacity Market Rules to facilitate the use of Market-Wide Half-Hourly Settlement Systems.
We are consulting on our proposed approach to granting Authority consent for a request to access land made by Green Volt Offshore Windfarm Limited.
We are looking for feedback on our priorities for 2026 to 2027 before finalising our plan.
Our statutory consultation on establishing a consistent harmonised prioritisation process in the Industry Codes.
We are consulting on data reporting guidance for heat networks.
Our decision on the proposed changes to the Data Assurance Guidance.
Our decision following our consultation on our Early Construction Funding assessment for six National Grid projects.
Our proposals on a set of financial resilience measures to ensure consistency across sectors and to strengthen the ring-fence licence conditions.
Our consultation and decision on the Data Communications Company (DCC) price control proposals for regulatory year 2024 to 2025.
This call for input launches our review of the supplier Guaranteed Standards of Performance (GSoP) and seeks views and evidence to guide its development.
Our statutory consultation on introducing Phase 1 of a Debt Relief Scheme (DRS) for customers.
Our call for input seeking views on the causes behind shrinkage volumes on the National Transmission System (NTS).
We are seeking views on our proposals for the future of regulated traditional gas metering obligations beyond 31 December 2025.
We want to hear views on additional guidance on the determination of disputes when connecting to the electricity grid.
We are consulting on the draft Impact Assessment (IA) for our proposals for the digital Consumer Consent Solution (Consent Solution).
We are consulting on the full suite of heat networks authorisation conditions (the regulatory rules), after having previously consulted on them separately over the last year.
This consultation is part of the DCC review programme through which we are reviewing the regulatory framework for the Data Communications Company (DCC).
Outcome of proposed changes to the Warm Home Discount cost allowance in the energy price cap from 1 January 2026 to 31 March 2027 following expansion of the scheme.
We are seeking views on our minded-to position to approve the Original Proposal of CUSC code modification CMP448.
We are consulting on the proposed modifications to the licence conditions necessary to implement the Regional Energy Strategic Plan (RESP).
We consulted on a proposed licence change to Special Condition 9.13 of the gas transporter licence.
We are consulting on our minded to position on the Accelerated Strategic Transmission Investment (ASTI) Pre-Construction Funding (PCF) submission application by Scottish Hydro Electric Transmission Plc.
We are consulting on whether the Maximum Resale Price (MRP) protects consumers, enables investment, and delivers fair pricing.
We are consulting on the methodology we will apply to the electricity distribution sector from 1 April 2028.
We are seeking views on proposals for our new ‘consumer outcomes’, and how we could use them to improve customer experience and promote innovation and growth.
We have decided to modify the guidance for Consolidated Segmental Statements with the intent of driving comparability between returns to bring more transparency in the market.
We are consulting on a proposal to modify a number of licences to introduce a general requirement for licensees to ensure senior personnel remain fit and proper on an ongoing basis.
We want your feedback on introducing new rules stating that energy suppliers must offer their customers at least one lower standing charge tariff option.
We are seeking views on the draft Smart Meter Communication Licence for the Successor Licensee. Consultation closes 7 November 2025.
Our consultation on market facilitator governance, including a statutory consultation on modifications to licence conditions.
The Authority is consulting on proposed modifications to Offshore Transmission Licences (OFTO Licences).
Our minded-to position and subsequent determination on a request from the Transmission Owners to update outputs, target delivery dates and funding arrangements for three Accelerated Strategic Transmission Investment projects.
This consultation sets out the proposed methodology to calculate the Reimbursement Amount energy suppliers will receive for each successful site visit.
We are consulting on proposals to modify the standard conditions of the electricity licence that we are minded to grant to Sphere Energy Connect Limited.
We are seeking views on our draft guidance for the rules and requirements set out in our heat network authorisation conditions.
We are seeking views on our proposals for developing an early competition Offshore Transmission Owner (OFTO) build model.
We are looking for feedback on our proposal to temporarily extend the ban on acquisition-only tariffs from 1 April 2026 to 31 March 2027.
We are seeking views on a long-lasting approach to setting the unidentified gas allowance in the default tariff cap.
Outcome of our proposal to update benchmark consumption used within the price cap calculations.
We are consulting on the creation of a new pass-through mechanism in the current price control for Distribution Network Operators.
We are consulting on draft guidance setting out how we expect to handle any appeals of decisions that have been made by the Data Integration Platform Change and Advisory Board.
We are consulting on the National Energy System Operator’s (NESO) recommendations from this year’s Frequency Risk and Control Report (FRCR) 2025.
Consultation on our minded-to position on Last Resort Supply Payment claims received by Ofgem.
We are consulting on measures to mitigate the financial failure of heat networks in England, Scotland and Wales.
Our decision on the introduction of smart meter guaranteed standards.
Our request for information (RFI) aims to gather quantitative and qualitative data to better understand costs and system pressures associated with gas disconnections across Great Britain (England, Scotland and Wales) for future monitoring purposes, and to finalise initial information received under our CFI 'Exercising Consumer Choice: A review of the gas disconnections framework.'
Ofgem and government are seeking views and evidence on economic regulation for CO2 storage.
Update on our approach to the Debt Relief Scheme and our regulatory expectations for suppliers on Additional Support Credit.
