Generators
CfD, Capacity Market, RO, FiT
Four overlapping mechanisms support electricity generation in Great Britain: Contracts for Difference, the Capacity Market, the Renewables Obligation, and Feed-in Tariffs. Each has its own contract structure, settlement process, and dataset. The briefing below traces how they evolved from privatisation in 1990 to the present. The data pages provide interactive charts and registers for each scheme.
▶Data by scheme
▶Briefing28 Mar 2026
In one line
Four overlapping support mechanisms (CfDs, Capacity Market, Renewables Obligation, Feed-in Tariffs) now sit on top of a wholesale market that was designed to work without them, and over half of GB generation by 2030 will operate under administrative contracts rather than market prices.
The state monopoly
The Central Electricity Generating Board owned and operated all generation and transmission in England and Wales from 1958 to 1990. Scotland had two separate boards. The system built the nuclear fleet, the coal stations, and the 400kV supergrid. It did not discover prices. The Electricity Act 1989 broke the CEGB into National Power (30 GW), PowerGen (18 GW), Nuclear Electric, and the National Grid Company. Twelve regional electricity companies took over distribution and supply. Scotland privatised separately in 1991, keeping vertically integrated companies rather than splitting generation from supply.
The Pool and its failure
From April 1990, all generators in England and Wales sold through a mandatory gross pool. Every generator received the same price in each half-hour period, set by the most expensive unit needed. National Power and PowerGen controlled over 80% of price-setting plant. A uniform-price auction with two dominant sellers is an invitation to exercise market power, and wholesale prices rose roughly 50% in the Pool's first four years. Generators could also withdraw plant to inflate capacity payments. The regulator forced plant divestitures throughout the 1990s, but the design flaw was structural.
Bilateral trading
The New Electricity Trading Arrangements (NETA) replaced the Pool in March 2001, shifting from centralised dispatch to bilateral contracts. Generators and suppliers traded freely through forwards, futures, and power exchanges. Parties whose output differed from contract paid imbalance charges. BETTA extended these arrangements to Scotland in April 2005, creating a single GB wholesale market with a national price. Locational signals were provided through network charges (TNUoS/DUoS) rather than the energy price.
Renewables Obligation (2002-2017)
The RO placed a legal obligation on suppliers to source a rising share of electricity from renewables. Generators received Renewables Obligation Certificates (ROCs) per MWh produced. Suppliers who fell short paid into a buy-out fund (initially around 30/MWh), which was recycled back to ROC holders. All technologies received 1 ROC per MWh until banding was introduced in 2009: offshore wind received 2 ROCs, onshore wind 1, landfill gas 0.25. The RO closed to new capacity between 2015 and 2017 depending on technology. Existing stations continue receiving ROCs for their full 20-year term, so the obligation pays out into the 2030s. Total issuance to date: 4.7 billion ROCs.
Feed-in Tariffs (2010-2019)
FiTs targeted small-scale generation up to 5 MW, principally rooftop solar. The initial tariff for sub-4kW solar was 41.3p/kWh, guaranteed for 25 years. Installations grew from 24,000 in early 2011 to over 838,000 by end of 2015. Tariffs fell over 90% through quarterly degression to 4.01p/kWh by the time the scheme closed in March 2019. Over 870,000 installations now receive guaranteed payments. The Smart Export Guarantee replaced it with market-based export rates.
Contracts for Difference (2014-present)
CfDs are the centrepiece of the Energy Act 2013. A generator receives (or pays back) the difference between an administrative strike price and a market reference price. When wholesale is below the strike, consumers top up. When above, the generator pays back. The LCCC administers the contracts. The first was Hinkley Point C, agreed bilaterally at 92.50/MWh (2012 prices) for 35 years. Competitive allocation rounds began in 2015. Offshore wind strike prices fell from 114-120/MWh in AR1 (2015) to 57.50 in AR2 (2017) to 37.35 in AR4 (2022). AR5 (2023) received zero offshore wind bids after supply chain inflation pushed viable prices above the 44/MWh cap. AR6 cleared at 58.87. AR7 (January 2026) awarded 8.4 GW at 90.91/MWh in 2024 prices, the largest European offshore wind auction. 612 contracts are now in the CfD portfolio.
Capacity Market (2014-present)
The Capacity Market ensures firm capacity as intermittent renewables grow. Providers bid in descending-clock auctions to be available during system stress, receiving a fixed payment per kW per year. The first T-4 auction (December 2014) procured 49.3 GW at 19.40/kW. The scheme was suspended for eleven months in 2018-19 after the EU General Court annulled its state aid approval following a challenge by Tempus Energy, a demand-side response provider. The European Commission re-approved it in October 2019. Annual cost is now around 1.3 billion, projected to reach 4 billion by end of the decade.
The carbon price that closed coal
The Carbon Price Support, introduced in April 2013, created a UK-only tax on fossil fuels used for power generation. The rate rose from 4.94/tCO2 to 18.08/tCO2 by 2015/16, then was capped at 18/tCO2. Coal's share of GB generation fell from roughly 40% in 2012 to under 2% by 2019. Ratcliffe-on-Soar, the last coal station, closed on 30 September 2024. The CPS achieved this through a Pigouvian tax that made the externality visible in the marginal cost of generation, not through subsidy or mandate.
Where this stands
The GB generator support framework now has four overlapping layers: residual RO payments, closed FiT obligations, active CfD allocation rounds, and annual Capacity Market auctions. Over half of GB generation by 2030 will operate under administrative contracts rather than a market price. The wholesale market is becoming a residual balancing mechanism rather than the primary venue for price discovery. The REMA process (2022-2025) rejected zonal and nodal pricing in favour of Reformed National Pricing with sharper locational signals through network charges. Whether administered contracts can coordinate investment and dispatch as effectively as a functioning price signal remains the central question for the next decade of GB electricity.
▶Timeline
▶Open consultations (14)
Ofgem consults on 13 Capacity Market rule change proposals (CP382-CP394). Proposals cover Independent Technical Expert definitions, termination reasons, load-following obligation calculations, metering test processes, and other operational rules. Consultation closes 24 May 2026.
Ofgem sets out five options for redesigning transmission network charges to steer investment towards Strategic Spatial Energy Plan locations, ranging from tweaking existing TNUoS to auctioning connection capacity by zone. Charges would apply to new generators, demand, and storage. Responses by 26 May 2026, reforms targeted for 2029.
STC modification CM097 mandates Transmission Owners to submit EMT and RMS models of their assets to NESO, enabling system-wide dynamic modelling as inverter-based resources replace synchronous generation. The workgroup unanimously supported the original solution. Implementation aligns with Grid Code modification GC0168.
Ofgem consults on the second preliminary Strategic Direction Statement, which sets binding priorities for how GB industry codes must develop under the Energy Act 2023 governance reforms. The SDS categorises policy areas requiring code changes and proposes converting from a preliminary to a hybrid document once BSC and REC are designated by end-2026. Responses due 28 May 2026.
DESNZ seeks evidence on nuclear third party liability limits for Small Modular Reactors and Advanced Modular Reactors, which by default face the same €1.2bn liability requirement as gigawatt-scale plants by 2027. The consultation runs until 1 June 2026 and covers both electricity-generating SMRs and non-electric applications like hydrogen production or industrial heat. Current liability arrangements require operators to secure insurance cover up to their liability limit, with lower limits available only for prescribed lower-risk sites.
DESNZ consults on siting and investment levers under Reformed National Pricing (RNP), the programme that replaces REMA after ministers rejected zonal pricing. Closes 2 June 2026. Ofgem runs a parallel Call for Input on network and connections charging to 26 May. Together these set how much new generation and storage pay, and where.
The RNP Delivery Plan landing page. Frames the 21 April DESNZ consultation and confirms REMA is closed. Substantive response window is the companion siting-and-investment consultation.
DESNZ proposes to simplify UK ETS permitting for cross-boundary CCS pipelines by reducing the number of permits required from multiple regulators to a maximum of two. Current rules require separate permits from each jurisdiction a pipeline crosses (England, Scotland, Wales, Northern Ireland, and offshore), plus monitoring infrastructure at each boundary. The consultation runs until 4 June 2026.
GC0168 would require legacy generators (completion before 1 September 2022) to provide Electromagnetic Transient models to NESO on request, enabling analysis of inverter instability, system oscillations, and transient overvoltage on a grid increasingly dominated by power electronics. The workgroup's preferred alternative (WAGCM1) defers the obligation for GB Code Users until a CUSC cost recovery mechanism is in place, while applying immediately to EU Code Users. Responses due by 8 June 2026.
DESNZ proposes new permitted development rights for non-domestic wind turbines up to 30m tip height and 200m² swept area, allowing single turbines on farms, businesses and public sites without planning applications. The proposal requires prior approval from local planning authorities for siting and amenity impacts, with buffer distances of tip height plus 10% from site boundaries and ten times rotor diameter from neighbouring homes. Consultation closes 10 June 2026 with policy expected in autumn.
Ofgem proposes to allow Liverpool Bay CCS Ltd to recover costs from a Change in Scope Re-opener under its CCS transport and storage economic licence, covering the ongoing Runcorn TCPA planning application and the licensee's participation in the Cubico Frodsham Solar Project DCO examination. The submission follows DESNZ's deprioritisation of Viridor under the HyNet Track-1 Expansion. Ofgem's minded-to position adjusts the Approved Project Development Plan, Financial Settlement Document and project-specific licence schedule rather than changing the regulated revenue model itself.
Muirhall Energy has raised CMP471, a temporary CUSC amendment letting Users adjust connection dates and contract elements before the first CMP434 Gated Application Window and the 1 April 2027 liability trigger. The CUSC Panel unanimously recommended urgent treatment on 15 May 2026; if Ofgem agrees by 19 May, implementation lands 31 July 2026 instead of an undated 2027 slot. Without it, queue holders enter Gate 2 carrying contractual connection dates that no longer match deliverable programmes.
Ofgem proposes an early competition OFTO build model where transmission assets are competitively tendered before construction, rather than after. The consultation also updates the existing late competition model. Early competition would be mandatory in certain circumstances, with detailed proposals covering tender process, evaluation criteria, and commercial framework.
Ofgem is gathering evidence from gas shippers and interconnectors to assess UNC0903, which would replace the current locational NTS capacity reference prices with a single uniform price across all entry points. Separate RFIs target shippers using interconnectors (IUK/BBL), LNG terminals, and Norwegian pipelines, plus the interconnectors themselves and National Gas Transmission. The modification is subject to an Authority decision; this RFI will feed an impact assessment.
▶All publications (1204)
Ofgem's interim CEO confirms the regulator will publish its ED3 strategic decision tomorrow (21 May 2026), signalling a 'targeted' rather than anticipatory build-out: invest where demand growth is clear, lean on flexibility elsewhere. Jarvis confirms electricity transmission expenditure could reach around £70bn over five years, that the connections queue has been cut by 220 GW from 700+ GW via NESO triage, and that Ofgem will progress a Debt Relief Scheme writing off up to £400m of crisis-era domestic debt. He also flags consultation this summer on house-moves rules (where roughly a third of supplier debt accrues) and a shift toward outcomes-based retail regulation under a PACT framing (Predictable, Agile, Collaborative, Technology-enabled).
CMP477 proposes a CUSC change to allow a single connection modification request to span more than one Transmission Owner area, rather than forcing developers to raise separate applications when their works touch the boundary between TO networks. Raised by Andrew Urquhart on 19 May 2026 as an Urgent modification under an Authority-agreed timetable, status Proposal Raised. NESO classifies the impact as Medium across generators, demand customers, TOs (including CATOs) and consumers.
DESNZ announces £15.6m through the Heat Network Efficiency Scheme to upgrade 94 existing heat networks in England and Wales, plus £25m through the Green Heat Network Fund for four new projects including Bristol City Leap expansion and a sewer-heat scheme in Rochdale. Funding sits within the previously announced Warm Homes Plan envelope (£195m/yr GHNF, £15m/yr HNES to 2029/30).
DESNZ pre-announces the Energy Trends and Prices release covering March to May 2027, the monthly statistical bundle on production, trade, generation, consumption and retail prices for coal, electricity, gas and oil. This is the regular series, not a methodology change or new dataset. Content itself is not yet published; this is the scheduling notice.
DESNZ has directed under section 35 of the Planning Act 2008 that National Gas Transmission's Project Union: East Coast hydrogen pipeline be treated as a Nationally Significant Infrastructure Project requiring a Development Consent Order. The Project covers up to 420 km of new mainline hydrogen pipeline plus ~200 km of repurposed NTS pipe across Teesside, the Humber and the East Midlands, with 13 Hub Above-Ground Installations at locations from Bishop Auckland to Staythorpe. The direction was needed because the pipeline narrowly fails the s.20 NSIP threshold (under 50,000 customers), so DCO consent would otherwise not apply.
NESO has raised GC0186, a Grid Code modification updating restoration requirements following GC0156's implementation of the Electricity System Restoration Standard. The proposal introduces Regional Restoration Plans, equal treatment of NGET, SPT and SHET during restoration, requirements for Network Operators to switch at sufficient speed, and tightened testing and data obligations. Currently at Workgroup Nominations stage, governance route still to be decided by the Panel.
Ofgem has issued procedural guidance to electricity suppliers and generators with Renewable and Electricity Register accounts on how to hold REGOs for GB Fuel Mix Disclosure 2026. The letters set out the administrative process for the 2026 FMD cycle; they do not change the underlying REGO scheme rules, eligibility, or trading mechanics.
Ofgem has been appointed administrator of the government's Bill Discount Scheme, which gives households living near new electricity transmission infrastructure up to £250 per year off their bills. DESNZ aims to lay regulations in Summer 2026, with first payments in early 2027. Ofgem will consult on delivery mechanics (eligibility, compliance) for six weeks from July 2026.
Ofgem has been named scheme administrator for DESNZ's bill discount scheme, which pays households living near new or significantly upgraded electricity transmission infrastructure up to £250 per year for up to 10 years. This is an administrative appointment; the scheme itself, sitting alongside Community Funds, was already established as a community benefit package for transmission hosts. No change to the scheme parameters, eligibility, or funding mechanism.
The Secretary of State has used Energy Act 2023 section 245(1)(a) and (e) powers to insert new Standard Licence Condition 11C into the Electricity Supply Licence and a new Schedule 35 into the Retail Energy Code, mandating that electricity suppliers expose tariff and export-tariff pricing data via a standardised API. The licence condition takes legal effect on 18 February 2027; suppliers must build a compliant Tariff Interoperability API, register a Supplier Endpoint with RECCo by 31 December 2026, and meet 99.9% monthly availability with a 95th-percentile 1-second response time at steady-state volume. Smaller non-domestic-only suppliers below 100,000 meter points are exempt, as are block tariffs, current-transformer-metered sites, and bespoke charges.
Three University of Sheffield Key Knowledge Deliverables from the £1bn Net Zero Innovation Portfolio CCUS Innovation 2.0 programme, comparing a novel molten carbonate fuel cell (MCFC) approach to BECCS against conventional amine post-combustion capture, plus solvent performance data for MEA versus the CESAR1 (piperazine/AMP) blend. The reports document techno-economic baseline configurations, capture rates (~95% biomass flue gas, up to 100% on the MCFC natural gas feed), and solvent degradation/nitrosamine management. They are status-of-project knowledge documents, explicitly not final and not changing any rule, charge, or business model.
DESNZ has published Key Knowledge Deliverables from Promethean Particles' MONET project, a pilot-scale carbon capture rig using Metal Organic Framework solid sorbents, funded under the £1bn Net Zero Innovation Portfolio CCUS Innovation 2.0 programme. The released documents (D3.3 build and D4.1 installation) are factory and site acceptance test verification sheets for a prototype unit tested on Drax's flue gas stream at its CCUS Incubation Site in May 2025. The substantive deliverables (CAPEX/OPEX technoeconomic analysis, lifecycle assessment) are listed as pending release after redaction.
Muirhall Energy has raised CMP471, a temporary CUSC amendment letting Users adjust connection dates and contract elements before the first CMP434 Gated Application Window and the 1 April 2027 liability trigger. The CUSC Panel unanimously recommended urgent treatment on 15 May 2026; if Ofgem agrees by 19 May, implementation lands 31 July 2026 instead of an undated 2027 slot. Without it, queue holders enter Gate 2 carrying contractual connection dates that no longer match deliverable programmes.
NESO proposes a defined process for commissioning and funding pathfinder feasibility studies under the network services pathfinder programmes. The modification (PM0133) creates a standardised mechanism between the System Operator and Transmission Owners for scoping and procuring feasibility work, with Panel Approval as the governance route. Status remains Proposal Raised; no decision date set.
NESO has reissued STCP 11-1 (Outage Planning) as Issue 013, incorporating System Access Reform changes and a revised Emergency Return to Service (ERTS) profiling regime under modification PM0153. The procedure governs how the system operator and transmission owners (NGET, SPT, SHETL, offshore TOs, and Competitively Appointed Transmission Owners) coordinate outages from six years ahead down to day-ahead handover. The substantive change is to ERTS profiling; the rest is administrative consolidation of CATO inclusion already made in Issues 011 and 012.
