Denny to Wishaw 400kV Reinforcement Project: Early Construction Funding

OFGEM·consultation·medium·17 Mar 2026·source document

This consultation is open for responses

Closes 15 Apr 2026 (10 days remaining)

Summary

Ofgem is consulting on Early Construction Funding for Scottish Power Transmission's Denny to Wishaw 400kV reinforcement project under the ASTI re-opener mechanism. The consultation closes 15 April 2026 with responses to be submitted to transmission.acceleration@ofgem.gov.uk. This follows SPT's application for accelerated funding to begin construction ahead of the normal RIIO price control cycle.

Why it matters

Early Construction Funding allows transmission owners to recover costs before projects are formally included in price controls, transferring construction risk from developers to consumers earlier than usual. This mechanism favours incumbents by providing capital certainty while socialising pre-construction risks that would otherwise sit with network companies.

Key facts

  • Consultation period: 17 March 2026 to 15 April 2026
  • Project: Denny to Wishaw 400kV reinforcement
  • Mechanism: ASTI re-opener Early Construction Funding
  • Applicant: Scottish Power Transmission

Timeline

Consultation closes15 Apr 2026

Areas affected

transmissionnetwork charges

Related programmes

RIIO-ET3

Memo

What this is about

Scottish Power Transmission has applied for Early Construction Funding to start building the Denny to Wishaw 400kV reinforcement project ahead of the normal RIIO price control cycle. This consultation presents Ofgem's minded-to position on whether to approve funding through the ASTI re-opener mechanism.

The project involves upgrading transmission infrastructure between Denny and Wishaw substations in central Scotland. SPT is seeking to begin construction now rather than waiting for the next price control period, arguing this will accelerate delivery of critical grid reinforcement needed for net zero. Under Early Construction Funding, consumers would start paying for the project through transmission charges before it formally enters the regulated asset base, effectively transferring construction risk from SPT to network users earlier than usual.

Options on the table

The consultation presents Ofgem's preliminary assessment rather than distinct policy options. However, the fundamental choice is binary:

Approve Early Construction Funding

Under this approach, SPT would receive regulatory approval and funding certainty to begin construction immediately. The company would recover costs through transmission charges as the project progresses, with consumers bearing construction risks including potential cost overruns or delays. This accelerates project delivery but removes the normal discipline of competitive price control processes where projects compete for inclusion based on demonstrated need and efficient costs. Network users pay earlier and potentially more, while SPT gains capital certainty and reduced commercial risk.

Reject Early Construction Funding

The alternative is requiring SPT to wait for the standard RIIO process where the project would compete alongside other investments for inclusion in the next price control. This maintains normal regulatory discipline around need demonstration and cost efficiency, with construction risk remaining with the transmission owner. However, it delays project delivery which could constrain renewable energy connections and net zero progress. SPT would bear full construction risk and funding uncertainty, while consumers pay later but potentially face higher system costs from delayed grid reinforcement.

Questions being asked

The consultation document is not fully accessible from the provided text, but based on the description, questions likely focus on:

Project justification and timing

Questions around whether the Denny to Wishaw reinforcement represents critical infrastructure that justifies bypassing normal price control processes, and whether the proposed timing aligns with genuine system needs rather than commercial convenience for SPT.

Cost efficiency and risk allocation

Assessment of whether SPT's cost estimates are reasonable and efficiently derived, and whether the proposed risk allocation between company and consumers represents appropriate value compared to standard regulatory arrangements.

Process and precedent implications

Evaluation of how approving this application might affect future ASTI applications and whether the Early Construction Funding mechanism is being applied consistently with its original policy intent of enabling genuinely strategic transmission investments.

How to respond

Submit responses by 15 April 2026 by emailing transmission.acceleration@ofgem.gov.uk. Ofgem particularly welcomes views from consumer groups, stakeholders impacted by the project, those with interests in transmission infrastructure costs, and transmission owners. Responses from other stakeholders and the public are also welcome.

The consultation seeks input from anyone interested in new transmission infrastructure, meeting net zero challenges, and competition in onshore transmission networks. After the consultation closes, Ofgem will consider all responses before making its final decision on SPT's Early Construction Funding application.