Outcome of our Draft Centralised Strategic Network Plan (CSNP) Guidance consultation.
We are consulting on the proposed licence conditions required to implement the RIIO-3 price control settlement for electricity transmission, gas transmission and gas distribution.
Our consultation on making interim adjustments to the unidentified gas allowance within the energy price cap.
Our call for input seeks views on a proposal to create an Ofgem AI technical sandbox, a safe and controlled digital environment to test artificial intelligence (AI) uses in the energy sector.
We are consulting on our minded-to position on the Early Construction Funding application by National Grid Electricity Transmission for the Sea Link project.
We are proposing to issue new Regulatory Instructions and Guidance (RIGs) under Special Conditions 21.11 and 21.12 of the Regulated Asset Base licence for Sizewell C.
We are consulting on our Draft Determinations and draft directions for these applications.
We are seeking views on our proposed changes to the Special Conditions of the carbon dioxide transport and storage licences for Net Zero North Sea Storage Limited and Liverpool Bay CCS Limited.
We are consulting on HVDC availability, control of OFTO assets, changes to the Generator Commissioning Clause and Bidder Incentive Mechanisms.
Our proposal to modify the standard conditions of the Licence that we are minded to grant to AGR Networks Limited.
We are consulting on proposed modifications to the Regulatory Financial Reporting Pack template and guidance document for NESO ‘National Energy System Operator' for the RIIO 2 period.
We are consulting on the proposed modifications to the licence conditions necessary to implement the Regional Energy Strategic Plan.
Non-statutory consultation on new licence conditions to the Standard Conditions of the Electricity Distribution Licence and the Electricity System Operator (ESO) Licence.
We are consulting on our minded-to decision to reject Connection and Use of System Code Modification Proposal CMP444: Introducing a cap and floor to wider generation TNUoS charges.
We are consulting on expanding the obligation to follow Data Best Practice Guidance (“DBP Guidance”) to selected code parties.
This is a Statutory Consultation for CP388: Conditional Prequalification for assets that have applied for a revised connection date.
Following the consultation and government response on expanding the Warm Home Discount in 2025 to 2026, we have reviewed our guidance in England & Wales and Scotland.
Ofgem is seeking views on our proposed financial framework for Long Duration Electricity Storage (LDES) projects applying under Window 1 of the cap and floor regime.
We are reviewing the regulatory framework for the Data Communications Company (DCC). This is to put in place new arrangements following the expiry of the Smart Meter Communication Licence in 2027.
We are consulting on proposals to modify the standard conditions of the electricity licence that we are minded to grant to E.ON UK Network Assets Limited.
We are reviewing the regulatory framework for the Data Communications Company ahead of the expiry of the Smart Meter Communication Licence. This consultation focuses on the objectives, operational model and role of the Successor Licensee.
We are seeking views on our proposed approach for assessing which Long-Duration Energy Storage (LDES) projects should be awarded a cap and floor regime.
We are consulting on the content of National Energy System Operator (NESO)’s Business Plan Guidance for the enduring regulatory framework, which will commence with the business plan cycle from 1 April 2026.
We are consulting on our enduring regulatory framework for National Energy System Operator (NESO), commencing with the business plan cycle from 1 April 2026.
We are consulting on our minded-to methodology for valuing assets.
This is a statutory consultation to modify the delivery date in Special Condition 3.13 Large Onshore Transmission Investments Re-opener of NGET’s electricity transmission licence.
We are consulting on our minded-to decision for SSEN’s Insulation and Interruption Gas Exceptional Event Claim.
This consultation seeks views on draft text of two guidance documents to help the Data Communications Company (DCC) prepare a Business Plan for implementation of the first ex-ante cost control cycle.
We are consulting on interim changes to the Smart Meter Communication Licence to support our policy conclusions on transition to a new cost control regime and to help administer the final Price Control at the end of the Licence term.
We welcome feedback from stakeholders on the proposed licence modification.
We are consulting on a fair pricing framework for heat networks, including its structure, objectives, principles, and a 'fairness test' for implementation.
View our proposed changes to NESO’s Regulatory Instructions and Guidance and Reporting Pack for the RIIO-2 network price controls period.
We are proposing several amendments to the Price Control Financial Models (PCFMs), Price Control Financial Handbooks (PCFHs), Standard and Special Conditions for electricity distribution and transmission licences and gas distribution and transmission licences.
We are consulting on our proposal to modify the Regulatory Instructions and Guidance (“RIGs”) for RIIO-2.
We have reviewed our current guidance on how to apply for a gas or electricity licence to update our expectations. Find out what has changed and comment in our consultation.
We are consulting on a proposed licence change to Special Condition 9.13 of the gas transporter licence.
We are consulting on proposed amendments to the MHHS Governance Framework following our approval of CR055 'Amendments to M10 and corresponding milestones'.
We are seeking views on how we administer planned changes to the ECO4 and GBIS schemes and seeking comments on draft updates to scheme guidance documents.
We have completed our assessment of the request for an ASTI ODI Penalty Exemption Period for the EGL1 project.
We are consulting on our approach to implementing the industry code governance reforms as set out in the Energy Act 2023.
We are consulting on our recommendation to propose a new licensable activity following a review of the regulatory arrangements for dedicated provision of network services.