NESO has raised PM0153 to revisit the criteria for recalling transmission circuits with longer Emergency Return to Service (ERTS) times during winter. The modification mandates use of a Winter Risk Policy Form to document system margins, constraints, mitigations, and recall plans, with the aim of clearing more winter outages without breaching security standards. It is self-assessed as low impact on Transmission Owners, Transmission Licensees, Generators, and System Operators, with a Panel Decision governance route.
DESNZ has refreshed its index page for local-authority and community decarbonisation support, listing existing programmes: the £19m Local Net Zero Accelerator (three pilots), the Local Net Zero Hubs, the £10m Mayoral Renewables Scheme, and the £5m Great British Energy Community Fund (continuing the 2023-25 Community Energy Fund on the same scope and eligibility). It appends a register of CEF and GBECF awards, almost all £10k-£100k grants for community solar, hydro, heat networks and feasibility studies. No new money, no rule change, no change to how generation connects or what it is paid.
Ofgem proposes to allow Liverpool Bay CCS Ltd to recover costs from a Change in Scope Re-opener under its CCS transport and storage economic licence, covering the ongoing Runcorn TCPA planning application and the licensee's participation in the Cubico Frodsham Solar Project DCO examination. The submission follows DESNZ's deprioritisation of Viridor under the HyNet Track-1 Expansion. Ofgem's minded-to position adjusts the Approved Project Development Plan, Financial Settlement Document and project-specific licence schedule rather than changing the regulated revenue model itself.
The Secretary of State granted a development consent order for North Falls, a ~1 GW offshore wind farm of up to 57 turbines roughly 40km off the East Anglia coast. Consent covers construction, operation, maintenance, and decommissioning under the Planning Act 2008. This clears the principal planning barrier for a project led by North Falls Offshore Wind Farm Limited (an SSE Renewables / RWE joint venture vehicle).
Ofgem has put market participants on notice that withholding interconnector capacity to drive extreme auction prices is non-compliant with the Electricity Regulation prohibition on capacity hoarding. The accompanying paper sets out observations on occasional price spikes in NESO interconnector auctions between 2022 and 2026 and the steps Ofgem expects traders to take to demonstrate compliance. It is a regulatory warning shot rather than a new rule, but it signals enforcement intent against specific bidding behaviour.
The Secretary of State has formally determined the standard licence conditions for code manager licences under Sections 33(1) and 81(2) of the Utilities Act 2000, completing the legal step that brings code manager licences into existence for electricity (s.6(1)(g) Electricity Act 1989) and gas (s.7AC(1) Gas Act 1986). This is the determination instrument enacting the SLCs already finalised in the March 2026 joint government-Ofgem consultation response; it adds no new policy. Code managers will replace the existing self-governance model where industry parties run their own code panels.
DESNZ published the statutory Fuel Mix Disclosure data table for the April 2024 to March 2025 period, the figures suppliers must use on customer bills under supply licence condition 21. The residual fuel mix (the pool allocated to suppliers not buying REGO-backed or sourced electricity) is 74.7% gas, 14.8% coal, 6.3% other, 3.9% nuclear and 0.3% renewables, with a carbon intensity of 919 g/kWh for coal and 382 g/kWh for gas. The headline UK supplied mix including imports is 42.1% renewables, 33.3% gas, 16.2% nuclear and 5.9% coal.
This is a release-date announcement for DESNZ's monthly solar PV deployment statistics, not the statistics themselves. The April 2026 data will be published on 28 May 2026 at 9:30am. No deployment figures, capacity numbers, or trends are contained in this page.
DESNZ proposes a second, higher price cap in the Capacity Market auction to procure new-build dispatchable enduring capacity for prolonged tight-supply periods, plus a package that reduces information given to participants before and during auctions to suppress strategic bidding. Battery CMUs would be allowed to self-nominate connection capacity below full network capacity to avoid degradation-related extended performance test failures, biogenic generation would gain a route to low-carbon CM benefits via sustainability criteria, and a Termination Fee would be introduced for currently fee-free Termination Events with payment suspension for units in Insolvency Termination Events.
DESNZ proposes Capacity Market Rule changes for the July 2026 Prequalification round, the most consequential being a route for CfD-directed Generating Units to keep CM agreements without drawing both subsidies simultaneously, plus tighter delivery assurance: a more stringent termination framework and Credit Cover held until a New Build CMU completes commissioning. It also sets CM eligibility criteria for Long Duration Electricity Storage Cap and Floor projects, clarifies Secondary Trading entrant rules, and adds a higher CapEx threshold to qualify for the second, higher price cap under the Multiple Price Capacity Market. The consultation runs ahead of Prequalification commencing July 2026 and auctions in 2027.
DESNZ is gathering evidence on how to categorise Hydrogen to Power (H2P) plants within the Capacity Market so they can bid as a new technology class, and on revising the technical adjustment used to set interconnector de-rating factors, including how high-impact low-probability events are treated. The de-rating factor directly determines how much capacity an asset can sell, so a methodology change reprices interconnector revenue. Categorisation sets the de-rating treatment and reliability assumptions H2P will be held to before any plant exists.
DESNZ has granted development consent under the Planning Act 2008 for RWE's two Dogger Bank South offshore wind farms, each up to 1.5 GW, for a combined 3 GW across up to 200 turbines. The arrays sit 100 km (West) and 122 km (East) from shore in the North Sea, with onshore export cables and converter stations connecting to the National Grid.
DESNZ and RECCo propose a new obligation in the Electricity Supplier Standard Licence Conditions and the Retail Energy Code requiring every supplier to publish tariff pricing data in a standardised, machine-readable format via a defined API. The arrangements add a TI Arrangements Schedule to the REC, redline the Standard Definition Document, and specify the data items, market messages, and API technical specification that Energy Smart Appliances will read to respond to price signals. Phase one runs through the REC and Supplier SLCs with implementation activities scheduled from post-consultation to early 2027.
Ofgem has endorsed five innovation challenges for the Strategic Innovation Fund covering RIIO-3 transmission (2026-2031) and electricity distribution (2028-2033): six-month industrial connections by 2033, 50% faster and 20% cheaper build by 2035, plug-and-play domestic device connections by 2032, near-zero outages via autonomous islanding by 2038, and decentralised local balancing by 2034. The challenges were recommended by the Energy Networks Innovation Taskforce and will be delivered through Innovation Delivery Groups and SIF-funded projects. This document sets the target framework; it does not allocate funding or change rules.
John Crane UK Limited published the closing documents from its CCUS Innovation 2.0 grant project to develop an uncooled high-temperature dry gas seal for supercritical CO2 power cycles. The work covered new simulations, material compositions, and testing validation aimed at reducing seal leakage and potentially enabling an additional turbine expansion stage. This is a component-level R&D output from a competition-funded project, not a policy or market change.
DESNZ has published the project documents from Immaterial Limited's CCUS Innovation 2.0 grant to develop monolithic metal-organic framework (MOF) adsorbents for post-combustion carbon capture. The work designed a demonstrator to strip CO2 from flue gas using structured MOF adsorbents instead of conventional amine solvents, which suffer from degradation, corrosion, and a high energy penalty. This is a materials R&D output, not a policy or market measure.
Ofgem has directed Ørsted ESS Mersey Limited to surrender its mandatory Elexon share, revoking an earlier direction issued under Standard Licence Condition 21.5 of the Generation Licence. Elexon administers the Balancing and Settlement Code; its shares carry no economic value and exist only to bind code parties into the governance structure. This is a single-licensee administrative tidy-up, typically following a generator exiting the BSC party population or ceasing licensable activity at the relevant site.
DESNZ publishes selected projects awarded funding under the Direct Air Capture and Greenhouse Gas Removal Innovation Programme. Programme supports innovation in negative-emissions technologies.
DESNZ Great British Energy framework document. Sets out the operating framework for the new state-owned energy company GBE.
DESNZ consults on changes to the Contracts for Difference contract to implement Clean Industry Bonus (CIB) reforms ahead of Allocation Round 8. Proposed changes: workforce protection through a Fair Work Charter, skills investment criteria, onshore wind into the CIB for AR9, hybrid metering contract changes, and various process improvements. Tracked amendments published alongside.
DESNZ publishes funded projects under the Hydrogen BECCS (Bioenergy with Carbon Capture and Storage) Innovation Programme. Phase 1 (£5m) funded scoping for 22 organisations; Phase 2 has a £26m budget for innovation design through demonstration. Three categories: feedstock pre-processing, advanced gasification, and novel biohydrogen technologies.
NESO explains its voltage reduction capability, where DNOs cut distribution voltage by 3-6% to reduce demand during emergencies. Testing with DNO groups shows a 3% voltage reduction yields approximately 1.2% demand reduction. Full DNO-wide testing is planned to refine the process.
NESO publishes its forecasting strategy to 2030, committing to probabilistic forecasts, multiple weather data sources, and in-house cloud infrastructure (Platform for Energy Forecasting) to replace legacy systems. The headline number is an estimated £2.5m per month saving from dynamic reserve setting underpinned by probabilistic forecasts, reducing average reserve holding by 400MW. FES2025 anticipates 90-120GW of wind and solar installed capacity by 2030 and 12-16% demand growth from 2024 to 2030.
NESO's Constraint Management Intertrip Service (CMIS) page consolidates the three active constraint management programmes: EC5 East Anglia (enduring service starting mid-2026), B6 Anglo-Scottish boundary (15 generators contracted, now extended to September 2027), and a new CMIS Scotland consultation launched 13 April 2026. These are commercial alternatives to transmission build, paying generators to accept automatic disconnection post-fault so more power can flow on existing infrastructure pre-fault.
Ofgem has rejected CMP344, which sought to shift the cost of offshore transmission Income Adjusting Events (IAEs) from offshore generators to demand consumers via the Transmission Demand Residual. The existing arrangement, where generators bear IAE costs through Offshore Local Charges, remains in place. The modification had been in development since May 2020 and was sent back twice before this final rejection.
GC0164 rewrites Grid Code Operating Code 2 (Operational Planning and Data Provision) in plain English with diagrams and flowcharts, without changing any obligations on users. The Panel unanimously recommended the original proposal. It now awaits Ofgem decision, with implementation 10 business days after approval.
The CUSC Panel on 24 April 2026 progressed three new modifications and one workgroup report. CMP469 creates a one-year cost recovery mechanism for parties affected by Grid Code restoration obligations (GC0186). CMP472 allows NESO to share large embedded generators' red line boundaries with DNOs without customer consent, enabling Gate 2 distribution contract verification. CMP471, which proposed interim contract variations ahead of the first CMP434 gated application window, was sent back to the proposer for scope clarification.
STC modification CM097 mandates Transmission Owners to submit EMT and RMS models of their assets to NESO, enabling system-wide dynamic modelling as inverter-based resources replace synchronous generation. The workgroup unanimously supported the original solution. Implementation aligns with Grid Code modification GC0168.
GC0168 would require legacy generators (completion before 1 September 2022) to provide Electromagnetic Transient models to NESO on request, enabling analysis of inverter instability, system oscillations, and transient overvoltage on a grid increasingly dominated by power electronics. The workgroup's preferred alternative (WAGCM1) defers the obligation for GB Code Users until a CUSC cost recovery mechanism is in place, while applying immediately to EU Code Users. Responses due by 8 June 2026.
DESNZ publishes accounting officer assessments for three major projects: CCUS Track-1 (HyNet and East Coast Cluster), the STEP fusion prototype, and the Boiler Upgrade Scheme extension. All three pass the four standard tests (regularity, propriety, value for money, feasibility). No new funding, no rule changes, no new mechanisms: these are retrospective sign-offs on decisions already taken.
DESNZ has published the process for generators excluded from CfD rounds to apply for exemption from their temporary site exclusion for Allocation Round 8, due to open in July 2026. Exclusion applies to generators that let a previous CfD offer lapse or had a CfD terminated. The notice sets out information requirements, the closing date for exemption requests, and where to submit them.
Ofgem proposes an early competition OFTO build model where transmission assets are competitively tendered before construction, rather than after. The consultation also updates the existing late competition model. Early competition would be mandatory in certain circumstances, with detailed proposals covering tender process, evaluation criteria, and commercial framework.
Ofgem has accepted urgency for CMP470, a CUSC modification proposing a commitment fee for oversubscribed generation technologies in the grid connection queue. Raised by Field Energy Limited on 20 March 2026, the proposal would price queue positions for technologies that dominate the 700 GW backlog. Urgency was requested by the CUSC Panel on 27 March and accepted by Ofgem on 2 April, meaning this bypasses the standard modification timeline.
Ofgem is gathering evidence from gas shippers and interconnectors to assess UNC0903, which would replace the current locational NTS capacity reference prices with a single uniform price across all entry points. Separate RFIs target shippers using interconnectors (IUK/BBL), LNG terminals, and Norwegian pipelines, plus the interconnectors themselves and National Gas Transmission. The modification is subject to an Authority decision; this RFI will feed an impact assessment.
DESNZ pre-announces the January 2026 monthly Renewables Obligation certificate and generation statistics, scheduled for release on 14 May 2026. This is the landing page for the announcement, not the data itself. No new figures are available yet.
DESNZ has published a pre-announcement for the Energy Trends and Prices statistical release covering December 2026 to February 2027, confirmed for publication on 25 February 2027. This is the landing page only; no data is yet available.
DESNZ pre-announces the Energy Trends and Prices statistical release covering November 2026 to January 2027, confirmed for publication on 28 January 2027. This is the standard monthly compendium of production, trade, generation, consumption, and retail/wholesale price data across all fuel types. No data is available yet; this is the accredited official statistics announcement page.
DESNZ has published a pre-release notice for Energy Trends and Prices covering Q4 2026, confirmed for release on 17 December 2026 at 9:30am. No data is yet available. This is an announcement of an announcement.
DESNZ has published a pre-release notice for Energy Trends and Prices covering September to November 2026, confirming publication on 26 November 2026 at 9:30am. No data is yet available. This is an announcement of an announcement.
DESNZ has confirmed that Energy Trends and Prices statistical tables covering August to October 2026 will be released on 29 October 2026 at 9:30am. This is a pre-announcement page with no data content. The actual release will cover monthly production, trade, electricity generation, consumption, and retail/wholesale price data.
DESNZ pre-announces the Q3 2026 Energy Trends and Prices statistical release, confirmed for 29 September 2026. No data is published yet. This is the GOV.UK placeholder page for the forthcoming release covering monthly production, trade, generation, consumption, and retail/wholesale price data.
DESNZ confirms the next Energy Trends and Energy Prices statistical releases for 27 August 2026. These cover monthly production, trade, generation, consumption across all fuels, plus retail and EU comparative prices. This is the pre-release announcement, not the data itself.
DESNZ confirms that Energy Trends and Energy Prices statistical releases will be published on 30 July 2026. This is a pre-announcement page with no data content. The actual release will cover monthly production, trade, generation, consumption, and retail/wholesale price data across all fuel types.
DESNZ confirms the next Energy Trends and Prices statistical release for 30 June 2026, covering monthly production, trade, generation, consumption across all fuels, plus retail and EU comparative price data. This is the pre-release announcement; no data is yet available. The series is the primary official dataset for tracking GB electricity generation mix, gas flows, and retail price movements.
DESNZ will publish Energy Trends and Energy Prices statistical bulletins on 28 May 2026, covering monthly production, trade, generation, and consumption across all fuel types, plus retail and EU comparative price data. This is the pre-release announcement; no data is available yet.
DESNZ lists 23 training providers sharing up to £8 million to deliver subsidised retrofit and solar PV installation courses under the Warm Homes Skills Programme, targeting up to 9,000 training places by July 2026. Courses span Level 2 entry-level retrofit awareness through Level 5 retrofit coordination diplomas, delivered across England's five Net Zero Hub regions.
DESNZ publishes the Q1 2026 extract of the Renewable Energy Planning Database, tracking all UK renewable electricity projects above 150kW through planning, construction, operation, and decommissioning. The database is managed by Barbour ABI and covers project-level detail including capacity, technology type, CfD allocation round, planning status, and grid coordinates. It includes an interactive map and links to the equivalent heat network database.
DESNZ published updated technical guidance for UK ETS installation operators on monitoring and reporting obligations under the 2018 MRR. Covers uncertainty assessments, biomass reporting, data flow controls, and sampling requirements. No rule changes; this is compliance documentation for an existing scheme.
DESNZ lists 25 projects that received £36 million across two phases of the Biomass Feedstocks Innovation Programme, funding R&D in domestic biomass production including algae, miscanthus, hemp, willow coppice, and forestry. Phase 1 awarded £4 million for project development; Phase 2 awarded £32 million for demonstration. Both phases are now closed.
