NESOOFGEMDESNZ

System Operator Transmission Owner Code

All modifications to the System Operator Transmission Owner Code, tracked through their lifecycle. Administered by NESO.

How STC modifications work

The System Operator Transmission Owner Code (STC) governs the relationship between the System Operator (NESO) and the three Transmission Owners: National Grid Electricity Transmission, SP Transmission, and SSEN Transmission. It covers planning, construction, operation, and maintenance of the GB transmission system, including data exchange, outage planning, and the coordination of investment.

The modification process

The STC has two types of modification. Connection Modifications (CM) change the main body of the code. Procedure Modifications (PM) change the associated STC Procedures, which contain the detailed operational and planning processes. Both follow a similar governance route: a proposal is raised, assessed by a Workgroup or Amendment Panel, consulted on, and then decided by Ofgem or (for Self-Governance modifications) by the STC Amendment Panel.

Key concepts

  • CM vs PM: Connection Modifications change the code itself. Procedure Modifications change the supporting STC Procedures. PMs are typically more operational and technical in nature.
  • Self-Governance applies when a modification will not materially affect consumers, competition, or existing contractual arrangements. The Amendment Panel decides; parties can appeal.
  • Cross-code impact means the modification affects other industry codes (Grid Code, CUSC, BSC). When this happens, the codes must be changed in coordination.
87 shown
GovernanceStageRaised
NAcurrent9 Feb 2026
PM0153PM0153: System Access Reform. Emergency Return to Service (ERTS): Profiling Review.
also affects NA
NAcurrent9 Feb 2026
PM0154PM0154: STCP16: System Access Reform. Investment Planning Process - Data on Constraint Costs.
also affects NA
NAcurrent9 Jan 2026
PM0152STCP Legal Text Rectifications January 2026
also affects NA
NAImplemented15 Oct 2025
PM0151Introducing Competitively Appointed Transmission Owners to TO Lists on all Definitions
also affects N/A
Standardworkgroup nominations14 Oct 2025
CM0105Standardisation of Power Flow Metering Polarity
also affects GC0182
Self-Governance (direct)appeals window3 Oct 2025
CM0104Due Date for Monthly Payments to Transmission Operators (TOs)
also affects BSC / PM0150
NAImplemented3 Oct 2025
PM0150Due Date for Monthly Payments to Transmission Owners (TOs)
also affects CM0104
NAImplemented11 Sept 2025
PM0149Reconciliation – Change to STCP 19-2
also affects CUSC Section 2 2.14.3 (c)
NAapproved pending implementation5 Sept 2025
PM0148STCP Consequential Modification for CMP447: Removal of designated strategic works from cancellation charges/securitisation
also affects CMP447
Self-Governancepending implememtation6 Aug 2025
CM0103STC Consequential Modification for CMP447 (Follow on Modification to CMP428)
also affects CMP447
Fast TrackImplemented2 Jul 2025
CM0102Recificaiton to implementaion of varoius legal text
also affects NA
NAon hold until gc0168 have completed a solution6 May 2025
PM0147RMS and EMT Model Sharing Process (STC 122 issues 01)
also affects STC097/GC0168
Self-GovernanceImplemented11 Feb 2025
CM0101Additional Definitions in Relation to PM0144
NAImplemented3 Dec 2024
PM0144Digital Communication System Integration
also affects NA
NAWithdrawn3 Dec 2024
PM0145Digital Communication System Integration
also affects NA
NAImplemented25 Sept 2024
PM0141Incorporating a revised outage change code list in STCP 11.2 Appendix 5
also affects NA
Self-GovernanceImplemented1 Jul 2024
CM0100Consequential modification following the approval and implementation of CUSC modification – CMP428 User Commitment liabilities for Onshore Transmission (reinforcement) in the Holistic Network Design
also affects NA
Fast TrackImplemented1 Jun 2024
CM099Removing references to “Fax” and “Facsimile” within the STC
also affects Grid Code/CUSC
Standard (direct)Implemented9 May 2024