We are seeking feedback on NESO's three roles and its deliverables laid out in its business plan as well as its transition from the Electricity System Operator to its current form, under the Future System Operator transition.
We are seeking views on the unit cost of risk threshold under the Network Asset Risk Metric (NARM) Funding Adjustment and Penalty Mechanism.
Consultation on introducing Smart Meter Guaranteed Standards
We are consulting on our proposal to provide additional funding through the Networks Innovation Allowance (NIA) to Distribution Network Operators (DNOs) for the final two years of RIIO-ED2.
This is our call for evidence on Distribution System Operator (DSO) performance in 2024 to 2025.
Proposed changes to the electricity transmission licences held by each of the Transmission Owners to implement the Advanced Procurement Mechanism.
We are consulting about our initial position on the National Energy System Operator’s (NESO) Business Plan 3.
We are reviewing the regulatory arrangements for the Data Communications Company ahead of the expiry of its Licence. As part of this process we must also identify and select a successor licensee to hold the new Smart Meter Communication Licence.
We are consulting on a suite of directions to ensure MHHS Participants fulfil their responsibilities in the delivery of the Programme milestones in line with the existing Implementation Timetable.
The purpose of the consultation is to provide stakeholders with an overview of the Proposal, its implementation, its benefits and the reasoning which has influenced our minded-to decision.
Our consultation on the draft Impact Assessment (IA) for the introduction of Regional Energy Strategic Plan (RESP) policy framework.
We are publishing a suite of consultation documents on connections reform, collectively known as the TM04+ reform package.
We are consulting on our current review of and updates to the Strategic Investment Fund Governance document.
Our proposed modifications to the relevant licensees’ licenses to implement our Tier 1 Stubs Repex Policy Re-opener decisions.
We want to hear your views on our draft NESO Licence Expectations and Performance Arrangements Governance documents.
Under Article 28(2) of the Tariff Network Code, Ofgem must consult every tariff period on the items mentioned in Article 28(1).
Our consultation on a preliminary Strategic Direction Statement (SDS) which sets out Ofgem’s strategic assessment of government policies and developments in the energy sector that we consider will or may require industry code modifications.
Outcome of our consultation seeking views on our proposal to strengthen guidance for supply licensee governance arrangements.
This call for input sets out our intention to undertake a review of the Relative Price Control (RPC) framework as it applies to Independent Gas Transporters (IGTs), and invites responses from relevant stakeholders on the scope, focus and conduct of that review.
Our draft determination and draft direction for the application from Northern Gas Networks requesting additional allowances for its Birkshall Rationalisation and Relocation Works project.
We are consulting on our minded-to position on the Early Construction Funding submission application by SP Transmission plc for the Denny Wishaw project.
We want views about adding a new licence condition for Radio Teleswitch Service (RTS) meters that will safeguard consumers after the switch off.
We want to remove the Performance Metrics (PMs) in the incentive governance document and reporting requirements for PMs, adding other performance requirements instead.
We are consulting on a suite of draft directions on Elexon as Market-wide Half-Hourly Settlement (MHHS) Implementation Manager.
We are seeking views on our draft determination on Scottish and Southern Electricity Network’s RIIO-2 Re-opener Skye-Uist project.
.
This call for input seeks stakeholder views on the current gas disconnections framework and potential future regulatory frameworks that may operate more effectively, assist in achieving net zero and protect consumers.
A statutory consultation for six Capacity Market Rule change proposals brought to us by the Capacity Market Advisory Group.
DESNZ has tasked Ofgem with implementing a cap and floor regime to encourage investments in LDES. This call for input invites feedback from stakeholders to help shape the final plan and ensure we can decide on approved projects by mid 2026.
Our call for evidence from wider stakeholders on companies' published Business Plans for RIIO-3.
We would welcome views from people with an interest in our proposed work programme for the year ahead; particularly those from the energy industry, consumer groups and charities.
We are seeking views on our proposals to design an ex-ante cost control framework for the Data Communications Company (DCC).
We are seeking views on how we should add an allowance into the energy price cap to reflect the Network Charge Compensation scheme (NCC scheme).
Since 2021, Ofgem has been engaging with stakeholders about a range of evolutionary changes aimed at ensuring the OFTO regime remains effective.
Our proposals to improve experiences for people who are struggling to pay their energy bills.
We are consulting on whether to introduce a debt relief scheme for people who have got behind with their energy bills during the energy crisis and may struggle to repay.
Our final consultation on proposals to update the operating cost and debt allowances in the energy price cap.
Our consultation on the market facilitator policy framework.
This statutory consultation sets out our proposed modifications to the relevant Licensees’ licences to implement our decisions for the aforementioned project funding requests.
This statutory consultation sets out our proposed modifications to the relevant Licensees’ licences to implement our decisions for the aforementioned project funding requests.
We are consulting on whether stakeholders and the public agree with our proposed approach to granting consent for a land access request made by Bowdun Offshore Wind Farm Limited.
This consultation seeks views on proposed changes to the data assurance requirements for transmission, distribution, operator, and system planner licensees.
Give us your feedback on our proposed framework, scope and draft request for information before our Levelisation Phase 1 review.
We are consulting on early construction funding and a proposed licence modification for Scottish Hydro Electric Transmission Plc (SHET) to deliver a eight Accelerated Strategic Transmission Investment (ASTI) projects.