DESNZ published the list of successful projects under its CCUS Innovation 2.0 programme, covering Calls 1 and 2. The programme funds 20+ R&D projects totalling roughly £22m across capture solvents, MOF-based adsorbents, CO2 utilisation in concrete and fertiliser, subsea storage equipment, and reservoir simulation tools. Most projects are TRL 3-7, targeting cost reduction and scale-up for next-generation capture and storage technologies.
DESNZ published project documents from Keadby Generation Limited's FOCUSS project under the CCUS Innovation 2.0 programme, exploring flexible post-combustion carbon capture with solvent storage. The project aimed to de-risk technology allowing CCS plants to operate flexibly rather than baseload-only.
Ofgem has rejected CMP344, which proposed shifting offshore Income Adjusting Event (IAE) costs from generators connected to OFTO assets onto demand consumers via the Transmission Demand Residual charge. The rejection preserves the status quo: generators connected to offshore transmission remain liable for IAE costs on their OFTO assets. This applies to both existing and future OFTOs.
UK solar installations hit 27,000 in March 2026, the highest monthly total since 2012, bringing cumulative installations past 2 million. Solar capacity grew 11.7% year-on-year, adding 2.3 GW. Peak solar output passed 15 GW for the first time on the GB system.
DESNZ quarterly energy statistics for Dec 2025-Feb 2026 show renewables at 51.8% of major power producer generation, gas down 11% year-on-year to 35.5%, and nuclear down 11% to 11.9%. Primary energy consumption fell 3.3% (2.1% temperature-adjusted). Indigenous production fell 4.5%.
UK solar PV reached 22.1 GW across 2,003,000 installations at end of March 2026, up 11.7% (2.3 GW) year-on-year. March 2026 saw 27,607 new installations (121 MW), the highest monthly installation count since 2012. Ground-mount now accounts for roughly 58% of total capacity, with 25 CfD-accredited solar farms operational including 19 commissioned during 2025.
DESNZ commissioned Baringa to update its 2024 assessment of supply chain constraints across renewable and network technologies to 2035. The study identifies bottlenecks that could delay deployment and recommends industry or policy interventions to address them.
The Secretary of State has corrected errors in the Tillbridge Solar Development Consent Order 2025, a large solar project in Lincolnshire. This is an administrative correction to an already-granted DCO, not a new planning decision or policy change.
Ofgem has granted urgency status to CMP475, which would allow NESO to reopen fixed BSUoS tariff periods mid-period when the Working Cash Flow (WCF) threshold is forecast to be exceeded, and to introduce a mechanism to recover the WCF position toward neutral within that period. NESO raised the modification on 15 April 2026; the CUSC Panel unanimously backed urgency on 21 April; Ofgem accepted on 29 April. This changes BSUoS from a truly fixed charge to one that can be reset intra-period, shifting forecast risk back onto demand users.
Ofgem has granted urgency status to CMP474, a CUSC modification that would introduce a reset mechanism for the fixed BSUoS tariff in response to rising balancing cost volatility. NESO raised the proposal on 14 April 2026 and the CUSC Panel unanimously supported urgency on 21 April. Urgency status compresses the modification timeline from months to weeks.
DESNZ has completed its statutory three-year review of the NSTA, concluding the regulator is effective but needs reformed objectives and stronger powers. The NSTA's principal objective will shift from Maximising Economic Recovery to three balanced objectives covering economic value, net zero, and workforce transition. Maximum financial penalties increase from £1 million to £5 million, with power to raise to £10 million; decommissioning cost estimates have risen from £37 billion to £44 billion.
DESNZ has updated its index page for Climate Change Agreement guidance. CCAs give energy-intensive industrial users a discount on the Climate Change Levy in exchange for meeting energy efficiency targets. No new rules or changes are announced; this is a document collection page.
DESNZ has published updated template agreements for the Climate Change Agreements scheme, covering the new phase with target periods from 1 January 2026 to 31 December 2030. CCAs allow energy-intensive industrial operators to receive a discount on the Climate Change Levy in exchange for meeting energy efficiency or carbon reduction targets. The templates set out the contractual framework between the Environment Agency, sector associations, and individual facility operators.
DESNZ and Ofgem published the outcome of a call for evidence on whether the RAB model of economic regulation for CO2 storage should evolve as the CCUS market matures. The call closed 31 October 2025 and explored whether unbundled CO2 storage could support competition, reducing the need for regulated returns and government revenue support agreements. This is part of a four-document series on transitioning CCUS to a self-sustaining market.
DBT publishes updated application guidance for the UK ETS and CPS indirect cost compensation scheme for energy-intensive industries. The scheme compensates 14 eligible sectors (by SIC code) for carbon costs passed through in wholesale electricity prices, using efficiency benchmarks and a 5% GVA intensity test. Key parameters for 2026-27: UK ETS reference price £53.19/tCO2, CPS rate £18/tCO2, CO2 emissions factor 0.45 tCO2/MWh, subsidy intensity capped at 75% of indirect costs or 1.5% of GVA.
DESNZ has announced that the monthly solar PV deployment statistics for August 2026 will be published on 29 September 2026, moved from 24 September to align with the Energy Trends release. No data is contained in this publication; it is a pre-announcement of a future statistical release.
DESNZ has pushed the next solar PV deployment statistics release from 25 June to 30 June 2026, aligning it with the Energy Trends publication. No data is included in this announcement.
The UK Kyoto Protocol Registry closed permanently on 1 April 2026. This is an administrative notice confirming the closure of a legacy carbon accounting system that has had no operational relevance to GB electricity markets since the UK left the EU ETS.
DESNZ will publish Energy Trends and Prices for February 2026 on 30 April 2026 at 09:30. This is the monthly compendium covering production, trade, generation, consumption across all fuels, plus retail and wholesale price indices. This is the pre-release announcement; the data itself is not yet available.
DESNZ will publish monthly Renewables Obligation certificate and generation data for December 2026 on 8 April 2027. This is a pre-announcement of a confirmed statistical release, not the data itself. ROC issuance data tracks the volume and technology mix of generation still operating under the RO scheme.
DESNZ will publish Energy Trends and Prices for February 2027 on 29 April 2027, covering monthly production, trade and consumption across all fuel types plus retail and EU comparative price data. This is a pre-announcement only; no data is yet available. The release is a regular monthly statistical publication.
The Secretary of State has issued corrections to the Rampion 2 Offshore Wind Farm Development Consent Order (1,200 MW). The publication contains only the fact of the correction with no detail on what was changed. This is a routine administrative tidying of an already-granted DCO.
DESNZ has issued ministerial directions under section 52 of the Climate Change Act 2008 covering three UK ETS matters: defining eligible fuels for maritime operators making emissions reduction claims under Schedule 2A paragraph 37, setting penalty levels for installation operators with permits under article 50(4), and penalties for ultra-small emitters exceeding thresholds under article 60(6). The penalty directions have been in force since October 2023; the maritime fuel eligibility direction references EU renewable energy and waste directives as at April 2026. Parallel directions have been issued by devolved governments.
DESNZ has published the document collection page for CfD Allocation Round 8. The page itself contains no substantive policy content, budget parameters, strike prices, or pot structures. It is a navigation index pointing to the CfD microsite, delivery partners, and a bulletin subscription.
DESNZ publishes the UK's first fossil fuel subsidy inventory under its COFFIS commitments, cataloguing every tax relief, rebate, and support measure that reduces the cost of fossil fuel use. The inventory confirms £7 billion of Renewables Obligation costs will shift from consumer levies to exchequer spending over 2026/27-2028/29. It also commits the UK to publishing a national phase-out strategy for fossil fuel incentives by COP31.
DESNZ has published the statutory notices required to launch CfD Allocation Round 8, including a new Clean Industry Bonus (CIB) allocation framework. The CIB is a supplementary payment mechanism layered on top of the standard CfD strike price, rewarding generators that meet domestic supply chain content requirements. These are the formal legal instruments that trigger the round opening.
DESNZ is reviewing Ofgem's mandate, statutory duties, regulatory remit, and enforcement powers. The call for evidence covers whether Ofgem's principal objective should shift from promoting competition to broader goals including innovation and consumer standards, whether its accumulating statutory duties should be streamlined, and whether it should gain FCA-style Consumer Duty and Senior Manager Regime powers. The consultation closed 28 February 2025; outcomes are now being considered.
DESNZ publishes the first comprehensive review of Ofgem in its 25-year history, proposing to rewrite its statutory duties, give it direct consumer law enforcement powers without court action, introduce individual executive accountability, and cap bonuses for rule-breaking. The review will produce a reformed Strategy and Policy Statement to separate government policy-setting from regulatory delivery, and commits to clarifying the boundary between DESNZ, NESO and Ofgem. Ofgem's workforce has grown from 890 FTE in 2014/15 to 2,110 in 2024/25.
Ofgem publishes final determinations on Contracts for Difference disputes raised in 2025. Decisions resolve contested payments between LCCC and generators under the CfD scheme.
DESNZ published the outcome of a call for evidence on how CO2 transport and storage networks should evolve from government-backed RAB models toward commercially self-sustaining operations. The call, which closed 31 October 2025, covered capacity booking reform, network utilisation, flexible products, and the future of Revenue Support Agreements and Government Support Packages for T&S operators. It sits alongside parallel workstreams on CO2 storage economic regulation and non-pipeline transport.
Ofgem's Jack Presley Abbott confirms that the battery pipeline emerging from connections reform may be oversupplied relative to Clean Power 2030 needs, and that many protected 2026 and 2027 projects will miss their original dates. Ofgem is considering intervention to prune the queue, and names demand-connection reform, including a data-centre levy, as the next front.
Miliband speech at the National Growth Debate. Frames the RNP package, SMR contracts, Sizewell C consent and EGL extension as a coherent clean energy security programme.
DESNZ consults on siting and investment levers under Reformed National Pricing (RNP), the programme that replaces REMA after ministers rejected zonal pricing. Closes 2 June 2026. Ofgem runs a parallel Call for Input on network and connections charging to 26 May. Together these set how much new generation and storage pay, and where.
DESNZ has announced a Wholesale Contract for Difference (WCfD) that would let existing Renewables Obligation and merchant generators swap forward wholesale revenue for a fixed government strike price, while ROC income continues unchanged. The Electricity Generator Levy rises from 45 to 55 percent, removing the legislated taper to zero. Consultation on WCfD design comes later in 2026, allocation in 2027. Reformed National Pricing is confirmed as the post-REMA track; zonal is off the table.
The RNP Delivery Plan landing page. Frames the 21 April DESNZ consultation and confirms REMA is closed. Substantive response window is the companion siting-and-investment consultation.
Ofgem and DESNZ confirm 221 GW has been removed from the connection queue under the new Gate 2 / Phase 1 process, with self-selection into Gate 1 filtering out additional capacity. Battery storage has progressed to Gate 2 at a materially higher level than planned: 14.8 GW above the Clean Power 2030 Action Plan range and 61.7 GW above projected 2035 system need. Protection measures for projects with planning consent, Capacity Market agreements or near-term offers, combined with batteries' faster consenting speed, are named as the cause.
DESNZ will publish March 2026 monthly solar PV deployment statistics on 30 April 2026. This is a pre-release announcement confirming the publication date; no data is yet available.
Ofgem calls for stakeholder input on NESO's Business Plan 3 performance for 1 April 2025 to 31 March 2026, the final year of RIIO-2. Assessment moves to a Below/Meets/Exceeds Expectations grading across two components: delivery of business plan aims (via Success Measures) and value for money. Responses due 18 May 2026; final decision summer 2026.
DESNZ and Ofgem signal they may intervene to remove battery storage projects from the reformed connection queue, where 14.8 GW above the Clean Power 2030 Action Plan range and 61.7 GW above projected 2035 system need have progressed to Gate 2. The surplus was caused by protection measures for projects with planning consent or Capacity Market agreements, which batteries secured faster than other technologies. NESO's annual consultation proposes disapplying protections so that only batteries with revenue support schemes qualify for future windows, and a code modification imposing financial attrition measures has been granted urgency.
Ofgem rejected urgency for BSC modification P510, which proposed replacing the mutualised compensation arrangements under P415 with direct compensation for Virtual Trading Party actions in the wholesale market. P510 was raised by Flexitricity on 5 March 2026 after evidence of rising volumes and costs in the P415 mutualised compensation fund. Related urgency requests for P509 and P511 were considered alongside and also rejected.
Ofgem has granted urgency for BSC modification P511, which proposes an eligibility threshold above which generation assets cannot participate in wholesale markets via Virtual Trading Parties (VLPs) created under P415. Raised by Axle Energy on 18 March 2026, P511 responds to a recent increase in the volume and cost of the P415 mutualised compensation fund. This is the third urgent modification (alongside P509 and P510) targeting the same problem: P415's market access framework is generating socialised costs that were not anticipated.
DESNZ will exempt over 10,000 manufacturers from Renewables Obligation, Feed-in Tariff, and Capacity Market levy costs on their electricity bills from April 2027, cutting bills by up to 25% (£35-40/MWh). The scheme expands eligibility by 40% from 7,000 to 10,000 businesses, with a one-off backdated payment covering April 2026 to March 2027, and is expected to cost £600 million per year funded through unspecified 'changes within the energy system' and Exchequer funding.
DESNZ publishes the summary programme business case for Great British Energy - Nuclear's SMR programme. GBE-N received over £2.5 billion capital funding in the 2025 Spending Review for the first project and enabling activities. Wylfa on Anglesey was selected in November 2025 as host site for the first SMR, adding up to 1.5 GW. Funding model undecided but RAB is under consideration. Delivery will run through an operationally independent DevCo intended to attract private investment.
Ofgem has published a call for input on the future regulatory framework for electricity interconnection, covering route to market, competition models, financing structures, and treatment of Offshore Hybrid Assets. This accompanies DESNZ's policy paper on interconnection's role in a strategically planned system. GB currently has 10.3 GW of operational interconnector capacity with 1.4 GW in construction and 8.9 GW in development under existing approvals.
Ofgem is challenging the widespread use of fixed MW thresholds — particularly the 100MW threshold — for determining whether outage and availability information must be published as inside information under REMIT Article 4. The regulator flags that threshold-based approaches ignore prevailing market conditions, cumulative effects of smaller outages, and aggregation across a participant's portfolio. The guidance explicitly extends expectations to Offshore Transmission Owners (OFTOs), signalling that transmission availability disclosure has been inadequate.
Ofgem has rejected IGT165, a modification proposed by OVO Energy to create an Independent Shrinkage Expert and Independent Shrinkage Charge on Independent Gas Transporter networks. The proposal aimed to incentivise reduction of gas shrinkage emissions on IGT networks by introducing a dedicated charge and expert role. Submitted September 2025, the rejection means the existing shrinkage arrangements on IGT networks remain unchanged.
Ofgem has approved NESO's methodology for refreshing the second transitional Centralised Strategic Network Plan (tCSNP2), which will reassess the transmission network build programme needed through the 2030s. The refresh will update cost estimates, delivery timescales, and network designs from the 2024 tCSNP2, incorporating connections reform outcomes and revised offshore network configurations. It also feeds into the pipeline for the full CSNP due by December 2028.
Ofgem has directed NESO to delay the first Centralised Strategic Network Plan by 12 months: submission moves from June 2027 to 15 September 2028, publication from December 2027 to 15 December 2028. The delay aligns CSNP with the revised Strategic Spatial Energy Plan timeline. NESO requested the derogation itself on 23 March 2026, and Ofgem granted it.
Ofgem has conditionally approved NESO's methodology for producing the Centralised Strategic Network Plan (CSNP), the first independent long-term plan covering electricity, gas transmission, and hydrogen transport and storage networks in GB. The methodology uses the Strategic Spatial Energy Plan as an input and describes how NESO will identify system needs, develop options, appraise them, and recommend delivery. Approval is subject to two conditions requiring further detail on unspecified areas.
DESNZ has published the methodology behind its Subsidy Control Transparency Database entries for CfD Allocation Round 7, disclosing that the total estimated subsidy has been rounded to the nearest £5 billion. AR7 contracts are now 20 years (up from 15) for fixed and floating offshore wind, onshore wind, and solar. Estimates use the AR7 Allocation Framework valuation formula and are presented in 2024 prices, undiscounted.
Ofgem republished the template Letter of Authorisation used when opening or updating an account on the Renewable Electricity Register. It is an administrative form, not a rule change.
UKAEA published its 2026-2030 strategy for the national fusion laboratory, setting objectives around completing STEP prototype design, expanding research facilities at Culham, and growing the fusion supply chain. It accompanies UK Fusion Energy Ltd's own strategy and builds on the government's Fusion Strategy launched the previous month.
UKAEA published a Global Fusion Guide for SMEs, a supplier-facing explainer on how UK businesses can enter the global fusion supply chain. It claims over 68 private fusion companies are operating and cites £100bn of expected global fusion spend between 2026 and 2035. No rules, charges, or market structures change.