Source text

[](#main-content) Please enable JavaScript in your web browser to get the best experience. BETA This site is currently in BETA. Help us improve [by giving us your feedback](/node/177776). Close alert: [![Ofgem](/themes/custom/numiko/logo.svg)](/ "Home") Open menu ## Main navigation * About us Go back [About us](/about-us) [About us](/about-us) + Who we are Go back Who we are - [Our leadership](/about-us/who-we-are/our-leadership) - [Our strategy](/about-us/who-we-are/our-strategy) - [What we regulate](/about-us/who-we-are/what-we-regulate) + How we work Go back How we work - [Finances](/about-us/how-we-work/finances) - [Policies and procedures](/about-us/how-we-work/policies-and-procedures) - [Procurement and contract opportunities](/about-us/how-we-work/procurement-and-contract-opportunities) + Join Ofgem Go back Join Ofgem - [Work with Ofgem](/about-us/join-ofgem/work-ofgem) - [Application and recruitment FAQs](/about-us/join-ofgem/application-and-recruitment-faqs) - [Terms and conditions of employment](/about-us/join-ofgem/terms-and-conditions-employment) - [Pay and benefits](/about-us/join-ofgem/pay-and-benefits) - [Staff networks](/about-us/join-ofgem/staff-networks) - [Equality and diversity](/about-us/join-ofgem/equality-and-diversity) + Get in touch Go back Get in touch - [Contact us](/about-us/get-in-touch/contact-us) - [Environmental and social scheme contacts](/about-us/get-in-touch/environmental-and-social-scheme-contacts) - [Information requests](/about-us/get-in-touch/information-requests) - [Media enquiries](/about-us/get-in-touch/media-enquiries) - [Complaining about Ofgem](/about-us/get-in-touch/complaining-about-ofgem) * Information for consumers Go back [Information for consumers](/information-consumers) [Information for consumers](/information-consumers) + Energy advice for households Go back Energy advice for households - [Find your energy supplier](/finding-your-energy-supplier-or-network-operator) - [Compensation for energy supply issues](/check-compensation-rules-power-cut-or-supply-problem) - [Complain about your energy supplier](/information-consumers/energy-advice-households/complain-about-your-energy-supplier) - [Connect to gas or electricity](/information-consumers/energy-advice-households/getting-gas-or-electricity-connection) - [Switch energy supplier](/information-consumers/energy-advice-households/switch-energy-supplier) - [Replacing your Radio Teleswitch electricity meter](/information-consumers/energy-advice-households/replacing-your-radio-teleswitch-electricity-meter) - [Get a smart meter](/getting-smart-meter) - [Prepayment meters consumer guidance](/prepayment-meters-consumer-guidance) - [Get energy price cap standing charges and unit rates by region](/information-consumers/energy-advice-households/get-energy-price-cap-standing-charges-and-unit-rates-region) - [Energy price cap explained](/information-consumers/energy-advice-households/energy-price-cap-explained) - [Standing charge for electricity and gas](/information-consumers/energy-advice-households/standing-charge-electricity-and-gas) - [What to do if you get a back bill](/information-consumers/energy-advice-households/what-do-if-you-get-back-bill) - [Join your supplier’s Priority Services Register](/information-consumers/energy-advice-households/join-your-suppliers-priority-services-register) - [Plan for a power cut](/information-consumers/energy-advice-households/plan-power-cut) - [What happens if the energy supplier to your business goes bust?](/information-consumers/energy-advice-businesses/what-happens-if-energy-supplier-your-business-goes-bust) - [Economy 7 consumer guide](/information-consumers/energy-advice-households/economy-7-consumer-guide) - [Get help with your energy bills](/information-consumers/energy-advice-households/get-help-with-your-energy-bills) - [Understand your electricity and gas bills](/understand-your-electricity-and-gas-bills) + Energy advice for businesses Go back Energy advice for businesses - [Set up a business energy contract](/information-consumers/energy-advice-businesses/set-business-energy-contract) - [Find business energy efficiency grants and schemes](/information-consumers/energy-advice-businesses/find-business-energy-efficiency-grants-and-schemes) - [Get energy for your business](/information-consumers/energy-advice-businesses/get-energy-your-business) * Environmental and social schemes Go back [Environmental and social schemes](/environmental-and-social-schemes) [Environmental and social schemes](/environmental-and-social-schemes) + [Boiler Upgrade Scheme (BUS)](/environmental-and-social-schemes/boiler-upgrade-scheme-bus) + [Counter fraud for environmental and social programmes](/environmental-and-social-schemes/counter-fraud-environmental-and-social-programmes) + [Domestic Renewable Heat Incentive (Domestic RHI)](/environmental-and-social-schemes/domestic-renewable-heat-incentive-domestic-rhi) + [Energy Company Obligation (ECO)](/environmental-and-social-schemes/energy-company-obligation-eco) + [Feed-in Tariffs (FIT)](/environmental-and-social-schemes/feed-tariffs-fit) + [Great British Insulation Scheme](/environmental-and-social-schemes/great-british-insulation-scheme) + [Green Gas Support Scheme (GGSS) and Green Gas Levy (GGL)](/environmental-and-social-schemes/green-gas-support-scheme-and-green-gas-levy) + [Non-Domestic Renewable Heat Incentive (RHI)](/environmental-and-social-schemes/non-domestic-renewable-heat-incentive-rhi) + [Northern Ireland Non-Domestic Renewable Heat Incentive](/about-northern-ireland-non-domestic-renewable-heat-incentive) + [Offtaker of Last Resort (OLR)](/environmental-and-social-schemes/offtaker-last-resort-olr) + [Renewable Electricity Register](/environmental-programmes/renewable-electricity-register) + [Renewables Energy Guarantees Origin (REGO)](/environmental-and-social-schemes/renewable-energy-guarantees-origin-rego) + [Renewables Obligation (RO)](/environmental-and-social-schemes/renewables-obligation-ro) + [Smart Export Guarantee (SEG)](/environmental-and-social-schemes/smart-export-guarantee-seg) + [Warm Home Discount (WHD)](/environmental-and-social-schemes/warm-home-discount-whd) + [Previous Environmental and Social Schemes](/environmental-and-social-schemes/previous-environmental-and-social-schemes) * Energy regulation Go back [Energy regulation](/energy-regulation) [Energy regulation](/energy-regulation) + How we regulate Go back How we regulate - [Energy licences and guidance](/energy-regulation/how-we-regulate/energy-licences-and-guidance) - [Energy codes](/energy-regulation/how-we-regulate/energy-codes) - [Compliance and enforcement](/energy-regulation/how-we-regulate/compliance-and-enforcement) - [Energy network price controls](/energy-regulation/how-we-regulate/energy-network-price-controls) + Electricity Go back Electricity - [Electricity supply](/energy-regulation/electricity/electricity-supply) - [Electricity interconnectors](/energy-regulation/electricity/electricity-interconnectors) - [Electricity generation](/energy-regulation/electricity/electricity-generation) - [Electricity distribution](/energy-regulation/electricity/electricity-distribution) - [Electricity transmission](/energy-regulation/electricity/electricity-transmission) - [Offshore electricity transmission](/energy-regulation/electricity/offshore-electricity-transmission) + Gas Go back Gas - [Gas supply](/energy-regulation/gas/gas-supply) - [Gas interconnectors](/energy-regulation/gas/gas-interconnectors) - [Gas shipping](/energy-regulation/gas/gas-shipping) - [Gas transmission](/energy-regulation/gas/gas-transmission) - [Gas distribution](/energy-regulation/gas/gas-distribution) + Low carbon Go back Low carbon - [Carbon capture and storage](/energy-regulation/low-carbon/carbon-capture-and-storage) - [Heat networks](/energy-regulation/low-carbon/heat-networks) - [Nuclear energy](/energy-regulation/low-carbon/nuclear-energy) - [Long duration electricity storage](/energy-regulation/low-carbon/long-duration-electricity-storage) + Technology and innovation Go back Technology and innovation - [Artificial intelligence](/energy-regulation/technology-and-innovation/artificial-intelligence) - [Cybersecurity](/energy-regulation/technology-and-innovation/cybersecurity) - [Digitalisation](/energy-regulation/technology-and-innovation/digitalisation) - [Innovation](/energy-regulation/technology-and-innovation/innovation) + Business resilience Go back Business resilience - [Financial resilience](/energy-regulation/business-resilience/financial-resilience) - [Security of supply](/energy-regulation/business-resilience/security-supply) + Domestic and non-domestic Go back Domestic and non-domestic - [Energy pricing rules](/energy-regulation/domestic-and-non-domestic/energy-pricing-rules) - [Consumer protection](/energy-regulation/domestic-and-non-domestic/consumer-protection) - [Non-domestic energy supply](/energy-regulation/domestic-and-non-domestic/non-domestic-energy-supply) - [Metering](/energy-regulation/domestic-and-non-domestic/metering) + Markets and investment Go back Markets and investment - [Energy trading](/energy-regulation/markets-and-investment/energy-trading) - [Investor