We are consulting on a proposal to amend the special conditions for the gas transporter licence.
Consultation regarding proposed changes to the electricity distribution licence under the Housekeeping modification process.
We are seeking views on our draft artificial intelligence guidance on the use of AI in the energy sector.
We are consulting on introducing an Advanced Procurement Mechanism into the electricity transmission price control.
Our statutory consultation on whether suppliers’ enquiry services should be available 24/7 for domestic customers who are without power or gas supply due to a faulty meter.
Call for input regarding the proposal to review and update the guidance for tax clawback calculations included within networks price controls.
We are seeking views on our proposed process and criteria for selecting code managers on either a competitive or non-competitive basis. This includes draft guidance and forms.
We are consulting on a proposal to modify the Vulnerability and Carbon Monoxide Allowance (VCMA) Governance Document.
Our consultation on whether to remove the entire of Section B of Vital Energi Power Networks Limited's electricity distribution licence.
Consultation on proposed changes to the regulatory framework around electricity grid connections as part of our connections end-to-end review.
We are consulting on our minded-to position on the Post Construction Review of the Viking Link interconnector project and conducting a statutory consultation on consequential changes to the special conditions in National Grid Viking Link Limited’s (NGVL) licence.
We are consulting on two Tier 1 Stubs Repex Policy Re-opener submissions from SGN and Cadent.
We have reviewed whether costs Data Communications Company (DCC) reported for Regulatory Year 2023/24 are economic and efficient and have set out our proposals.
We are consulting on the framework for the next electricity distribution price control, which will begin in April 2028.
Disclosure arrangements on the debt-related costs adjustment allowance and operating cost allowances review.
Tell us your views on our proposals to amend some of the existing and create new licence conditions related to the proposed Target Model Options (TMO4+) for Connections Reform.
Call for input to set out an Economic Evaluation Strategy for Ofgem.
Consultation on the National Energy System Operator’s (NESO) proposals on elements of the commercial framework for the Early Competition regime
Following our previous decisions on Last Resort Supply Payment claims, we have now assessed further subsequent claims and have published our minded-to position.
Consultation on extending the BAT and the associated Market-wide Derogation until 31 March 2026 and on how well they function.
Statutory consultation on proposed modifications to the electricity system operator and electricity transmission licences.
We are seeking views on how we can unlock more innovation, and protect consumers, in a changing and evolving energy retail market.
We are consulting on the Last Resort Supply Payment claims minded-to positions 2024.
This document sets out the conclusions to our August 2024 consultation on the review of Gas Transporter traditional metering licence conditions and consulting on the proposed modification to the Special and Standard Special licence conditions.
We are consulting on the draft Electricity (Early-Model Competitive Tenders for Onshore Transmission Licences) Regulations 2024 that will provide the legislative framework for future onshore transmission tender exercises.
We are consulting on further detailed regime parameters and timelines and incentives for the Non-Standard Interconnectors of the Offshore Hybrid Asset pilot scheme.
We are now consulting on the changes required to the gas and electricity supply and distribution licences.
We are calling on views and evidence on methods of evidencing Help to Heat Group membership under ECO4 and low-income group membership under the Great British Insulation Scheme.
We are consulting on Scottish Hydro Electric Power Distribution’s (SHEPD)1 Shetland Standby Project under the Shetland Enduring Solution reopener.
We are requesting feedback on the draft Request for Information from suppliers who currently have a derogation from the default tariff cap.
Our consultation on the principles and methodologies that will underpin the National Energy System Operator (NESO) Financial Handbook
We would like views from people with an interest in the electricity transmission, electricity distribution and gas distribution networks.
We are consulting on proposals for funding costs incurred by National Grid plc as a consequence of the introduction of the National Energy System Operator.
This minded to decision document sets out our proposed process for health reviews conducted by windfarms and OFTOs.
We are consulting on the content of NESO’s Business Plan Guidance, which aims to provide an update on the information that should be included in the Business Plan for BP3.
We are consulting on wider changes to our performance incentives framework for the business plan period commencing 1 April 2025 and ending 31 March 2026 (BP3).
We are seeking views on the options for how a simpler Smart Metering Net Cost Change (SMNCC) allowance could work.
This consultation contains proposed modifications to Special Condition 9.3 Price Control Deliverable Reporting Requirements and the Price Control Deliverable Reporting Requirements and Methodology Document.
We are consulting on our minded-to position on the project assessment for Yorkshire GREEN under the Accelerated Strategic Transmission Investment (ASTI) mechanism.
We are seeking views on our proposed design principles and necessary features for a solution to sharing data securely.
This consultation sets out our proposed approach to the traditional metering obligations found within the Gas Transporters Standard Special and Special Conditions, a number of which are due to sunset on 31 December 2024.
This consultation contains our proposals for a regulatory approval and funding framework for the onshore electricity transmission projects recommended by the Electricity System Operator.
Our consultation on our draft proposals for the design, calibration and operation of the Opex Escalator (OE) Review Mechanism.
This new Statutory Consultation sets out our consideration of responses to the May consultation and confirms our intention to progress with our preferred option to uplift the payment level from £30 to £40 per payment.