UKAEA publishes its 2026-2030 strategy for the National Fusion Laboratory, setting out research priorities alongside UK Fusion Energy Ltd (renamed from UKIFS in March 2026). The strategy confirms the £2.5bn fusion RDI budget to 2030 and four themes: International, Research, Commercialisation, Industry. Operational focus on H3AT, LIBRTI, MAST-U and JET decommissioning.
NESO has published Issue 8 of the EDL Message Interface Specification, the protocol Balancing Service Providers use to receive dispatch instructions and submit dynamic parameters. The update implements Grid Code modification GC0166, adding two new submission message types: Maximum Delivery Offer (MDO) and Maximum Delivery Bid (MDB), plus decimal-place precision for MWh values. References to BOAR and Replacement Reserve have been removed.
NESO's index page listing electrical standards documents for transmission-connected generators across England, Wales, SPT and SHE Transmission areas. The page was refreshed to show an updated EDL Message Interface Specification dated 13 April 2026; all other listed standards are unchanged.
DESNZ has updated the UK ETS free allocation table following Activity Level Change adjustments, with the 2021-2025 allocation period extended to cover 2026. The table sets installation-level free allowances for energy-intensive industry and, notably, some power-sector CHP and gas compressor stations. Several 2026 allocations step up materially (Tate & Lyle to 70,578 from 40,824; Humber Energy to 38,725 from 28,092) while others (CF Fertilisers Billingham) stay flat at 150,426 after earlier cuts.
DESNZ updated the UK ETS Aviation Allocation Table for the 2021-2025 period to reflect operator transfers and cessations. The table lists free allowance entitlements for aircraft operators; 2023-2025 figures remain indicative pending the free allocation review.
DESNZ has published a revised Electricity Supply Emergency Code setting out how rota disconnections would be imposed during a prolonged electricity shortage. Non-protected demand is split into 18 Load Blocks of ~5% each, disconnected in three-hour rotations under NESO-issued Activation Schedules, with Protected Sites shielded via a four-tier list (Tier 0 energy infrastructure, Tier 1 hospitals, Tier 2 essential services, Tier 3 industrial sites facing >=10% asset damage). The update follows a 2023 review and reflects the split between the short-notice Demand Control Rotation Protocol and the prolonged-emergency ESEC route.
DESNZ and China's Ministry of Ecology and Environment signed a bilateral MoU on climate cooperation in London on 16 June 2025, establishing an annual ministerial dialogue and working-level exchanges. Cooperation areas include mitigation policy, carbon markets, climate finance, and methane measurement. No binding commitments, no funding, no rule changes.
Ofgem published final Tier 2 determinations on ten Capacity Market prequalification disputes for the 2025-26 Delivery Year. Appellants include Capbal (Kilwinning), OakTree Power, Northwold Solar Farm, Nextpower Rutherglen, Harmony KB, Flexion Energy (two appeals), ENGIE Power, Diodes Zetex Semiconductors, and Battery Box. The determinations review whether the Delivery Body correctly applied the Capacity Market Regulations and Rules to each original prequalification decision.
Ofgem consults on 13 Capacity Market rule change proposals (CP382-CP394). Proposals cover Independent Technical Expert definitions, termination reasons, load-following obligation calculations, metering test processes, and other operational rules. Consultation closes 24 May 2026.
DESNZ has issued a screening decision that a single 132 kV tower, cable sealing end platforms, and two underground cables at Musty Haulgh Farm, Burnley do not require a statutory Environmental Impact Assessment. The works are a minor modification to Electricity North West's existing 'DR' overhead line to connect a 152 MWh battery storage site that already has planning consent (FUL/2021/0375, granted July 2023). Burnley Borough Council confirmed no EIA needed on 15 December 2025; no public representations were received by the 3 April 2026 deadline.
Secretary of State makes corrections to The Morgan Offshore Wind Project Generation Assets Order 2025. The project has a minimum output of 1,400 MW. Administrative correction to an existing DCO.
Ofgem grants urgency to CMP470, a CUSC modification that would introduce commitment fees for developers holding grid queue positions in oversubscribed technology categories — primarily battery storage, which exceeds CP2030 targets by 14.8GW (2030) and 61.7GW (2035). The fee mechanism would price queue occupation for the first time, giving non-viable projects a financial reason to exit before signing Gate 2 connection agreements. Decision needed before Phase 1 offers are accepted from mid-August 2026.
NESO has published its 2026 Operability Strategy Report and Electricity Markets Roadmap, covering operational changes needed for clean power by 2030. The reports emphasise demand-side flexibility, stability pathfinder programmes, reserve product markets, and changes to minimum inertia requirements. A separate Visibility and Access Roadmap consultation on distributed energy resource oversight is open until April 2026.
NESO's March 2026 monthly energy statistics report GB's generation mix and demand. Wind set a new maximum generation record of 23,880 MW on 25 March, providing 60% of electricity at peak. Wind led the month at 34.8% of generation, gas second at 22.2%, with peak demand of 38,160 MW on 3 March.
NESO consults on a roadmap to gain operational visibility and dispatch access to distributed energy resources (DERs) and consumer energy resources (CERs) — commercial batteries, small-scale wind, EVs, rooftop solar, and home batteries. The consultation closes 30 April 2026 and seeks feedback on ambition, practicality, and completeness of proposed capabilities and data requirements. This is the system operator's bid to extend its operational reach below the transmission-distribution boundary.
NESO's Balancing Programme landing page aggregates updates on the Open Balancing Platform (OBP), control room capability journeys, and stakeholder engagement events. No new rules, charges, or decisions are announced. The page serves as a navigation hub for existing materials including webinar recordings, slide packs, and closure reports.
NESO's first Q&A workshop on GC0166 explains the MDO/MDB (Maximum Delivery Output/Bid) mechanism that replaces the 30-minute rule for battery dispatch in the Balancing Mechanism. Control points must submit minute-granularity energy availability data from real-time to 05:00 D+2, protecting volumes committed to frequency response and reserve contracts. Go-live is 22 June 2026, with transition running to November 2026 as individual control points certify readiness.
The Grid Code Review Panel met on 26 March 2026. Two new modifications were presented: GC0185 proposing dynamic regulation as an alternative to mandatory frequency response was sent back for clearer scope, and GC0187 (legal text corrections) was deferred over a drafting query. GC0139 on enhanced planning-data exchange between network operators and NESO was unanimously recommended to Ofgem.
CUSC Panel granted urgent treatment to CMP470, which introduces a commitment fee for grid connection technologies oversubscribed relative to Clean Power 2030 targets — a pricing mechanism for queue capacity. CMP440, which removes the zero price floor on demand TNUoS locational tariffs to restore locational investment signals, was unanimously recommended to Ofgem. CMP445 (pro-rated first-year TNUoS for generators) proceeds to Code Administrator Consultation opening 7 April 2026.
TCMF slidepack covers five substantive items: a proposed CUSC clause to let NESO share Large Embedded Generator red line boundaries with DNOs without customer consent; a proposed urgent modification to allow connection date delays during the ~30-month freeze ahead of the first CMP434 gate window; RWE flagging significant errors and missing appendices in Gate 2 Offers where network companies delayed connection dates; and NESO's proposal to model Sea Link HVDC tariffs on a north-to-south (Sizewell-to-Richborough) flow direction based on power flow studies showing 75% southward flow. The code administrator update lists CMP470 (Oversubscribed Technologies Commitment Fee) as a new urgent modification with nominations closing 2 April.
NESO consults on guidance for secondary generators — those with Grid Code obligations but no restoration contract — on how to comply with the Electricity System Restoration Standard (ESRS). The ESRS requires 60% of national demand restored within 24 hours and 100% within five days of a total or partial shutdown, with a compliance deadline of 31 December 2026. The guidance codifies existing Grid Code obligations around 72-hour plant resilience, cold start time declarations, communications testing, and cyber security under the NIS Regulations.
Secretary of State approves non-material change to North Killingholme CCGT (Uniper). Routine planning amendment.
Ofgem consults on the second preliminary Strategic Direction Statement, which sets binding priorities for how GB industry codes must develop under the Energy Act 2023 governance reforms. The SDS categorises policy areas requiring code changes and proposes converting from a preliminary to a hybrid document once BSC and REC are designated by end-2026. Responses due 28 May 2026.
Ofgem consumer blog explaining wholesale energy cost components and their transmission to bills via the price cap. Notes wholesale costs are ~40% of bills, gas sets marginal electricity price 'a large majority of the time', and NESO estimates gas could set the price just 30% of the time by 2030. Confirms Q2 2026 price cap fall reflects both lower wholesale prices and the fiscal transfer of environmental levy costs to general taxation.
Ofgem's standing reference page for the Feed-in Tariff scheme, which closed to new applicants on 1 April 2019. The page describes how FIT works: accredited generators receive quarterly payments from licensed suppliers for electricity generated and exported, with costs spread across all suppliers via levelisation. No new rules, rates, or deadlines are introduced.
Ofgem's FIT tariff and payments reference page sets out how generation and export tariffs are calculated for accredited installations under the closed scheme. Tariff rates are set by DESNZ and indexed to CPI from FIT Year 17 onwards, replacing the previous RPI indexation. The scheme closed to new applications on 1 April 2019 but continues to pay existing generators for their 20-25 year tariff periods.
Ofgem's FIT data portal page lists the standard suite of Feed-in Tariff reports: annual, quarterly, deployment caps, installation, and levelisation. This is an index page linking to existing datasets, not a new release. The FIT scheme closed to new applicants in March 2019; these reports track the legacy tail.
Ofgem has updated its FIT supplier guidance (Version 18) to reflect the government's mandated transition from RPI to CPI inflation indexation for FIT tariff adjustments, following the January 2026 consultation response. The update also includes a revised contact email for the RE Compliance Team.
Ofgem publishes the quarterly FIT levelisation report detailing total payments made by FIT licensees to accredited generators. This is a routine administrative publication — a landing page for downloading historical levelisation data. No new policy, no rule change.
Pre-announcement for RO certificates and generation data: December 2025.
UK territorial GHG emissions statistics index page.
UK territorial greenhouse gas emissions fell 2% in 2025 to 367 MtCO2e, down 54% from 1990. CO2 made up 78% of the total. Rate of decline is slowing as easy wins (coal closure) are exhausted.
DESNZ publishes Clean Power 2030 tracking metrics showing clean generation share, clean demand share, and emissions intensity. Annual data in GWh and percentage shares.
Energy Trends special feature reviewing solid biomass classifications in UK energy statistics.
Duplicate listing of Energy Trends March 2026 biomass special feature.
Energy Trends Q4 2025 and full-year 2025. Renewables reached a record 52.5% share of electricity generation (152.5 TWh). Wind hit 30.0% (87.1 TWh) and solar rose 37% to a record 20 TWh. Nuclear fell to a record low — low carbon share barely moved from 64.6% to 64.8%.
Energy Trends UK electricity chapter. Generation -1.9%, exports +38%.
Renewables Obligation certificates and generation statistics. Tracks ROC issuance volumes by technology and accredited generating stations.
Ofgem sets the RO buy-out price at £69.34/ROC for 2026-27, up 3.4% from £67.06, with the indexation basis switching from RPI to CPI following DESNZ's January 2026 decision. The obligation level drops slightly to 0.472 ROCs/MWh from 0.493. Mutualisation ceilings are £417.7m for England & Wales and £41.8m for Scotland.
Ofgem has approved NESO's request to increase the derogated volume of Mandatory Frequency Response (MFR) procurement from 120 MW to 300 MW — a 150% increase. The derogation allows NESO to procure MFR earlier than day-ahead and for contract periods up to one month, bypassing standard Grid Code procurement rules. All other terms of the January 2025 derogation remain unchanged, with expiry on 31 December 2029.
CMP470 proposes a commitment fee for technologies oversubscribed relative to Clean Power 2030 targets, aimed at forcing speculative projects out of the connection queue. The CUSC Panel voted by majority to recommend urgent treatment to Ofgem, with a final modification report targeted for 30 June 2026 under the urgent timeline versus April 2027 under standard process. The proposal was raised by Field Energy on 20 March 2026 after Gate 2 capacity data revealed approximately 90 GW of battery storage projects seeking connection points when roughly one third will actually connect.
Ofgem's RO annual report for Scheme Year 23 (April 2024–March 2025) shows 101.4 million ROCs issued against a supplier obligation of 119.5 million ROCs, with suppliers presenting 105.9 million ROCs and paying £613.7 million into buy-out and late payment funds. RO-accredited generation from 35.0 GW of capacity produced electricity equivalent to 30.2% of UK supply, rising to 46.6% when combined with FiT and CfD. Two supplier failures (Tomato Energy and Rebel Energy) created a £23.6 million shortfall, though this remained below the mutualisation threshold for the third consecutive year.
Ofgem publishes the 16th annual biomass sustainability dataset under the Renewables Obligation, covering Scheme Year 23 (2024-2025). The dataset reports against sustainability criteria introduced in 2009 for biomass-fuelled generating stations. It accompanies the RO Annual Report's biomass sustainability chapter.
Ofgem published its 63rd quarterly FIT report covering Q4 2025 (October-December), summarising installations, installed capacity, and levelisation for the scheme now in its 16th year. The scheme has been closed to new applicants since April 2019; this is routine monitoring of legacy obligations.
Elexon launching API-based asset registration for the Balancing Mechanism on 31 March 2026, linking to their Customer Solution Platform. Reduces friction for flexibility providers entering the BM.
The Distribution Code proposes consolidating EREC G98 and EREC G99 distributed generation connection guides into a single document. This annual revision follows Distribution Code requirements with consultation planned for March 2025. The change streamlines guidance for generators connecting at different scales rather than altering connection rules themselves.
The Distribution Code modification EREC G59 Issue 3 A8 adds supplementary sections to facilitate intentional islanding during system restoration processes. This builds on existing Engineering Recommendation G59 guidance for distributed energy resources. The modification enables controlled isolation of network sections while maintaining local supply during wider system recovery.
EREC G99 adds supplementary sections to facilitate intentional islanding during system restoration. This is a code modification to the distribution connection standard. The change enables grid-connected assets to operate in isolation when the grid is being restored after blackouts.
The Standard Application Form (SAF) v11 for EREC G99 connections updates the formal document used to apply for connecting power generating modules exceeding 16A per phase to distribution networks. The form covers solar, wind, battery storage, and other generation technologies connecting under G99 requirements. This appears to be a routine version update to existing connection application procedures.
Distribution network operators assess whether to create explanatory guidance supporting Engineering Recommendation P28 Issue 2, which sets technical standards for distributed generation connections. The proposed Engineering Report would provide additional technical application guidance but would not change P28 itself. No timeline or specific technical areas are identified.
CMP470 proposes introducing a commitment fee floor for all technologies that are oversubscribed relative to Clean Power 2030 capacity targets. The modification targets generation developers with high impact and transmission owners with medium impact. It is proceeding through urgent governance route to workgroup stage.
NESO expands its Demand Flexibility Service to allow participants to be rewarded for increasing electricity consumption during periods of excess supply, alongside existing rewards for demand reduction. The service threshold drops from 1MW to 0.1MW, opening participation to smaller suppliers and businesses. Over 2.46 million businesses and consumers have already signed up.
NESO published guidance on its connections reform programme, including a new delivery pipeline prioritising 381.5GW of 'ready-to-build' capacity and announcing permanent leadership structure under new Director of Connections Colm Murphy from 13 April. The reform moves from a chronological queue to a delivery pipeline based on project readiness, with claims of unlocking £40bn annual investment.
NESO establishes a programme to track and enable demand-side flexibility participation in its balancing services markets, targeting 10-12 GW of demand flexibility by 2030. The programme includes quarterly reporting of participation levels and a Routes to Market Review to remove barriers for demand-side participants. Data relies on self-reported confirmations from asset owners, with NESO encouraging non-respondents to contact them for comprehensive representation.
NESO publishes quarterly updates on its review to remove barriers preventing demand-side flexibility from participating in system operator markets. The review has completed three stages and now publishes quarterly progress reports tracking barrier removal, with a data dashboard monitoring participation volumes. The programme follows NESO's Clean Power 2030 advice identifying demand-side flexibility as essential for operating a decarbonised system.
Code modification GSR038 proposed to remove the requirement for two offshore AC transformers at grid entry points of 90MW or more has been withdrawn. The modification aimed to assess restrictions in Grid Code Clause 7.7.1.1 that effectively mandated dual transformer configurations. NESO classified it as having high impact on offshore transmission owners and generators.
DESNZ publishes the CHPQA Standard that sets Quality Index thresholds for Combined Heat and Power plants to qualify for 'Good Quality' certification. Different versions apply based on when schemes commenced operation or entered CfD contracts, with Issue 7 (December 2018) applying to CfD schemes, Issue 6 (September 2016) to schemes operating from 2016, and Issue 5 (November 2013) to earlier schemes. The Standard determines eligibility for various benefits excluding Renewables Obligation and Contracts for Difference support.