CM098Updating STC Arrangements to replacing the Electricity Arbitration Association with the London Court of International Arbitration
also affects NA
NAImplemented7 May 2024
PM0140Housekeeping changes following the implementation of PM0135
also affects NA
StandardWorkgroup3 May 2024
CM097Electromagnetic Transient (EMT) Root Mean Square (RMS) Model Submission for Transmission Owners (TOs)
Open pagealso affects GC0168
Urgentmodification withdrawn19 Apr 2024
CM096Application of Gate 2 Criteria to existing contracted background
also affects CUSC CMP435
NAImplemented6 Feb 2024
PM0142Application of Gate 2 Criteria to existing contracted background
also affects CMP435
NAImplemented6 Feb 2024
PM0143Implementing Connection Reform
also affects CMP435, CMP434
NAImplemented21 Jan 2024
PM0146Emergency Control Centre Requirements
also affects NA
NAImplemented2 Dec 2023
PM0136Introducing Connections process to facilitate Competitively Appointed Transmission Owners
also affects NA
NAImplemented1 Dec 2023
PM0134Introducing Competitively Appointed Transmission Owners & Transmission Service Providers
also affects NA
StandardWorkgroup21 Nov 2023
CM093Extending the principles of the User Commitment Methodology to Final Sums Methodology as a consequence of CUSC Modification – CMP417
Open pagealso affects CUSC CMP417
NAawaiting panel approval13 Jun 2023
PM0133Network Services Feasibility Studies
N/AWithdrawn9 Aug 2022
PM0127Improving TNUoS Predictability through increased Notice of the Target Revenue & Inputs used in the TNUoS Tariff Setting Process
also affects CUSC (CMP286/287)
N/AImplemented17 May 2022
PM0126CUSC Modification 'Transmission Impact Assessment Process'
also affects CUSC CMP298
N/Asent back from authority14 Mar 2022
PM0124CUSC Modification 'Enduring Expansion Constant and Factor Review'
also affects CUSC (CMP315/375)
Standardsent back from authority4 Oct 2021
CM079Consideration of STC/STCP changes in relation to CMP330/374
also affects CUSC (CMP330/CMP374)
N/Aawaiting new proposer13 Sept 2021
PM0120CUSC Modification 'CMP328 - Connection Triggering Distribution Impact Assessment'
also affects CUSC (CMP328)
Standard (direct)awaiting new proposer15 Mar 2021
CM078CUSC Modification 'CMP328 - Connection Triggering Distribution Impact Assessment'
also affects CUSC (CMP328)
Implemented
CM063Implemented
Implemented
CM065Implemented
Implemented
CM066Implemented
Implemented
CM067Implemented
Implemented
CM068Implemented
Implemented
CM069Implemented
Implemented
CM071N/A
Implemented
CM073Implemented
Implemented
CM072Withdrawn
Implemented
CM074Withdrawn
Implemented
CM075Implemented
Implemented
CM076Implemented
Implemented
CM077Implemented
Implemented
CM080Implemented
Implemented
CM081Implemented 1 July 2022
Implemented
CM083Implemented 19 October 2022
Implemented
CM084Implemented 14 February 2023
Implemented
CM085Implemented on 15 November 2024
Implemented
CM086Implemented on 08 April 2025
Implemented
CM087Implemented on 08 April 2025
Implemented
CM0882023-06-23 00:00:00
Implemented
CM089Implemented 25 April 2023
Implemented
CM090Implemented 25 April 2023
Implemented
CM091Implementation 04/03/2024
Implemented
CM0922023-12-01 00:00:00
Implemented
CM094Authority decision received 11 June 2024 confirming the rejection of this modification.
Implemented
CM095Implemented on 10 June 2025.
Implemented
PM0102Implemented
Implemented
PM0103Implemented
Implemented
PM0104Implemented
Implemented
PM0105Implemented
Implemented
PM0106Implemented
Implemented
PM0112Implemented
Implemented
PM0114Implemented
Implemented
PM0113Implemented
Implemented
PM0115Implemented
Implemented
PM0116Implemented
Implemented
PM0117Implemented
Implemented
PM0118Implemented
Implemented
PM0121Implemented
Implemented
PM0122Implemented
Implemented
PM0123Implemented
Implemented
PM0125Implemented
Implemented
PM0128Implemented
Implemented
PM0130Implemented
Implemented
PM0129Implemented
Implemented
PM0131Implemented
Implemented
PM0132Implemented
Implemented
PM0135Implemented
Implemented
PM0137Implemented
Implemented
PM0138Implemented
Implemented
PM0139Implemented