This consultation sets out our proposed policy framework for the Regional Energy Strategic Plan. We are seeking input from stakeholders on RESP building blocks, regional governance, and boundaries.
We have published our proposed changes to Electricity Distribution Licence Special Conditions 1.2 and 4.8 to reflect our decision.
This consultation seeks views on an interim governance framework for the minimum viable product of the Data Sharing Infrastructure.
In this call for input we outline the proposed approaches for managing the effects of surplus residual charges.
We are seeking your views on delivering a Flexibility Market Asset Register to achieve the overall Flexibility Digital Infrastructure vision.
Under Article 28 of the Tariff Network Code, Ofgem must consult every tariff period with interested parties on the items mentioned in Article 28(1).
We are consulting on considerations to seek changes to the way in which smart meter communications licences can be granted under the Gas Act 1986 and the Electricity Act 1989.
We are consulting on our minded-to direction to Cadent Gas Ltd, Northern Gas Networks Limited and National Gas Transmission to return to national gas consumers a funding overpayment for Hydrogen Village Trial Stage 2.
We are presenting an updated Initial Project Assessment analysis for specific criteria to reflect material changes to the project and are seeking views from stakeholders.
Further consultation on the detailed parameters for the cap rate of the cap and floor regime for Window 3 electricity interconnectors.
We are consulting on our proposed upper and lower threshold values for the Unit Cost of Risk (UCR).
Our proposed Bacton Terminal site redevelopment Final Preferred Option following submission by National Gas Transmission of the Final Option Selection Report.
We are consulting on our proposed approach for how these Additional Support Credit costs could be accounted for beyond September 2024.
Our provisional views on NESO’s strategic aims, performance objectives, value for money, reporting requirements and innovation funding.
We are seeking views on the associated guidance document for the new RIIO-GT3 crossover licence condition 3.28.
Our assessment of companies' performance and have come to a view on whether we will be making any revenue adjustments.
We are seeking views on the associated guidance document for the new RIIO Gas Distribution (RIIO-GD3) crossover licence condition 3.28.
Our assessment of proposed modifications to the Network Asset Risk Metric methodologies used in the energy transmission and gas distributions sectors.
We are seeking views on proposed indicators of Ofgem’s performance and the health of the sector, to provide transparency against Multiyear Strategy priorities.
Our Early Construction Funding assessment of Scottish Power Transmission Plc’s Early Construction Funding (ECF) application for the Tealing-Kincardine Upgrade Project.
We are consulting on our project assessment of National Grid Electricity Transmission’s Hackney – Waltham Cross Upgrade Project.
Under Article 28(2) of the Tariff Network Code, Ofgem must consult every tariff period with interested parties on the items mentioned in Article 28(1).
We need to make technical Standard Licence Condition (SLC) changes which were not proposed by us nor identified by stakeholders during our statutory consultation.
This document, which is part consultation and part call for input, forms part of our wider work developing the methodology we should apply for ED3.
We are consulting on our minded-to position on the Early Construction Funding submission applications by Scottish and Southern Electricity Networks Transmission for eight electricity transmission projects.
Our consultation on proposed changes to template code text, the set up of stakeholder advisory forums and information about our code consolidation workshops.
We are consulting on proposals for three Associated Documents (ADs) that would be established under National Energy System Operator’s (NESO) proposed new licences.
We are seeking stakeholder interest in joining the Charging Transitional Arrangements Group (CTAG) to inform our view on whether arrangements might be needed ahead of transmission charging reforms.
We are consulting on proposed modifications to the RIIO-2 Regulatory Instructions and Guidance (RIGs) and Regulatory Reporting Pack (RRP) for the Electricity System Operator (ESO).
We are seeking views on a working draft of the proposed special licence conditions for the Long Duration Electricity Storage (LDES) cap and floor scheme.
We are seeking views on our proposals from CO2 Transport and Storage network companies, network users any other parties with an interest in our carbon capture and storage enforcement work.
This consultation sets out the proposed modifications to implement changes to some industry codes in relation to the Independent System Operator and Planner (ISOP).
Our analysis and proposals for the future governance arrangements for the Data Communications Company and the provision of the Centralised Registration Service (Switching).
DESNZ proposes updating ecodesign regulations for local space heating products to align with EU standards, replacing 2015/1188 with requirements based on EU Regulation 2024/1103. The consultation seeks views on improved efficiency standards that would reduce energy demand and cut consumer bills. This affects product standards for heating appliances, not electricity market structure.
DESNZ launches consultation on a £5 billion Warm Homes Fund offering government-backed loans and investments for domestic solar, batteries, heat pumps, and energy efficiency measures. The fund targets upfront cost barriers through financial transactions rather than grants. Consultation closes on an unspecified date seeking views from installers, manufacturers, housing providers, and finance institutions on fund design and target groups.
DESNZ seeks views on redesigning default tariffs for households who do not actively choose energy suppliers. The call for evidence covers design principles, tariff types, and alternative consumer protections. No specific proposals are presented.
DESNZ launches a call for evidence on hydrogen and CCUS supply chains under the £960 million Green Industries Growth Accelerator fund. The consultation seeks input on manufacturing capacity and supply chain bottlenecks in these sectors. GIGA forms part of a wider £4.5 billion manufacturing package targeting strategic clean energy sectors.