DESNZ and Ofgem propose mandatory baseline cyber security requirements for all 1,400+ Ofgem licensees through licence conditions, using Cyber Essentials certification as the starting point. The proposal also expands Network and Information Systems (NIS) Regulations to capture more distributed energy operators deemed critical to system stability. NESO will provide independent advice on which services and operators should fall under the enhanced NIS framework.
Ofgem and DESNZ propose baseline cyber security requirements for all energy licensees, plus expanded Network and Information System Regulations coverage. The consultation seeks to standardise cyber resilience across downstream gas and electricity sectors through mandatory minimum requirements. No specific thresholds, costs, or implementation dates are provided.
DESNZ launches new self-assessment portal for Combined Heat and Power Quality Assurance (CHPQA) scheme, replacing legacy digital service. CHP operators must register on the new portal to submit certification applications. Four existing forms (F1-F4) are now redundant.
DESNZ provides worked example for calculating Z-ratios through plant performance testing for combined heat and power qualification assessment. The example demonstrates solving simultaneous equations from three test conditions to determine specific electricity generation rates for different steam extraction points. This determines the Z-factor that measures efficiency loss when diverting steam for heat rather than electricity generation.
DESNZ requires Combined Heat and Power Quality Assurance (CHPQA) operators to report annual fiscal benefits received from certification including Climate Change Levy exemptions, Carbon Price Support reductions, and business rates relief. The guidance provides calculation methods for benefits worth millions annually to individual operators (£13.4m in example for 150 MW plant). This data collection supports policy development as government reviews CHP tax treatments.
DESNZ published updated CHPQA guidance for biomass and waste CHP schemes accessing support through the Renewables Obligation and Contracts for Difference. The guidance clarifies quality index calculations, certification requirements, and eligibility criteria for schemes claiming higher ROC payments or CfD support by demonstrating good quality CHP operation. It covers different fuel categories with specific formulae and includes safeguards for schemes supplying heating networks.
DESNZ guidance explains how CHP schemes with CHPQA certification can claim exemption from business rates on specific plant and machinery. The exemption covers power generation equipment (turbines, generators, engines) and accessories but excludes heat recovery plant and buildings. Schemes must hold a Secretary of State CHP Exemption Certificate and follow prescribed procedures with local Valuation Officers.
DESNZ has updated guidance on how combined heat and power (CHP) operators can use CHPQA certificates to claim exemptions from climate change levy and fuel duty. The guidance covers fuel input exemptions, carbon price support liabilities for schemes above 2 MWe, and electricity output relief calculations.
DESNZ publishes guidance on calculating Z ratios for Combined Heat and Power schemes with steam turbines, defining how to measure the trade-off between power generation and heat supply when steam is extracted at different pressures. The guidance provides reference tables showing Z ratios from 3.9 to 8.1 depending on turbine size (2-50+ MWe) and steam pressure (2.4-21.7 bar). Operators must determine their specific Z ratio through measurement or calculation, with fallback to tabulated values if testing is not feasible.
DESNZ updates guidance on calculating qualifying power capacity for combined heat and power schemes under the CHP Quality Assurance programme. The guidance sets minimum operational hours required for different scheme types (500-1000 hours annually) and establishes calculation methods for schemes that fail to meet quality index thresholds. This determines what proportion of CHP capacity qualifies for support mechanisms.
DESNZ updated guidance on calculating qualifying power output for CHP schemes that fail to meet minimum quality index thresholds. Schemes must achieve QI of 100 (or 95 for new schemes) for all power output to qualify as Good Quality CHP. Those below threshold must calculate reduced qualifying output using heat-to-power ratios and efficiency formulas.
DESNZ updates guidance on calculating qualifying fuel input for CHP schemes that fail to meet the 20% power efficiency threshold for Good Quality CHP status. The guidance provides a specific formula: CHPQFI = Annual Power Efficiency × Total Fuel Input ÷ Power Efficiency Threshold. This is version 3 of Guidance Note 25, published March 2026.
CHPQA Guidance Note 18 details how Combined Heat and Power operators should calculate and report uncertainties in energy input and output measurements when self-assessing their schemes for quality assurance purposes. The guidance provides mathematical methods for propagating measurement uncertainties through calculations, requiring operators to assign realistic uncertainty values and demonstrate overall uncertainty below specified thresholds. This updates technical procedures for an existing certification scheme that validates CHP efficiency claims.
DESNZ published a simple guide to the Combined Heat and Power Quality Assurance (CHPQA) programme, explaining application procedures for CHP certification. The guide covers registration, submission requirements for simple schemes (≤2 MWe, single reciprocating engine) versus complex schemes, and certification timescales. It also details how certified CHP operators can claim Climate Change Levy exemption, Carbon Price Support exemption, and renewable support through ROCs, CfDs, and RHI.
Government grants £64 million to Associated British Ports for design and engineering work to develop Port Talbot as a floating offshore wind port. The port would support 4.5 GW of Celtic Sea floating wind projects following Crown Estate seabed leasing. Funding is subject to Subsidy Advice Unit approval and final government sign-off.
Ofgem sets out five options for redesigning transmission network charges to steer investment towards Strategic Spatial Energy Plan locations, ranging from tweaking existing TNUoS to auctioning connection capacity by zone. Charges would apply to new generators, demand, and storage. Responses by 26 May 2026, reforms targeted for 2029.
Vestas announces conditional plans for a Scottish wind component factory creating 500 jobs, contingent on AR7 and AR8 orders. DESNZ launches a trial allowing suppliers to offer discounted electricity on windy days when wind farms would otherwise be constrained off. The factory announcement follows AR7 securing 8.4GW of offshore wind capacity.
DESNZ launched an interactive map showing clean energy projects supported by government funding since July 2024, including National Wealth Fund and Great British Energy investments. The map displays investment amounts and job figures for featured projects. More projects will be added as they are announced.
Government sets strategic framework for expanding interconnection beyond current 10.3GW operational capacity and 7.45GW under development, moving from market-led Cap and Floor regime to planned approach aligned with NESO's Strategic Spatial Energy Plan due autumn 2027. New delivery framework will identify optimal location, capacity and connecting countries for interconnectors and Offshore Hybrid Assets combining cables with wind farms.
Ofgem proposes strategic planning-led interconnector development where NESO identifies projects and government sets delivery and financing arrangements. The consultation closes 1 May 2026. This shifts from developer-led merchant models to centrally planned interconnection aligned with wider system needs.
DESNZ proposes a bill discount scheme offering households within 500 metres of new transmission infrastructure £250 annually for 10 years, funded by an obligation on all electricity suppliers who will pass costs to all customers via bills. The scheme covers new overhead lines and substations from 2027, with eligible households identified automatically via their MPAN, plus an opt-in route for those on commercial meters or off-grid. Administrative costs are socialised across all billpayers while benefits flow only to those hosting infrastructure.
Government introduces regulations requiring majority of new homes in England to have solar panels fitted as standard from 2028 under the Future Homes Standard, removes regulatory barriers for plug-in solar panels under 800W to connect via domestic sockets without electrician installation, and launches trial allowing suppliers to offer discounted electricity on windy days in constrained areas instead of paying wind farms to switch off. The Future Homes Standard also mandates low-carbon heating systems like heat pumps in new builds, while plug-in solar will be available in shops within months through retailers like Lidl and Amazon.
DESNZ launches consultation on a £5 billion Warm Homes Fund offering government-backed loans and investments for domestic solar, batteries, heat pumps, and energy efficiency measures. The fund targets upfront cost barriers through financial transactions rather than grants. Consultation closes on an unspecified date seeking views from installers, manufacturers, housing providers, and finance institutions on fund design and target groups.
DESNZ seeks evidence on nuclear third party liability limits for Small Modular Reactors and Advanced Modular Reactors, which by default face the same €1.2bn liability requirement as gigawatt-scale plants by 2027. The consultation runs until 1 June 2026 and covers both electricity-generating SMRs and non-electric applications like hydrogen production or industrial heat. Current liability arrangements require operators to secure insurance cover up to their liability limit, with lower limits available only for prescribed lower-risk sites.
Government and Ofgem establish a data domain model with four coordinators (NESO, RECCo, Elexon) to standardise energy system digitalisation, replacing the current fragmented initiative-led approach. The framework introduces a digitalisation coordination function and mandates interoperability between Data Sharing Infrastructure (DSI) and Consumer Consent Service (CCS). Implementation begins immediately with interim governance, moving to full coordination function by 2028-29.
DESNZ proposes to expand the exclusion zone around Eskdalemuir seismic array from 10km to 15km radius, blocking around 0.8GW of onshore wind pipeline but unlocking 3-6GW between 28-50km through updated seismic measurement methodology. The consultation introduces a Seismic Impact Limit of 0.004614-0.005479 nm/√MW to ration remaining seismic 'headroom' and requires determining authorities to refuse applications that breach thresholds rather than treat MOD objections as mere material considerations.
DESNZ published technical guidance and tools for UK ETS compliance, including emission factors and reporting templates for installations and aircraft operators. The collection provides operational documentation for existing carbon pricing obligations rather than policy changes.
DESNZ publishes guidance for operators on UK ETS baseline data collection and hospital/small emitter applications, covering the submission window from 1 April to 30 June 2025. The guidance explains how to complete templates for the 2027-2030 allocation period and applies to installations seeking free allocation or USE/HSE status. Operators must submit verified baseline data reports to avoid losing free allocation eligibility.
Government confirms administrative changes to CfD scheme allowing NESO to correct assessment errors and consider new evidence for non-material application omissions at appeal stage. Changes include project-specific pauses when qualification decisions are reversed, refined pending application rules, and new procedures for floating offshore wind projects. Regulations will be amended before AR8 opens, with detailed arrangements set in Contract Allocation Framework.
DESNZ published its methodology for converting renewable capacity into generation estimates and 'homes powered' figures used in government communications. The department applies standardised load factors from CfD Round 7 frameworks, accounts for grid losses using DUKES data, and compares results against median household consumption rather than mean to avoid skewing from high-consumption households.
DESNZ consults on revising secondary legislation and planning guidance for managing wind turbine interference around the Eskdalemuir seismic array. The seismic array, used for nuclear test detection, creates exclusion zones that restrict onshore wind development in parts of southern Scotland. Scottish Renewables has developed an industry tool to help manage interference.
Ofgem published its administrative schedule for issuing Renewables Obligation Certificates (ROCs) for the period April 2026 to March 2027. Generators must submit monthly output data by the end of the second month following generation, with ROCs issued roughly three weeks later. The schedule maintains existing deadlines with no changes to ROC allocation or pricing mechanisms.
NESO published updated Connections Reform methodologies in March 2026, extending the Evidence Submission Window closure beyond July 29, 2025 due to portal issues and query response delays. The methodologies cover the Gate 2 Two-way Queue (G2TWQ) process, including network design criteria, project designation rules, and gate progression requirements.
Ofgem publishes quarterly and annual timetables for the Offtaker of Last Resort levelisation process covering April 2026 to March 2027. The schedule sets deadlines for BPPA generation data submission, invoice distribution, payment collection and distribution across four quarterly periods and one annual reconciliation. Levelisation only occurs if a Backstop Power Purchase Agreement is active in the preceding year.
The Warm Homes Plan commits £15bn over 2025-2028 to upgrade 5 million homes with heat pumps, solar panels, and insulation, targeting 450,000 annual heat pump installations by 2030. The plan combines capital grants for low-income households with minimum energy efficiency standards for rental properties, funded through general taxation rather than energy bills. The programme represents the largest capital allocation to home energy efficiency to date.
DESNZ proposes extending permitted development rights to allow businesses, schools and farms in England to install onshore wind turbines up to 30 metres without planning permission. The proposal removes the current restriction limiting these rights to small domestic turbines only. Implementation timing is not specified.
DESNZ proposes new permitted development rights for non-domestic wind turbines up to 30m tip height and 200m² swept area, allowing single turbines on farms, businesses and public sites without planning applications. The proposal requires prior approval from local planning authorities for siting and amenity impacts, with buffer distances of tip height plus 10% from site boundaries and ten times rotor diameter from neighbouring homes. Consultation closes 10 June 2026 with policy expected in autumn.
DESNZ publishes updated levelised cost estimates (LCOE) for electricity generation technologies, with significant upward revisions for offshore wind and gas plants due to supply chain pressures and commodity price increases. Solar and onshore wind costs remain relatively stable. Hurdle rates increase 1-2 percentage points across all technologies, while carbon price assumptions no longer converge to the social cost of carbon, reducing long-term costs for gas generation.
DESNZ commissioned Lucy Yu to review AI deployment in electricity networks, examining applications across grid planning, operations, and management. The review will map current AI applications, identify deployment barriers, assess system benefits and risks, and provide recommendations by Summer 2026. The scope covers transmission and distribution applications, regulatory landscape, and enabling conditions like data access and testing environments.
Energy suppliers must reduce domestic tariffs from April 2026, receiving government funding for 75% of Renewables Obligation costs (£1.4bn annually) while removing Energy Company Obligation costs following ECO4/GBIS scheme closure. RO tariff reductions apply via volumetric discounts or automatic adjustments for price-capped customers, with suppliers required to execute deeds and maintain qualifying bank accounts for grant payments. The scheme runs until March 2029 with quarterly reconciliation based on actual versus assumed domestic supply volumes.
Consultation on expanding permitted development rights for onshore wind turbines in England. Proposes relaxing planning restrictions that have effectively blocked new onshore wind since 2015.
The Chancellor's Mais Lecture outlines a strategy for investment-led growth through an 'active and strategic state', including energy security measures and industrial policy. Key energy commitments include lifting the onshore wind ban, investing in offshore wind and nuclear (Sizewell C, small modular reactors), and implementing the Fingleton Review to accelerate nuclear deployment. The government claims these measures have reduced gas imports by 17% since 2021 and enabled a £117 average reduction in the energy price cap.
This guidance document explains the UK Emissions Trading Scheme, which applies to power generation installations above 20MW thermal input, energy-intensive industries, and aviation. Operators must surrender allowances annually by 30 April to cover verified emissions. Free allocation is provided to reduce carbon leakage risk, with a baseline data collection exercise running 1 April - 30 June 2025 for the next allocation period.
DESNZ published UN location codes for offshore installations as part of extending the UK ETS to maritime activities from 2026. The guidance lists installations that will be subject to carbon pricing under the amended trading scheme. This supports implementation of the draft Greenhouse Gas Emissions Trading Scheme (Amendment) (Extension to Maritime Activities) Order 2026.
The government sets out a £2.5bn fusion strategy over five years, primarily funding STEP prototype plant development at West Burton and R&D facilities. The strategy aims to develop UK fusion industrial capability through UKAEA Group restructuring and private sector partnerships. Most funding flows to construction and engineering contracts rather than direct energy market interventions.
UK Industrial Fusion Solutions appoints ILIOS as construction partner for the STEP Fusion programme at West Burton under a £200 million contract. The consortium will act as principal design and build contractor for the prototype fusion plant, managing all construction aspects through to planned operation in 2040. Construction is expected to support up to 8,000 onsite jobs at peak.
The 2025 Capacity Market T-4 auction cleared at £27.10/kW/year for delivery in 2029/30, procuring 40.1GW of capacity. Deloitte's audit confirms NESO ran the auction in compliance with market rules, with 254 generators awarded contracts ranging from gas plants to battery storage to demand response.
Ofgem consultation on Long Duration Electricity Storage Draft Special Licence Conditions. These are the licence-level terms LDES cap-and-floor projects will operate under after appointment.
DESNZ announces plug-in solar panels will be made available in the UK for the first time, alongside bringing forward the next renewables auction to July 2026 and accelerating £130m of devolved funding for home upgrades to additional mayors. The plug-in solar allows households to connect portable panels directly to mains sockets without grid export arrangements.
NESO issues mandatory Information Request Notice to transmission-level demand customers and co-located generation projects to gather detailed project readiness data. The IRN requires complete responses by 13 April 2025, building on last year's voluntary Call for Input which saw 460% queue growth. NESO uses statutory information gathering powers to compile evidence for Ofgem's Demand Connections Reform programme.
NESO published results from its November 2025 Call for Input on demand connections, receiving 243 responses representing over 90GW of demand capability. Data centres dominate at 55% of total capacity (50.8GW), with 81% of all projects willing to accept alternative connection arrangements like phased or non-firm connections for earlier dates. Connection dates span 2027-2035, with 40% of projects seeking pre-2030 energisation.
DESNZ publishes monthly statistics covering electricity generation, consumption, and retail prices alongside broader energy production and trade data. The January 2026 data includes electricity market fundamentals, retail price movements, and EU comparative pricing. This is routine statistical publication providing market context rather than announcing policy changes.
DESNZ opens applications for CCUS projects seeking connection to the East Coast Cluster Teesside network by 2032. Expression of interest deadline is 10 March 2026, with full applications due 10 April 2026. The process allocates remaining capacity at the Endurance offshore storage site through competitive assessment.