relations](/energy-regulation/markets-and-investment/investor-relations) * Consultations Go back [Consultations](/consultations) [Consultations](/consultations) + [Consultations and calls for input](/consultations/consultations-and-calls-input) + [How we consult](/consultations/how-we-consult) * News and insight Go back [News and insight](/news-and-insight) [News and insight](/news-and-insight) + [News](/news-and-insight/news) + [Blog](/news-and-insight/blog) + [Press releases](/news-and-insight/press-releases) + [Speeches](/news-and-insight/speeches) + [Research](/news-and-insight/research) + [Data](/news-and-insight/data) Search Please enter a search term Submit search query Please enter a search term Submit search query # Denny to Wishaw 400kV Reinforcement Project: Early Construction Funding Publication type: : Consultation Publication date: : 17 March 2026 Closing date: : 15 April 2026 Status: : Open Topic: : Electricity transmission Subtopic: : Accelerated Strategic Transmission Investment (ASTI) Get emails about this page [Print this page](/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) ### Share the page * [Share on Facebook](http://www.facebook.com/share.php?u=https://www.ofgem.gov.uk/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) * [Share on Twitter](https://twitter.com/intent/tweet?text=Denny%20to%20Wishaw%20400kV%20Reinforcement%20Project%3A%20Early%20Construction%20Funding&url=https://www.ofgem.gov.uk/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) * [Share on LinkedIn](https://www.linkedin.com/shareArticle?mini=true&url=https://www.ofgem.gov.uk/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) Our minded-to position on the Early Construction Funding application submitted by Scottish Power Transmission Plc for the Denny to Wishaw 400kV Reinforcement Project ## Consultation description This consultation sets out our Early Construction Funding assessment of Scottish Power Transmission Plc's (SPT’s) Early Construction Funding (ECF) application for the Denny to Wishaw 400kV Reinforcement Project (DWNO) under the Accelerated Strategic Transmission Investment (ASTI) re-opener. This document outlines the scope, purpose, and questions of the consultation and how you can get involved. Once the consultation is closed, we will consider all responses. ## Who should respond We would like views from people with an interest in new transmission infrastructure, meeting the net zero challenge, and competition in onshore transmission networks. We particularly welcome responses from consumer groups, stakeholders impacted by the projects, stakeholders with an interest in the costs of electricity transmission infrastructure, and transmission owners. We would also welcome responses from other stakeholders and the public. ## How to respond Submit your response by 15 April 2026 by emailing transmission.acceleration@ofgem.gov.uk. ## Consultation documents [Denny to Wishaw 400kV Reinforcement Project (DWNO) [PDF, 300.13KB]](/sites/default/files/2026-03/DWNO-ECF.pdf) Get emails about this page [Print this page](/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) ### Share the page * [Share on Facebook](http://www.facebook.com/share.php?u=https://www.ofgem.gov.uk/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) * [Share on Twitter](https://twitter.com/intent/tweet?text=Denny%20to%20Wishaw%20400kV%20Reinforcement%20Project%3A%20Early%20Construction%20Funding&url=https://www.ofgem.gov.uk/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) * [Share on LinkedIn](https://www.linkedin.com/shareArticle?mini=true&url=https://www.ofgem.gov.uk/consultation/denny-wishaw-400kv-reinforcement-project-early-construction-funding) Close Notify me Would you like to be kept up to date with *Denny to Wishaw 400kV Reinforcement Project: Early Construction Funding*? subscribe to notifications: Email [![](/themes/custom/numiko/logo.svg)](/ "Home") ### Subscribe to receive our latest news and communications [Subscribe now](https://email.ofgem.gov.uk/p/1QCB-1GX5/subscribe) ## Contact us * [Contact us](/about-us/get-in-touch/contact-us) * [Publications](/publications) * [Schemes register](/log-your-scheme-register) * [Electronic public register](https://epr.ofgem.gov.uk/) ## Other * [Cookies](/cookies) * [Ofgem privacy policy](/ofgem-privacy-policy) * [Website accessibility](/website-accessibility) * [© Ofgem 2026](/c-ofgem-2026) Follow us * [X](https://x.com/ofgem) * [LinkedIn](https://www.linkedin.com/company/ofgem) * [Facebook](https://www.facebook.com/ofgem) Close