DESNZ opens consultation on future policy framework for biomethane production, seeking evidence on support mechanisms beyond current schemes. The call for evidence runs until an unspecified date and covers policy options for scaling biomethane injection into gas networks. This focuses on gas infrastructure rather than electricity markets.
DESNZ launches a call for evidence on transition finance — funding for organisations to decarbonise activities in hard-to-abate sectors. The review will report in summer 2024 and focuses on making the UK attractive for raising capital to support net zero transitions. No specific energy market mechanisms or charges are proposed.
DESNZ seeks evidence on non-pipeline CO2 transport and cross-border CO2 networks for CCUS deployment. The consultation covers value chain data, policy landscape, and deployment barriers for shipping and road/rail transport of captured carbon. This focuses on industrial decarbonisation infrastructure rather than electricity generation or grid systems.
DESNZ proposes guidance on criminal and civil sanctions for fuel supply resilience measures under Part 12 of the Energy Act 2023. The guidance covers statutory obligations, enforcement regimes, and procedures for enforcement undertakings when core fuel sector participants commit offences. Consultation closes on details not specified in the excerpt.
DESNZ proposes regulations under Section 276 of the Energy Act 2023 requiring fuel sector participants to provide routine data on activities, assets, sales and stock levels to government. The consultation sets out data collection requirements, timescales and which participants must comply. This covers fuel supply chains rather than electricity generation or grid operations.
DESNZ proposes integrating greenhouse gas removals (GGRs) into the UK Emissions Trading Scheme, allowing carbon removal credits to offset emissions within the carbon pricing system. The consultation covers engineered removals and potentially nature-based solutions, with decisions on cap policy, allowance design, and permanence requirements. This extends the UK ETS beyond direct emissions to include negative emissions technologies.
DESNZ proposes establishing a regulatory framework for Third-Party Intermediaries (TPIs) — price comparison websites, energy brokers, and switching services — in the retail energy market. The consultation closes with no specified date and seeks views on regulatory options including mandatory licensing, voluntary codes, or hybrid approaches. This targets consumer protection rather than market structure reform.
DESNZ consults on mid-scheme changes to ECO4 and GBIS, including pay-for-performance measures. The consultation covers modifications to current requirements and new performance-based elements to help reach the 2030 fuel poverty target of band C homes. Responses close date not specified in the excerpt.
The consultation proposes allowing UK ETS operators to deduct CO2 from their allowance obligations when it is permanently stored via non-pipeline transport (road, rail, ship). This enables facilities without pipeline connections to access geological carbon storage while receiving ETS credits. The framework would regulate transport emissions and intermediate storage sites.
The UK ETS Authority proposes expanding the emissions trading scheme to cover maritime sector from 2026, applying carbon pricing to shipping fuels that currently do not reflect environmental costs. The consultation covers scope definitions, cap adjustments, operator requirements, and potential future expansion to international routes. Maritime operators would need to purchase allowances for their emissions, creating a direct carbon cost.
DESNZ consults on adjusting free carbon allowances for industrial sectors under UK ETS, focusing on carbon leakage calculations and border adjustment impacts. The consultation proposes changes to how the Carbon Leakage List is calculated and how free allocations adjust when EU's Carbon Border Adjustment Mechanism affects UK industries. This follows a 2023 review that committed to publishing a draft leakage list.
DESNZ proposes raising minimum efficiency standards for heat pumps, introducing efficiency standards for hybrid heat pumps, and removing lower-performing gas boilers from the market through updated ecodesign regulations. The consultation also proposes simplifying energy labels from the current A to A+++ scale to a clearer A-G scale. These are product standards that affect heating equipment manufacturing and retail, not electricity system operation.
DESNZ proposes a Smart Data scheme allowing customers to share energy consumption data with authorised third parties for tariff comparison and personalised services. The consultation seeks views on scope, governance, and implementation design. No specific timeline or regulatory framework is outlined.
DESNZ proposes a Gas Shipper Obligation to fund hydrogen production projects through charges on gas shippers. The mechanism would support the Hydrogen Production Business Model for initial projects, with potential extension to future hydrogen developments. Consultation seeks views on design choices for this funding approach.
DESNZ opens consultation on updating the fuel poverty strategy, seeking views on priorities for delivering warm homes. The consultation runs until an unspecified date and covers policy approaches to reduce fuel poverty rates. This follows the existing fuel poverty strategy framework established under previous governments.
DESNZ proposes raising minimum energy efficiency standards for privately rented homes in England and Wales by 2030, building on a 2020 consultation. The consultation seeks views on increasing the threshold beyond the current EPC Band E requirement. No specific new standards or timelines are detailed in this announcement.
DESNZ proposes removing the high-cost-to-heat threshold from the Warm Home Discount Scheme, making all households on means-tested benefits eligible for the £150 rebate from winter 2025/26. The scheme would also extend to park home residents without direct supplier relationships while maintaining current budget levels. Scotland would receive proportionally increased spending allocation for its Broader Group distribution.
DESNZ seeks technical evidence on hydrogen-to-power projects that can deploy by 2030 without large-scale hydrogen infrastructure. The consultation targets developers with existing H2P deployment plans. No policy changes or funding commitments are proposed — this is information gathering for future policy development.