Government accepts 47 recommendations from the Nuclear Regulatory Review to consolidate nuclear regulation, merge ONR and DNSR by 2028, and establish a Nuclear Commission to resolve regulatory conflicts. Implementation commits to delivery by end-2027 subject to legislative timelines, with a Nuclear Regulatory Implementation Panel to hold government and industry accountable.
Government accepts Nuclear Regulatory Taskforce recommendations to streamline nuclear planning and regulation, with all reforms to be completed by end-2027. The taskforce found an 'overly complex' and 'bureaucratic' system that favoured process over outcomes. New £65.6m funding will train 500 doctoral students across 4 intakes, quadrupling current nuclear PhD numbers.
Ofgem decision on the market arrangements regime for Multi-Purpose Interconnectors (MPIs). MPIs combine interconnector capacity with offshore wind generation in a single asset, similar to offshore hybrid assets.
UK ETS covers 25% of territorial emissions across power, industry and aviation, creating carbon price through cap-and-trade system. Authority expanding to maritime (July 2026), waste incineration (2028), and greenhouse gas removals (2029). May 2025 UK-EU agreement to work towards linking schemes, with negotiations begun December 2025.
DESNZ proposes to simplify UK ETS permitting for cross-boundary CCS pipelines by reducing the number of permits required from multiple regulators to a maximum of two. Current rules require separate permits from each jurisdiction a pipeline crosses (England, Scotland, Wales, Northern Ireland, and offshore), plus monitoring infrastructure at each boundary. The consultation runs until 4 June 2026.
Government proposes using new statutory powers to accelerate grid connections for strategic demand projects, including data centres and AI Growth Zones, through queue management reforms, capacity reservation, and reallocation mechanisms. The proposals would impose higher financial requirements on data centres to address speculation in the 125GW demand queue, while creating prioritisation systems for government-identified strategic projects. Consultation closes 15 April 2026.
DESNZ publishes quarterly data showing UK renewable electricity generation reached 35.5 TWh in Q3 2025, up 7.4% year-on-year, driven by 2.9 GW of new solar capacity and 1.0 GW of offshore wind. Total UK energy production hit a record low at 21.2 million tonnes oil equivalent, down 2.5%, with nuclear generation falling 28% due to maintenance outages. Renewables achieved 54.7% of electricity generation, just below Q2's record.
DESNZ published its Winter 2025 Public Attitudes Tracker, a triannual survey of 3,283 UK adults covering awareness and attitudes toward energy policies. The survey shows declining concern about climate change (77%, down from 79% in Summer 2025) and declining support for renewable energy (78%, down from 87% in Autumn 2021). Nuclear energy support held steady at 44%, while heat pump installation likelihood among owner-occupiers dropped to 22% for air source and 12% for ground source systems.
DESNZ publishes annual statistics on MCS-certified domestic battery installations covering April 2025 to March 2026, including capacity and cost data. The MCS database captures installations eligible for various support schemes and provides the primary dataset for tracking behind-the-meter storage deployment. This data informs policy development on distributed storage and network impact assessments.
DESNZ published monthly cost per kW data for solar PV installations during 2025/26, marking this as 'Official Statistics in Development'. The data covers installation costs by month across the financial year. This provides market intelligence on solar deployment costs as the sector scales.
DESNZ launches the Advanced Nuclear Framework enabling privately-led SMR, AMR and MMR projects through a government Pipeline process offering limited endorsement and potential revenue support. Projects submit detailed plans across technology, finance, siting, and operations for structured assessment by DESNZ and Great British Energy-Nuclear. Pipeline membership provides a statement of credibility, access to discussions on CfD-style revenue support and high-impact low-probability risk protections, plus potential National Wealth Fund investment.
DESNZ will enable government to prioritise strategically important demand projects (AI data centres, industrial sites) in transmission connection queues while requiring higher financial commitments from developers to tackle speculative applications. The demand connection queue grew 460% in six months to June 2025, creating waits up to 15 years. Ofgem will consult on increased deposits or fees for queue participants who miss milestones.
DESNZ opens consultation on CfD contract changes to implement Clean Industry Bonus reforms for Allocation Round 8. The consultation closes on 1 April 2026. This follows earlier announcements of the Clean Industry Bonus mechanism designed to incentivise domestic supply chain investment.
DESNZ published updated guidance on participating in UK ETS auctions and secondary markets, incorporating the April 2026 auction reserve price increase from £22 to £28. The guidance details auction clearing mechanisms, cost containment triggers, and eligibility criteria for market participants. ICE Futures Europe continues as the auction platform provider.
DESNZ publishes lists of companies receiving exemptions from CfD/RO costs (as at March 2026) and compensation for RO/FIT costs (up to 2018). The 2026 exemption list covers 521 companies across manufacturing and processing sectors. The 2018 compensation list covers 23 companies, primarily in energy-intensive industries.
The 2025 T-1 capacity auction for delivery year 2026/27 cleared at £5.00/kW/year with 7,192 MW awarded across 15 rounds over two days in March 2026. The clearing price represents a 95% fall from the previous year's £100/kW result. NESO's auction process received clean assurance from Deloitte with no compliance breaches identified.
The government requires energy suppliers to take all reasonable steps to complete domestic smart meter installation by 2030, replacing the current targets framework which expires end-2025. Suppliers must resolve smart meters operating in traditional mode within 90 days and pre-emptively replace assets before 2G/3G shutdown by 2033. Annual deployment plans with binding milestones become mandatory from January 2027.
Ofgem, NESO and DESNZ seek stakeholder interest in joining a Charging Transitional Arrangements Group (CTAG) to inform whether transitional or legacy arrangements are needed ahead of transmission charging reforms. Part of the Reformed National Pricing programme that followed the July 2025 decision to retain a single national wholesale price.
DESNZ published February 2026 solar PV deployment statistics. This is a routine monthly data release tracking installed solar capacity in the UK. The publication provides market participants with deployment data for commercial and policy analysis.
The Clean Industry Bonus allocates extra CfD revenue support to offshore wind projects that invest in sustainable supply chains, with applications opening 13-21 May 2026. Projects must meet minimum standards including Fair Work Charter signatory status, Industrial Growth Plan contributions, and specified investment thresholds. Performance-related adjustments apply to CfD payments if minimum standards are not met, with bonus payments withheld if non-financial standards fail.
DESNZ published a factsheet reassuring that UK gas supply faces no immediate disruption from Middle East conflict, with Qatar accounting for only 1% of UK gas imports in 2025. The energy price cap will fall 7% (£117 annually) from April-June 2026. The government reiterates its clean energy transition messaging while confirming existing North Sea production will continue via Transitional Energy Certificates.
NESO updates queue management guidance with new milestone calculation methods and evidence requirements for transmission connections. The guidance incorporates recent code changes CMP434 and CMP435 that implement connections reform, establishing eight mandatory milestones that developers must meet or face termination. Projects must now demonstrate progression through planning, land rights, construction planning, financial commitment, and construction initiation phases with specific evidence requirements and timelines calculated backwards from completion dates.
NESO publishes BSUoS charging data including fixed tariffs, monthly forecasts, and payment calendars through March 2026. BSUoS charges recover balancing costs and are paid by final demand customers only since April 2023 reforms. Current fixed tariff structure replaced variable charges following CMP308 and CMP361 implementation.
Ofgem consults on Early Construction Funding (ECF) for eight Scottish Hydro Electric Transmission projects under the ASTI re-opener, allowing permitted early-construction activity to begin ahead of full planning consents.
DESNZ proposes contract amendments to implement Clean Industry Bonus reforms for Allocation Round 8, adding workforce protection measures, skills investment criteria, and extending the bonus scheme to onshore wind for AR9. The consultation runs until March 2026 with final contracts expected before AR8 opens. Changes also include hybrid metering contract amendments affecting all CfD agreements.
NESO publishes detailed guidance for its Enduring Auction Capability (EAC) platform, which conducts co-optimised day-ahead procurement for frequency response and reserve services. The platform uses N-SIDE's algorithm to clear Dynamic Response, Quick Reserve, and Balancing Reserve services together at 14:00 daily, with Slow Reserve to be added in March 2026. Results are published via data portal with monthly archiving for sell orders and annual archiving for other datasets.
Elexon's CFO highlights that non-commodity costs rather than wholesale prices now drive consumer bill pressure, with Market-wide Half-Hourly Settlement progressing from 3 million to target 30 million meters. Smart meter penetration has reached 60-70%, enabling time-of-use tariffs and flexibility services.
NESO has issued Gate 2 offers to transmission-connected projects under connections reform, with customers having 90 days to accept or reject offers. Projects that reject Gate 2 offers revert to Gate 1 agreements, triggering security release processes under CUSC Section 18. Technical queries must be submitted within 4 weeks of receiving offers, with transmission operators providing 2-4 week response times.
Ofgem Project Assessment of the Hackney Waltham Cross Upgrade Project (HWUP). Standard ASTI project assessment for the North London transmission reinforcement.
Ofgem consultation on Early Construction Funding and licence modification for the Tealing-Kincardine Upgrade Project. Part of the ASTI Scotland-area transmission reinforcements.
NESO has raised a modification to assess whether offshore wind farms of 90MW or more should be required to have two AC transformers at their grid connection point. The current SQSS rule 7.7.1.1 effectively mandates dual transformers for these capacities. The proposal will go to SQSS Panel on 24 March 2026.
NESO has issued the Go-Live Notice for Slow Reserve service, opening the Enduring Auction Capability (EAC) auction on 17 March with the first auction on 31 March 2026. This triggers the end of STOR service at 05:00 on 1 April 2026. Slow Reserve provides frequency management through post-fault energy balancing, requiring units to respond within 15 minutes with minimum 1MW capability.
DESNZ sets the CfD Allocation Round 8 Supply Chain Plan application window from 1-7 April 2026 for large-scale solar and onshore wind projects (300MW+). Prospective applicants must email their intention to submit during the week before the window opens. The department will provide a secure online platform for electronic submissions.
NESO publishes webinar schedules and archive materials for Connections Reform, including upcoming sessions on advancement fees and securities (25 March), plus archived recordings from 2025-2026 covering queue management, offer processes, and evidence submission guidance. The materials support customers navigating the reformed connections process with regular updates on timelines, portal functionality, and technical requirements.
NESO publishes standard weekly Operational Transparency Forum materials - presentation slides and recordings from system operations discussions. The forum runs every Wednesday at 11am, covering recent operational actions in the Electricity National Control Centre.
NESO launches a call for input on Reformed National Pricing (RNP) proposals to reform dispatch arrangements and electricity market design, with responses due 14 April 2026. The RNP programme aims to strengthen investment signals, improve operational efficiency, and reduce constraint costs within Great Britain's retained single national wholesale market. Government will provide legislation as required for timely delivery.
NESO proposes Grid Code changes to implement 'Regional Restoration Plans' following the previous GC0156 modification, standardising how transmission operators coordinate during system blackout recovery. The proposal affects all transmission system operators, transmission owners, network operators and generators, requiring workgroup development under standard governance. Cross-code impacts extend to STC and DCODE.
NESO publishes mock auction results for its Enhanced Ancillary Services (EAC) platform, showing weekly test runs of response-reserve procurements ahead of live operations. The dataset includes buy orders, sell orders, results by unit, and summary statistics from mock auctions scheduled for late September 2023. Live EAC auctions will run daily with results published on a separate page.
Ofgem consultation on equipping the OFTO regime for the future. Sets out proposed changes to position OFTO for the next phase of offshore transmission build.
NESO publishes quarterly TNUoS tariff data across eight categories including transmission demand residual charges, generator tariffs (onshore and offshore), and embedded export tariffs. The dataset provides granular breakdown of network use charges that recover transmission system costs from users. Files are updated quarterly when tariffs are published, with data available via API and CSV download.
Ofgem consultation on the Project Assessment for the Bramford to Twinstead transmission upgrade. Bramford-Twinstead is part of the East Anglia transmission reinforcement programme.
NESO publishes weekly Capacity Market Register data tracking all applications, successful bidders, and capacity agreements across auctions. The register includes component-level detail and historical changes, updated with one-hour frequency. Four CSV datasets cover current status and change histories for both components and Capacity Market Units.
NESO publishes planning methodology documents and consultation responses for Strategic Spatial Energy Plan (SSEP), Centralised Strategic Network Plan (CSNP), and transitional network planning. The SSEP draft methodology consultation closed 20 January 2025, with final methodology expected spring 2025 following government and Ofgem approval. CSNP methodology consultation launches Q2 2025, with tCSNP2 methodology submission to Ofgem by 31 March 2025.
NESO publishes comprehensive guidance for its Dynamic Services suite — Dynamic Containment (DC), Dynamic Moderation (DM) and Dynamic Regulation (DR) — which provide frequency response to keep the grid within 50Hz ±1%. The services require response times from 0.5 seconds (DC/DM) to 2 seconds (DR), with delivery duration from 15 minutes (DC) to 60 minutes (DR). Procurement occurs via the EAC platform with results published on the NESO Data Portal.
CMP465 proposes to allow affected generators to reset their construction progression milestones (M5-M8) back to what they would have been without the G2tWQ (Gate 2 to the West Queue) extension granted until 2026. The modification follows NESO's decision to extend G2tWQ connection offers beyond their original 2025 deadline. It proceeds under urgent modification procedures with Authority decision pending.
NESO publishes its C9 statements page, consolidating balancing service procurement guidelines, methodology statements, and consultation documents previously held under the C16 licence condition. The page hosts current versions of five methodology statements (Procurement Guidelines v28, Balancing Principles v26, BSAD v26, ABSVD v20, SMAF v19) effective from September 2025, plus historical versions and consultation records dating back to 2009. A 2026-27 consultation is open until February 6, 2026.
DESNZ proposes comprehensive cost recovery fees for energy infrastructure planning applications to replace current non-cost-reflective charges. The fixed fee model aims to generate revenue for resourcing planning decisions, with annual fee reviews and potential indicative timescales for applications without statutory deadlines. Consultation responses are due by spring 2026 with implementation following.
DESNZ proposes eight refinements to Contracts for Difference (CfD) terms ahead of Allocation Round 8, including permanent restrictions on re-bidding surrendered capacity, hybrid metering arrangements to reduce costs, and excluding applications with Gate 1 connection offers. The consultation runs until early 2025 with changes taking effect for AR8. Other proposals include extending floating offshore wind delivery timelines, strengthening enforcement against distribution-connected generators gaming merchant revenues, and creating a new deepwater offshore wind technology category.
DESNZ proposes extending CfD eligibility to existing nuclear plants seeking lifetime extensions, requiring legislation changes to enable subsidised investment in plant refurbishments. The consultation runs until early 2025 with no specified implementation timeline. This would apply CfD strike prices to plants that currently operate merchant, potentially covering substantial refurbishment costs at Sizewell B and other AGR stations nearing end of design life.
Ofgem directs that NESO's Network Options Assessment (NOA) and Electricity Ten Year Statement (ETYS) publication move from January to June 2026, giving NESO time to incorporate Connections Reform into the second transitional Centralised Strategic Network Plan refresh (tCSNP2r). The NOA for interconnectors is suspended pending the Strategic Spatial Energy Plan and CSNP.
Ofgem publishes Final Determinations for the RIIO-3 price control covering Electricity Transmission, Gas Distribution and Gas Transmission for the period 1 April 2026 to 31 March 2031. RIIO-3 succeeds RIIO-2 which ends on 31 March 2026.
DESNZ proposes a unified biomass sustainability framework to standardise criteria across sectors including power generation, applying consistent carbon and ecological standards to all biomass use. The framework would affect existing biomass generators and future CfD allocations. The consultation runs until early 2025 with implementation expected by 2026.
DESNZ proposes changes to Capacity Market rules affecting CfD projects, Long Duration Electricity Storage, and delivery assurance ahead of 2026 prequalification. Key changes include allowing CfD units strategic participation in CM, setting LDES Cap and Floor eligibility criteria, and raising termination fees by 30% or simplifying to single £45,500/MW fee. Multiple Price Capacity Market eligibility tightens with higher CapEx thresholds and disconnection certificate requirements.
CMP466 enables generators to recover costs of providing Electromagnetic Transient (EMT) models required under Grid Code GC0168. The modification follows after CMP456 and addresses the financial burden placed on existing generators, particularly older plant with complex systems. CUSC Panel initially rejected urgency but assigned high priority status on 5 February 2026.
Ofgem consults on Green Volt Offshore Windfarm Limited's application for Authority consent to exercise statutory rights of entry on land.
Ofgem consultation on revisions proposed by the Electricity Market Reform Delivery Body to the Relevant Balancing arrangements within the Capacity Market.
DESNZ reviews the 2011 CO2 storage infrastructure access regulations to support CCUS market development. The consultation examines whether third-party access rules need updating to reflect current policy and support first-of-a-kind CCUS projects. This follows government commitments to establish industrial carbon capture clusters.
DESNZ proposes policy actions to maintain gas system security during energy transition, including infrastructure capacity requirements, resilience measures, and commercial model changes for LNG terminals, interconnectors, and storage. The consultation covers maintaining peak-day capacity and ensuring infrastructure remains commercially viable as gas demand declines. This follows the June 2025 commitment to public engagement on gas system transition.