DESNZ launches consultation on governance framework for voluntary carbon and nature credit markets, establishing six integrity principles for credit standards and use. The consultation responds to stakeholder calls for regulatory clarity and Climate Change Committee recommendations. Consultation closes in summer 2025.
DESNZ launches a call for evidence to inform a Nuclear Regulatory Taskforce examining defence and civil nuclear regulation. The consultation seeks case studies, historical data, and evidence for regulatory reform from industry stakeholders. No specific reforms are proposed — this is evidence-gathering to inform future taskforce recommendations.
DESNZ proposes changes to the Boiler Upgrade Scheme to increase heat pump uptake and mandates MCS as the sole certification scheme across all clean heat programmes. The consultation covers grant mechanics for heat pumps and biomass boilers in England and Wales, alongside certification requirements for ECO4, Social Housing Fund, and Local Grant schemes. Consultation closes on date to be confirmed.
DESNZ consults on revisions to the Clean Heat Market Mechanism for scheme year 2 (2026/2027), following the mechanism's launch on 1 April 2025. The mechanism requires fossil fuel heating manufacturers to contribute to heat pump deployment costs. Specific revisions and parameters are not detailed in this announcement.
DESNZ commissioned an independent review of greenhouse gas removals (GGRs), including BECCS and DACCS, to assess how these technologies can help meet net zero targets by 2050. Dr Alan Whitehead chairs the review, which includes stakeholder roundtables and a public call for evidence. The review will produce recommendations for government consideration, but government will not respond to individual submissions.
DESNZ consults on mandating FTSE 100 companies and UK financial institutions to develop transition plans aligned with 1.5°C targets. The consultation follows a manifesto commitment but provides no details on requirements, enforcement, or timing.
DESNZ proposes a new regulatory framework for 100% hydrogen pipeline networks under the Gas Act 1986, covering economic regulation for hydrogen transport infrastructure. The consultation runs until an unspecified date and seeks views on implementation through legislation, licences, and codes. This targets hydrogen for industrial decarbonisation and heavy transport, not electricity generation.
DESNZ proposes minimum energy performance standards that would phase out air-vented, gas-fired and condenser tumble dryers, allowing only heat pump models. The consultation also sets 80% minimum condensation efficiency and introduces circular economy measures including spare parts availability. These changes align with new EU regulations on household tumble dryers.
DESNZ consults on blending hydrogen into the gas transmission network, seeking views on strategic value, commercial support models, and technical delivery arrangements. The consultation covers impacts on gas network users, market arrangements, and billing structures. No specific timelines or cost estimates are provided.
DESNZ consults on creating a consumer engagement framework to increase uptake of demand-side flexibility through information campaigns and coordination between existing organisations. The consultation explores government's role in promoting voluntary demand shifting but proposes no specific mechanisms, charges, or market changes. This is a consultation about whether to consult further on detailed proposals.
DESNZ consults on transitioning carbon capture, utilisation and storage networks from government-led development to market-led operation. The consultation seeks industry views on challenges hindering CO2 transport and storage network commercialisation. No specific timeline or cost allocation mechanisms are detailed.
DESNZ opens consultation on economic regulation of CO2 storage infrastructure, questioning whether the existing Regulated Asset Base model remains appropriate as carbon capture markets mature. The consultation examines natural monopoly characteristics, competition mechanisms, and investment incentives for offshore CO2 storage.
DESNZ consults on bill discount scheme design for residents living near new or significantly upgraded transmission infrastructure. The scheme would provide direct bill reductions to households in defined proximity to transmission projects. Consultation closes on a date not specified in the provided content.
DESNZ seeks evidence on coordinating smart meter installations with low carbon technology deployments to reduce field capacity constraints and improve consumer experience. The call for evidence focuses on installation efficiency, field capacity constraints in certain locations, and local coordination opportunities in areas with low smart meter penetration. No specific mechanisms or changes are proposed.
DESNZ proposes extending smart meter installation obligations beyond 2025, requiring suppliers to complete domestic rollout by 2030 and improve operational performance. Current annual installation targets end 31 December 2025. Suppliers would submit annual deployment plans and face new obligations on meter functionality.
DESNZ proposes extending ECO4 by 6-9 months beyond March 2026 to maintain supplier obligations for installing energy efficiency measures. The extension allows obligated suppliers to deliver beyond their targets and carry delivery forward to future schemes. The consultation runs until late 2025 with implementation details to follow.
DESNZ proposes amendments to Nuclear Safeguards regulations to improve clarity and operational effectiveness following a 2023 statutory review. Changes include terminology updates and corresponding fee structure adjustments. The amendments maintain international non-proliferation obligations while streamlining domestic compliance requirements.
The consultation proposes to continue the Warm Home Discount scheme beyond its March 2026 expiry, maintaining support for around 6 million households through winter 2030/31. The scheme provides annual discounts on electricity bills funded through supplier obligations that socialise costs across all consumers.
DESNZ proposes to halve complaint escalation times from 8 weeks to 4 weeks, reduce Ombudsman decision timeframes to 4 weeks, and strengthen enforcement powers against suppliers who fail to implement rulings. The consultation covers domestic suppliers, small enterprise complaints, and heat networks but excludes electricity and gas networks. These are process improvements to existing consumer redress mechanisms rather than market structure changes.