DESNZ consults on operational cost budgets for LCCC and ESC covering 2026/27 to 2028/29, with resulting levy rates to be applied to electricity suppliers. The consultation seeks views on administrative costs for running CfD and capacity market settlement functions. Costs are recovered through levies on licensed electricity suppliers who pass them to consumers.
DESNZ proposes expanding the UK Emissions Trading Scheme to cover a share of emissions from international maritime voyages to and from UK ports. The consultation seeks views on scheme scope, cap adjustment mechanisms, future IMO alignment, and impacts. This follows generally supportive responses to November 2024 maritime ETS expansion proposals.
Ofgem decides on Early Construction Funding for six NGET projects under the ASTI re-opener: GWNC, PTC1/PPTNO, CGNC, EDN2, Brinsworth to High Marnham (EDEU) and Norwich to Tilbury (AENC, ATNC). Allowances adjusted via Special Condition 3.41 to permit NGET's ECF expenditure request.
NESO proposes increasing minimum reactive power requirements for full converter technology Power Park Modules operating below maximum active power output through Grid Code modification GC0184. The Grid Code Review Panel rejected the proposal on 13 November 2025, stating it did not identify a clear defect. The proposer is considering next steps.
NESO proposes reviewing voltage limits that apply during operational timescales and introducing flexibility around these constraints. The modification affects transmission owners, NESO, distribution networks, generators, and directly connected customers. Cross-code changes to Grid Code and STC may be required.
DESNZ proposes urgent changes to Capacity Market Rules regarding locational changes of capacity units, requiring rule modifications as soon as possible. The consultation aims to enhance scheme functionality and strengthen delivery assurance. This follows a separate broader consultation on Capacity Market Rules published recently.
DESNZ proposes switching from RPI to CPI for inflation indexation of Renewable Obligation buy-out prices and Feed-in Tariff payments. CPI typically runs 0.5-1 percentage point below RPI over time. The change would reduce annual uplifts for both schemes, affecting existing contract holders.
Government proposes switching inflation indexation for Renewables Obligation buy-out prices and Feed-in Tariff rates from RPI to CPI. Both schemes use inflation adjustments to maintain real value of payments over time. The change would reduce annual increases since CPI typically runs 0.5-1 percentage point below RPI.
Ofgem approved CMP463, freezing Specific Onshore Expansion Factors at 2025/26 levels from 1 April 2026. The modification prevents large unexpected increases in these TNUoS charges that would have resulted from the 2026 Price Control. The freeze is temporary, pending a fundamental TNUoS review.
Ofgem minded-to position to approve the Original Proposal of CUSC modification CMP448, which introduces a progression commitment fee in the connections process. 40 responses received (25 non-confidential).
Ofgem consults on licence modifications giving NESO a statutory obligation to produce Regional Energy Strategic Plans (RESPs), with parallel obligations on DNOs and gas distribution networks to participate. Guidance covers RESP methodology, governance and information-sharing.
Ofgem consults on pre-construction funding and licence modifications for Scottish Hydro Electric Transmission.
DESNZ proposes changes to Capacity Market prequalification rules for the 2026 auction, aiming to align the scheme with decarbonisation goals and improve functionality. The consultation covers reforms to existing market rules that determine which capacity providers can participate and under what terms. Specific changes are not detailed in the summary provided.
DESNZ seeks views on allowing hydrogen-to-power generation into the Capacity Market and on revising interconnector de-rating factors. The consultation runs through early 2026 with decisions expected before the next capacity auction. This would expand the technology mix eligible for capacity payments beyond current fossil and renewable generators.
Ofgem notice: Powertree (Sidings Road) Limited applies for an electricity generation licence. Routine administrative notice.
NESO now publishes real-time reserve availability and utilisation prices for non-balancing mechanism services through its Open Balancing Platform. Quick Reserve service data is live, with Slow Reserve data to follow when that service launches. This creates transparency on ancillary service costs and provider behaviour previously hidden from the market.
Ofgem notice: Powertree (Taylor Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: BSSL East Ayrshire 1 Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Ecopower Suffolk Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Attix CIC has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Daines BESS Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: EP Eggborough New Energy Developments Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem consultation on introducing a general ongoing fit and proper requirement for licensees. Currently fit and proper assessment is primarily a licensing-stage requirement; this would extend the obligation through the lifetime of the licence.
Ofgem notice: Powertree (Foxwood Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Vicarage Drove Energy Centre Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Bramley Solar Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Ninfield Grid Solutions Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Tasway Energy Park Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem consults on Material Scope Change and Early Construction Funding treatment within the Accelerated Strategic Transmission Investment (ASTI) regime.
Ofgem statutory consultation on proposed modifications to Offshore Transmission Owner (OFTO) Licences.
Ofgem notice: Enso Green Holdings R Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Enso Green Holdings A Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Zeusa Energy Ltd applies for an electricity supply licence. Routine administrative notice.
Ofgem consultation on ways forward for an OFTO Build early competition model. Examines how to introduce competitive procurement into the offshore transmission build phase.
Ofgem notice: AGR Networks Limited has been granted an electricity distribution licence. Routine administrative notice.
Ofgem notice: Weagle Group Limited applies for an electricity supply licence. Routine administrative notice.
Ofgem notice: TI LIRIC LIMITED has been granted an electricity interconnector licence. Routine administrative notice.
Ofgem notice: Abbotshaugh Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Yaxley Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Moss Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Hamilton Lane Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Aldon Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Salford Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Nu-Link Interconnector UK Ltd has had an electricity interconnector licence revoked. Routine administrative notice.
Ofgem notice: Bodelwyddan Solar & Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Ashton Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem consultation on the energy price cap methodology: contracts for difference review. Examines how CfD costs are reflected in the price cap.
Ofgem decides on amendments to the energy price cap methodology to account for the Nuclear Regulated Asset Base (RAB) allowance. The Nuclear RAB scheme funds Sizewell C through a consumer-funded levy.
Ofgem notice: Care Power (Newtonwood) Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Care Power (North Tawton) Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Care Power (Brook Farm) Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Elements Green Trent Ltd applies for an electricity generation licence. Routine administrative notice.
DESNZ proposes reforms to the Clean Industry Bonus (CIB) for CfD Allocation Round 8, introducing workforce protection and skills investment criteria, extending eligibility to onshore wind, and implementing technical improvements. The CIB provides additional revenue to renewable projects that meet domestic supply chain requirements. The consultation seeks views on these changes ahead of AR8.
Ofgem notice: Uniper Global Commodities SE applies for an electricity supply licence. Routine administrative notice.
Ofgem notice: Care Power (Barnsley) Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Northwich Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Nevern Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Grid Line Power Networks Ltd applies for an electricity distribution licence. Routine administrative notice.
Ofgem notice: Ogmore Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Care Power (Wolverhampton) Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Camblesforth Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Care Power (Berkeley) Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Care Power (Brentwood) Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Loddon Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Irwell Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Kiln Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Marden Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Larigan Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Care Power (Erskine) Ltd applies for an electricity generation licence. Routine administrative notice.
DESNZ seeks evidence on coordinating smart meter installations with low carbon technology deployments to reduce field capacity constraints and improve consumer experience. The call for evidence focuses on installation efficiency, field capacity constraints in certain locations, and local coordination opportunities in areas with low smart meter penetration. No specific mechanisms or changes are proposed.
NESO proposes to socialise transmission connection asset costs and cap customer contributions through CUSC modification CMP460. The modification seeks to create more certain charging by reducing direct customer charges for connection infrastructure. Workgroup consultation runs 28 January to 18 February 2026.
Ofgem notice: Sutton Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Immingham Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Corpower Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Cryobattery One Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Hull Reserve Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Goring Power Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Blaguegate Power Limited applies for an electricity generation licence. Routine administrative notice.
DESNZ consults on transitioning carbon capture, utilisation and storage networks from government-led development to market-led operation. The consultation seeks industry views on challenges hindering CO2 transport and storage network commercialisation. No specific timeline or cost allocation mechanisms are detailed.
Ofgem notice: Cadoxton Reserve Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Cynon Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Clyne Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Dafen Reserve Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Culvery Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Bury Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Banbury Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem decides on the Centralised Strategic Network Plan (CSNP) guidance covering NESO's expectations and methodology requirements. The CSNP will be an independent, coordinated, long-term whole-system plan for electricity and natural gas transmission and for hydrogen transport and storage. 21 responses received.
Ofgem notice: Elements Green Staythorpe BESS Ltd has been granted an electricity generation licence. Routine administrative notice.
DESNZ proposes to transfer governance of technical and security standards for smart energy devices from government to industry-led arrangements under Elexon's management through Balancing and Settlement Code modifications. The governance would manage requirements for domestic EV chargers, heat pumps, and other flexibility devices. Costs would be recovered through BSC levies on industry participants.
Ofgem notice: Kitland Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem opens review of energy system cost allocation and recovery, examining how network, wholesale, policy, and retail costs are recovered from domestic and non-domestic consumers. The review considers alternatives to current standing charge structure, including block tariffs, time-of-use charging, location-based pricing, and ability-to-pay options. Consultation closes 24 September 2025 with policy options expected end-2025.
Ofgem notice: AGR Solar 2 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Daines BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Cerulean Winds Aspen Project Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: S & C Energy Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Tesla Energy Ventures Limited applies for an electricity supply licence. Routine administrative notice.
Ofgem approves Early Construction Funding for the Sea Link electricity transmission project (NOA code SCD1). Decision taken under NGET's transmission licence Special Condition 3.41 (the ASTI Re-opener).
Ofgem consults on new Regulatory Instructions and Guidance (RIGs) for the Sizewell C nuclear licensee, the regulated entity that will hold the licence for the project funded under the Nuclear RAB model.
DESNZ launches consultation on improving visibility of distributed energy assets including EV chargers, solar panels, heat pumps and batteries through better data collection from installation to operation. The consultation seeks views on strategic data flows and options for mandating asset registration. No specific mechanisms or costs are proposed at this stage.
Ofgem consults on the further evolution of the Offshore Transmission Owner (OFTO) regime as a mature asset class, building on more than a decade of operation since the first competitive tender round.
Ofgem notice: E.ON UK Network Assets Limited has been granted an electricity distribution licence. Routine administrative notice.
Ofgem policy consultation on the licence modifications and guidance document needed to give NESO a statutory obligation to produce Regional Energy Strategic Plans (RESPs), with parallel obligations on DNOs and GDNs.
NESO is revising the Obligatory Reactive Power Service (ORPS) compensation methodology through CUSC modification CMP457, moving away from gas price-based rates. The Standard Governance workgroup process begins after 13 November 2025, following unanimous CUSC Panel approval in October. Current ORPS costs reflect gas prices despite the shift to low-carbon generation requiring grid stability services.
Ofgem notice: Whaddon Farm Solar Park Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem decision on OFTO extension and evolution of the mature asset class. Operative outcome of the December 2024 consultation.
Ofgem rejects CUSC modification CMP444, which would have placed upper and lower limits on the absolute £/kW Peak, Year-Round Shared and Year-Round Not Shared Wider generation TNUoS tariffs. 25 responses received including four confidential. Ofgem concludes none of the modification proposals would better facilitate the Applicable CUSC Objectives.
Ofgem notice: Abbotshaugh Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Sandon Brook Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Exeter Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Sundon Storage Limited has been granted an electricity generation licence. Routine administrative notice.
NESO introduces Grid Code modification GC0183 requiring generators and interconnectors to notify their intended availability during severe space weather events. Ofgem approved the modification on 20 November 2025 with implementation on 4 December. The modification proceeded through urgent procedures due to national security implications.
Ofgem notice: Birch Solar Park Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ consults on streamlining land rights and consents processes for electricity network infrastructure to enable faster deployment. The consultation follows a 2022 call for evidence and targets reducing costs, complexity and delays that currently hinder network projects. Minor changes to existing infrastructure will be fast-tracked to free resources for complex cases requiring detailed scrutiny.
Ofgem notice: Fern Brook Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Meadow Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Sphere Energy Connect Limited applies for an electricity distribution licence. Routine administrative notice.
Ofgem notice: SSE Eggborough Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Vicarage Drove Energy Centre Limited applies for an electricity generation licence. Routine administrative notice.
DESNZ proposes updates to technical guidance for assessing wind turbine noise emissions, which local authorities use to evaluate onshore wind planning applications. The guidance aims to align with current evidence, turbine technology developments, and noise assessment methodologies. No specific noise thresholds or assessment parameters are detailed in this preliminary notice.
Ofgem notice: Npower Limited has had an electricity supply licence revoked. Routine administrative notice.
Ofgem notice: Attix CIC applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Orsted East Irish Sea Transmission Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: TGC Emerald Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Wednesbury Power Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: EP Eggborough New Energy Developments Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Sandwell Power Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: SpectrumReserve5 Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Spectrumreserve4 Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Itchen Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Power Initiatives (2) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Point Energy EM Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Reliable Generation Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Gresley Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Lime Kilns Energy Centre Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: FlexibleGridPower3 Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Greys Hall Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Energyfarm Allt Domhain Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: GCP Generation Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Camblesforth Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Farmoor Energy Limited has had an electricity supply licence revoked. Routine administrative notice.
Ofgem notice: Brecon Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem decides on the financial framework for Long Duration Electricity Storage (LDES) projects under Window 1 of the cap-and-floor scheme. Changes from consultation include reducing competitive bid parameters from five to two, raising the revenue-sharing rate above the cap from 10% to 30%, pared-back cost and delivery incentives, and updated inflation indexation. 35 responses received.
Ofgem notice: Basildon Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Beaufort Power Limited has been granted an electricity generation licence. Routine administrative notice.
CMP456 creates a cost recovery mechanism for generators required to produce Electro Magnetic Transient (EMT) models under GC0168, shifting the financial burden from plant operators to system users. The modification addresses 'significant' costs imposed on older generators with multiple discrete systems who gain no direct benefit from producing these grid stability models. Authority rejected urgent processing in December 2024, with the CUSC Panel designating this high priority in January 2025.
Ofgem notice: Field New Deer Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Rigifa Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Long Stratton Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Coulomb Energy Supply Limited has been granted a restriction of an electricity supply licence. Routine administrative notice.
Ofgem notice: Field Netherton Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem decides on updated guidance for gas and electricity licence applications. The new guidance reorganises and clarifies the application process for prospective licensees.
Ofgem notice: Berkswell Battery Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Fyrish Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: 24 Power Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem decision on Capacity Market change proposals CP371, CP376, CP377, CP378, CP381. Operative outcome of the January 2025 statutory consultation.
Ofgem notice: Frodsham Solar Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Edge Utility Networks Limited applies for an electricity distribution licence. Routine administrative notice.
Ofgem notice: Dunfermline Solar Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Bicker Drove Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Welbar Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Cadzow Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem decides on the Multi-Criteria Assessment (MCA) Framework for evaluating Long Duration Electricity Storage projects applying for the cap-and-floor regime under Window 1. 44 responses received; broad stakeholder support.
DESNZ consults on drafting changes to CfD Standard Terms and Conditions to allow unconsented fixed-bottom offshore wind projects to bid in Allocation Round 7. The changes would relax eligibility requirements that currently require projects to have consents before bidding. AR7 is scheduled to open in summer 2025.
Ofgem notice: West Burton C Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ proposes mandatory community benefit funds for low carbon energy infrastructure, requiring developers to provide monetary or in-kind contributions to local communities. The scheme would require primary legislation to grant regulation-making powers. Separately, the consultation reviews whether to exercise existing powers in the Infrastructure Act 2015 to mandate community shared ownership of renewable projects.
Ofgem update and summary of responses on the Transmission Constraint Licence Condition (TCLC) call for input. TCLC restricts generators from exploiting market power during constrained periods.
Ofgem notice: S & C Energy Limited applies for an electricity generation licence. Routine administrative notice.
DESNZ commissioned an independent review of greenhouse gas removals (GGRs), including BECCS and DACCS, to assess how these technologies can help meet net zero targets by 2050. Dr Alan Whitehead chairs the review, which includes stakeholder roundtables and a public call for evidence. The review will produce recommendations for government consideration, but government will not respond to individual submissions.
Ofgem consultation on NGET licence modifications for Large Onshore Transmission Investment. Provides the licence machinery for large onshore transmission projects under NGET's licence.
Ofgem determinations on Tier 2 Capacity Market disputes for Delivery Year 2024-25. Tier 2 disputes are appeals against Capacity Market decisions on individual CMUs (Capacity Market Units).
Ofgem notice: Group Utilities Limited applies for an electricity supply licence. Routine administrative notice.
Ofgem notice: Blackdyke BESS Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ consults on mandating solar canopies on new outdoor car parks above an unspecified size threshold, covering public and private sites. The consultation also seeks views on expanding permitted development rights for EV charging infrastructure to reduce planning barriers. The solar mandate would apply to new car parks, with exploration of retrofitting existing facilities.
Ofgem notice: Sundon Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem consults on modifications to the Electricity System Operator Licence to enable Early Competition in onshore electricity transmission. Companion to the April 2025 Regulations under which a CATO can be appointed to design, finance, build and operate transmission assets.