DESNZ explores alternative heating technologies beyond heat pumps and heat networks as backup options for buildings where primary solutions are unsuitable. The consultation seeks views on technologies like hybrid heat pumps, biomass, and hydrogen for domestic and non-domestic buildings. Government maintains heat pumps and heat networks remain the primary decarbonisation path.
DESNZ proposes expanding the UK Emissions Trading Scheme to cover a share of emissions from international maritime voyages to and from UK ports. The consultation seeks views on scheme scope, cap adjustment mechanisms, future IMO alignment, and impacts. This follows generally supportive responses to November 2024 maritime ETS expansion proposals.
DESNZ consults on operational cost budgets for LCCC and ESC covering 2026/27 to 2028/29, with resulting levy rates to be applied to electricity suppliers. The consultation seeks views on administrative costs for running CfD and capacity market settlement functions. Costs are recovered through levies on licensed electricity suppliers who pass them to consumers.
DESNZ proposes policy actions to maintain gas system security during energy transition, including infrastructure capacity requirements, resilience measures, and commercial model changes for LNG terminals, interconnectors, and storage. The consultation covers maintaining peak-day capacity and ensuring infrastructure remains commercially viable as gas demand declines. This follows the June 2025 commitment to public engagement on gas system transition.
DESNZ reviews the 2011 CO2 storage infrastructure access regulations to support CCUS market development. The consultation examines whether third-party access rules need updating to reflect current policy and support first-of-a-kind CCUS projects. This follows government commitments to establish industrial carbon capture clusters.
DESNZ proposes moving Warm Home Discount cost recovery from standing charges to unit rates (per-kWh charges) for electricity and gas. The consultation seeks views on impacts for consumers and suppliers, requiring changes to WHD reconciliation regulations. No financial figures or timeline details are provided in the summary.
DESNZ proposes to extend CE marking recognition to products regulated under the EU's new Ecodesign for Sustainable Products Regulation (ESPR), which replaces the Ecodesign Directive from mid-2027. This maintains the current system where EU-certified products can be sold in GB without additional UK conformity assessment.
DESNZ is reviewing three nuclear installation regulations from 2017-2018 that govern prescribed sites, insurance certificates, and excepted matters. The post-implementation review seeks feedback on whether the regulations meet objectives and if less onerous alternatives exist. This is routine regulatory review, not policy change.
DESNZ consults on reforming Energy Performance Certificates through a new Home Energy Model methodology, expanding calculations to include on-site inspections and introducing four new headline metrics: Fabric Performance, Heating System, Smart Readiness and Energy Cost. The consultation seeks views on how these metrics should be calculated and translated into EPC scoring bands.
DESNZ launches a call for evidence on the downstream oil sector to inform an upcoming strategy. The consultation seeks stakeholder views on how refineries, fuel distribution, and retail petrol stations can adapt to the changing energy landscape. No specific proposals or timeframes are provided.
Ofgem publishes final guidance on heat network consumer protections, covering complaints handling, billing transparency, and protections for vulnerable consumers. The guidance takes effect from regulatory commencement on 27 January 2026. Heat network suppliers and operators must now comply with standards similar to gas and electricity retail regulation.
MHCLG introduces four headline metrics for domestic EPCs (fabric performance, heating system, smart readiness, energy cost) replacing the single Energy Efficiency Rating from October 2026. Non-domestic EPCs retain the single carbon-based Environmental Impact Rating. EPCs will be required before marketing properties and for HMOs letting single rooms, with heritage exemptions removed.
Ofgem published five consultations in late February 2026 updating the data reporting rules and load-related spending triggers for the current electricity and gas price controls.
4 related publications from Ofgem. We are seeking input on whether we should consider making changes to the contract for difference allowance methodology in the default tariff cap.
4 related publications from Ofgem. This consultation seeks views on proposed changes to the Regulatory Instructions and Guidance (RIGs) RIIO-2 Year 2 for Electricity Distribution.
Five routine Ofgem decisions and one consultation covering gas transmission asset health, offshore wind transmission costs, gas exit capacity, and onshore electricity transmission competition.
DESNZ: DESNZ and Ofgem consult on consumer protection regulations for heat networks, implementing powers from the Energy Act 2023. The consultation focuses on finalising proposals for a second statutory instrument due in 2025. This follows CMA's 2018 recommendation to regulate the sector. Ofgem: Ofgem confirms operator-led registration for heat networks from spring 2026, with quarterly data reporting for pricing and vulnerability metrics. Networks with deemed authorisation must register by January 2027, after which new activity requires prior application. The regulator simplifies change notification requirements and confirms risk-based audits will focus initially on registration declarations.
DESNZ: DESNZ proposes rule changes to prevent emissions verification deadlines from reducing Capacity Market auction liquidity. The changes include conditional deadline extensions for generators required to submit verified emissions declarations at prequalification. This addresses administrative bottlenecks that could force viable capacity out of auctions due to paperwork delays rather than economic merit. Ofgem: Ofgem approves revisions to the Relevant Balancing Services Guidelines proposed by the Capacity Market Delivery Body for 2024. The decision letter outlines which specific changes have been accepted to the technical guidelines that determine which balancing services are relevant for capacity market participation.