DESNZ and Ofgem propose standard licence conditions for code managers and update CMA appeals process following Energy Act 2023. Code managers will replace industry panels with licensed entities that set budgets, recommend modifications to Ofgem, and align codes with Ofgem's Strategic Direction Statement. Appeals trigger when Ofgem disagrees with code manager recommendations, replacing current panel-based triggers.
Ofgem notice: Getlink Projects 2 Limited has been granted an electricity interconnector licence. Routine administrative notice.
CMP453 proposes to charge BSUoS on net rather than gross flows for BSC Trading Units, meaning customers who export more than they import would not pay system balancing costs. The CUSC Panel recommended the change by majority on 31 October 2025, with the Final Modification Report sent to Ofgem on 11 November 2025. The modification follows Standard Governance through a Workgroup process.
Ofgem notice: JBM Solar Projects 2 Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: JBM Solar Projects 17 Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: JBM Solar Projects 24 Limited applies for an electricity generation licence. Routine administrative notice.
DESNZ consults on revenue support regulations for Greenhouse Gas Removals and Power Bioenergy with Carbon Capture and Storage, covering contracting procedures, information publication, counterparty functions, and eligibility criteria. The consultation targets project developers, carbon market participants, and investors. This follows the government's broader CCUS and negative emissions strategy but provides implementation detail rather than policy direction.
DESNZ is revising National Policy Statements EN-1, EN-3, and EN-5 to align with Clean Power 2030 targets, including bringing onshore wind back into the Nationally Significant Infrastructure Projects regime. The consultation on material changes runs until 23 June 2025. These NPSs guide Planning Inspectorate decisions on major energy infrastructure applications.
Ofgem consults on updated guidance for gas and electricity licence applications, reorganising existing content and adding new sections on Ofgem's expectations of applicants.
Ofgem notice: Elements Green Renewables SPV001 Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Elements Green Staythorpe BESS Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Bristol Community Energy Limited has had an electricity generation licence revoked. Routine administrative notice.
Ofgem notice: Euston Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Eggborough Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Whaddon Farm Solar Park Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Rebel Energy Supply Limited has had an electricity supply licence revoked. Routine administrative notice.
Ofgem notice: Exeter Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Glendevon Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Yorkshire Reactive Power Limited applies for an electricity transmission licence. Routine administrative notice.
Ofgem notice: TI LIRIC LIMITED applies for an electricity interconnector licence. Routine administrative notice.
Ofgem notice: Hasland Green Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Melksham Calne Green Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Bramford Green Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem investigation into Moray Offshore Windfarm (East) Limited's compliance with the Transmission Constraint Licence Condition (TCLC). TCLC restricts generators from exploiting market power during constrained periods.
Ofgem notice: HEIT LR Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: HEIT BF Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Energyfarm Allt Domhain Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem publishes the eligibility assessment outcome for Long Duration Electricity Storage Window 1. The eligibility filter decides which applicants progress to the substantive cap-and-floor assessment.
Ofgem decision on further detailed regime parameters for the Offshore Hybrid Asset (OHA) pilot scheme.
Ofgem notice: Glen Earrach Energy Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Spennymoor Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Aludra BESS Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Frodsham Solar Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Sandon Brook Solar Park Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Fern Brook Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem decides on the policy framework for the Regional Energy Strategic Plan (RESP). Introduces RESPs as the regional strategic-planning instrument delivered by NESO, convening regional stakeholders around a common view of how the energy system will develop.
Ofgem notice: Birch Solar Park Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Meadow Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
DESNZ seeks technical evidence on hydrogen-to-power projects that can deploy by 2030 without large-scale hydrogen infrastructure. The consultation targets developers with existing H2P deployment plans. No policy changes or funding commitments are proposed — this is information gathering for future policy development.
Ofgem notice: Redlake Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Botein BESS Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Leoda Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Nevern Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Wharf Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Wolverhampton Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Westwood Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: St Asaph Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Warrington Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Selby Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Corringham Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Marden Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Tillingham Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Loddon Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Northwich Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Ogmore Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Cadoxton Reserve Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: E.ON UK Battery Storage Systems Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Cynon Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Clyne Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Irwell Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Dafen Reserve Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Hull Reserve Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Immingham Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Kiln Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Woolaston Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Amalgamated Smart Metering Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Harbourne Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Whittington Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Larigan Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Banbury Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Bury Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Culvery Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Sookholme Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (The Wood Yard) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Riby Street) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Bicker Drove Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Bodelwyddan Solar & Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Abergelli Farm BESS Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Enderby BESS Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Barr Hall Farm BESS Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Fanny House Farm BESS Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem statement on the Drax investigation into Renewables Obligation annual profiling reports. Drax was found to have misreported biomass sustainability characteristics; the company agreed to a £25m redress payment. The RO subsidies themselves remain in payment.
Ofgem notice: Almholme BESS Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Stenson Lane BESS Limited has been granted an electricity generation licence. Routine administrative notice.
GC0178 seeks to specify limits on temporary overvoltage events and clarify generator obligations during such events. The modification is proceeding through Standard Governance and has been paused to allow appointment of a consultant to scope the work. High impact parties include generators, transmission owners, and interconnectors.
Ofgem notice: Mercia Power Response (Nottingham Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Holditch Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Durham RP Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem Long Duration Electricity Storage technical document. Sets out the technical parameters and definitions for LDES cap-and-floor applications.
Ofgem notice: Mercia Power Response (Bradberry Balk Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Blackdyke BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Hallam Way) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Hatton) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Ilkeston Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Westfield SM Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Graphite Way) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Asher Lane 2) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Cuckoo Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Dunfermline Solar Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Chesterfield Road) Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ seeks views on supporting oil and gas sector transition in the North Sea, framed as a 'managed transition' rather than immediate cessation. The consultation addresses how to balance existing hydrocarbon extraction with offshore wind development using the same seabed and infrastructure. No specific mechanisms or cost allocations are detailed in this initial announcement.
Ofgem notice: E.ON UK Network Assets Limited applies for an electricity distribution licence. Routine administrative notice.
Ofgem notice: Fearna PSH Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem consultation on Bowdun Offshore Wind Farm's application for Authority consent. Earlier instance of the Bowdun application.
Ofgem notice: Craig Watch Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: The Droves Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Green Hill Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Light Valley Solar Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Keith Ltd applies for an electricity generation licence. Routine administrative notice.
DESNZ proposes relaxing CfD eligibility to allow offshore wind projects without full planning consent to bid in AR7, opening summer 2025. The consultation considers extending CfD contract terms beyond the current 15 years and giving the Secretary of State greater visibility over sealed bid information to set budgets. AR7 budget allocation will use different criteria for fixed-bottom offshore wind.
Ofgem notice: Smart Pay Energy Ltd has been granted an electricity supply licence. Routine administrative notice.
Ofgem notice: Scorpia Energy Supply Limited has been granted an electricity supply licence. Routine administrative notice.
Ofgem notice: SpectrumReserve5 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Broxburn Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Wednesbury Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: TGC Emerald Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Reliable Generation Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Sandwell Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Spectrumreserve4 Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Point Energy EM Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Coddington 10 Renewables Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Power Initiatives (2) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Lime Kilns Energy Centre Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Greys Hall Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Itchen Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Gresley Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Hartmoor Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: GCP Generation Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Benbrack Wind Farm Limited has been granted an electricity generation licence. Routine administrative notice.
The UK ETS Authority proposes extending the emissions trading scheme beyond its current 31 December 2030 expiry into a Phase II from 1 January 2031. The consultation considers whether to allow banking of emissions allowances between phases and the duration of Phase II. This continues the existing carbon pricing framework that affects all fossil fuel generators in the power sector.
Ofgem notice: Basildon Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Beaufort Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: FlexibleGridPower3 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: EP UK Power Development II Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Brecon Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: West Burton C Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Vital Energi Power Networks Limited has been granted an electricity distribution licence. Routine administrative notice.
Ofgem notice: Elements Green Renewables SPV 001 Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Northwold Solar Farm Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ opens consultation on National Policy Statement EN-7, which will set planning policy for nuclear power stations deploying after 2025. The NPS replaces outdated planning guidance and determines how Planning Inspectorate assesses Development Consent Orders for new nuclear projects. This affects all nuclear development beyond current committed projects like Hinkley Point C and Sizewell C.
Ofgem notice: Exeter RP Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Doncaster Power (10MW) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Gridsource (Woburn Rd) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Outgang Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Fordbridge Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Euston Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (High View Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Pozitive Energy Limited has been granted a restriction of an electricity supply licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Pontefract Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: UES Asset 1 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Corringham Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Reserve Power Trading Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Spennymoor Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Sandy Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Aludra BESS Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem open letter on the approach to prioritisation of electricity transmission network charging methodology modifications.
Ofgem determination on Gwynt y Mor OFTO plc under paragraph 23 of Amended Standard Condition E12-J.
Ofgem notice: Sembcorp (Wilton Bess) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Common Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Albion Close) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Glendevon Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem consults on Early Construction Funding for the Denny Wishaw electricity transmission project and a proposed modification to the transmission licence to enable it.
Ofgem notice: Leoda Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Botein BESS Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Legacy Green Energy Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Trent BESS II Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Melksham West Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Melksham Calne Green Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: E.ON UK Battery Storage Systems Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Bramford Green Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Capella BESS Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Hasland Green Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Glen Earrach Energy Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Exergy Solutions Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Whitestone Net Zero Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Earba Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Habitat Energy Limited applies for an electricity supply licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Private Road No.5) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Wellington Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: BBD Energy Ltd applies for an electricity supply licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Manners Avenue 2) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Uskmouth Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Geddington Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Common Side Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Fulwood Road) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Green Blades Engineering Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mannington Energy Centre Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ proposes a Smart Data scheme allowing customers to share energy consumption data with authorised third parties for tariff comparison and personalised services. The consultation seeks views on scope, governance, and implementation design. No specific timeline or regulatory framework is outlined.
Ofgem statutory consultation on Capacity Market Rule change proposals CP371, CP376, CP377, CP378 and CP381. Each Change Proposal modifies Capacity Market Rules; together they form a routine batch of CM design updates.
Ofgem notice: Damsongreen Energyfarm Limited has been granted an electricity generation licence. Routine administrative notice.
NESO proposes Grid Code changes to replace Mandatory Frequency Response (MFR) with a new Real-time Dynamic Regulation service from 2026/27. The two products will run in parallel until 2029 before MFR is phased out. The Panel rejected the initial proposal in March 2026 for lacking clarity on defect and scope.
Ofgem notice: Energy Isles Shetland Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Cadzow Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Hams Lane NW BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Almholme BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Fanny House Farm BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Abergelli Farm BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Enderby BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Stenson Lane BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Barr Hall Farm BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Garth Fawr Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Slickly Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Sookholme Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Whittington Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Riby Street) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Woolaston Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (The Wood Yard) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Westfield SM Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Hatton) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Hallam Way) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Graphite Way) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Sheepwash Clean Energy Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Chesterfield Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Nottingham Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Cuckoo Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Loch Liath Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
DESNZ launches a review of Ofgem's role and powers, citing consumer protection concerns and the need for higher standards in energy markets. The review will examine the regulator's functions and delivery mechanisms. No specific timeline or scope limitations are provided.
Ofgem notice: Mercia Power Response (Asher Lane 2) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Holditch Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Light Valley Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Durham RP Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: The Droves Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Amalgamated Smart Metering Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Bradberry Balk Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Ilkeston Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem statement on its role, plan, and response to the DESNZ publication on the LDES Cap and Floor Regime. Sets out how Ofgem will operationalise the regime designed by DESNZ.
NESO releases a new dataset calculating skip rates per 30-minute period using methodology developed with LCP Delta. The data shows skip rates following each stage of exclusions as set out in their published methodology. The dataset is accompanied by an online dashboard for market participants.
Ofgem notice: Bramley Battery Storage Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ consults on adjusting free carbon allowances for industrial sectors under UK ETS, focusing on carbon leakage calculations and border adjustment impacts. The consultation proposes changes to how the Carbon Leakage List is calculated and how free allocations adjust when EU's Carbon Border Adjustment Mechanism affects UK industries. This follows a 2023 review that committed to publishing a draft leakage list.
DESNZ proposes changes to Capacity Market rules to improve demand side response (DSR) participation and delivery assurance. The consultation covers DSR technology categorisation and testing processes. The proposals aim to better integrate consumer-led flexibility within existing capacity procurement.
Ofgem consults on draft guidance for AI deployment across energy sector operations, covering safety, security, fairness and sustainability criteria. The guidance aims to streamline regulatory compliance by mapping AI use cases to existing regulatory frameworks rather than creating new rules. Consultation runs until spring 2025 with regulatory laboratory sessions in February.
Ofgem consultation on extension and evolution of OFTO as a mature asset class. Companion to the July 2025 further-evolution consultation.
Ofgem decides on modifications to the special licence conditions in the electricity transmission licences relating to Accelerated Strategic Transmission Investment (ASTI).
Ofgem consultation on Bowdun Offshore Wind Farm's application for Authority consent to exercise statutory rights.
Ofgem final determination on the Shetland enduring solution re-opener application. Determines allowed expenditure on the long-term transmission solution to connect Shetland to the GB system.
Ofgem notice: Benthead Solar Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Fearna PSH Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem ten-year review of the Capacity Market Rules. The CM has run since 2014; ten years of operation provides a body of evidence on whether the rules are delivering their intended outcomes.
Ofgem notice: Coddington 10 Renewables Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Melksham West Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem consults on NESO's request to competitively tender a sub-component of project WCN2 (a new circuit between South West Scotland and North West England) through onshore early competition. The first GB project to enter the onshore competitive tender regime for a Competitively Appointed Transmission Owner (CATO).
Ofgem notice: Broxburn Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Benbrack Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Knockcronal Wind Farm Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Earba Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: AGR Networks Limited applies for an electricity distribution licence. Routine administrative notice.
Ofgem consultation on Early Construction Funding for eight SHET electricity transmission projects under the ASTI re-opener. Decision (issued later) approved SHET's full ECF request, maintaining the minded-to position.
The UK ETS Authority proposes expanding the emissions trading scheme to cover maritime sector from 2026, applying carbon pricing to shipping fuels that currently do not reflect environmental costs. The consultation covers scope definitions, cap adjustments, operator requirements, and potential future expansion to international routes. Maritime operators would need to purchase allowances for their emissions, creating a direct carbon cost.
The consultation proposes allowing UK ETS operators to deduct CO2 from their allowance obligations when it is permanently stored via non-pipeline transport (road, rail, ship). This enables facilities without pipeline connections to access geological carbon storage while receiving ETS credits. The framework would regulate transport emissions and intermediate storage sites.
Ofgem notice: Car Duibh Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: MarramWind Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Artfield Forest Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: C & S Energy Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Beaw Field Shetland Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Green Blades Engineering Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Green Hill Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: East Pye Solar Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Wharfside Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Pontefract Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Outgang Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Reserve Power Trading Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (High View Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Northwold Solar Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Sandy Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Exeter RP Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Common Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem consults on funding transmission owners to book supply-chain capacity (cables, transformers, HVDC converters) before final certainty on project need, to compress delivery timelines for the ASTI build-out. Consumers carry the cost of the optionality upfront, with the regulator setting eligibility criteria and claw-back arrangements if commitments do not convert into delivered assets.
Ofgem notice: Mercia Power Response (Albion Close) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Fordbridge Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Cygnus Wind Transmission Limited has had an electricity generation licence revoked. Routine administrative notice.
Ofgem notice: Ecotricity (Alveston Storage) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Renesola Hercules Energy 1 Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Great Casterton Energy Park Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem Initial Project Assessment decision on the Offshore Hybrid Asset (OHA) Pilot Projects. OHAs combine interconnector capacity with offshore wind generation in a single asset (the predecessor to MPIs).
DESNZ proposes additions to CfD contracts to enable the Clean Industry Bonus mechanism, which provides extra revenue to offshore wind projects that meet supply chain sustainability criteria. The draft contract terms set out notice requirements, payment terms, and performance-related adjustments for non-delivery. The bonus operates within the existing CfD structure rather than as a separate support mechanism.
DESNZ launches the CfD Clean Industry Bonus, which provides additional revenue support to fixed and floating offshore wind projects that invest in more sustainable supply chains. The mechanism operates as an add-on to existing CfD payments, with details available on a dedicated microsite.
Ofgem notice: Capella BESS Limited applies for an electricity generation licence. Routine administrative notice.
NESO formalises a Demand Control Rotation Protocol allowing rolling blackouts for 3-24 hours during supply shortfalls, modifying Grid Code OC6. The modification affects Distribution Network Operators, NESO, and consumers, with cross-code impacts on the Distribution Code. Panel recommendation has been deferred to address Load Lock definition issues with the Energy Network Association.
CMP445 proposes to pro-rate first-year TNUoS charges for generators from their charging date rather than charging the full annual amount upfront. The modification was denied urgent treatment by the Authority in December 2024 and is proceeding through standard governance, with workgroup consultation closing 22 August 2025. The CUSC Panel placed this high on their prioritisation stack in March 2025.
Ofgem notice: Whitestone Net Zero Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: AVE 002 Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: ADV 003 Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Trent BESS II Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Legacy Green Energy Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Middleton Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Enderby Battery Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Stromar Offshore Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Private Road No.5) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Exergy Solutions Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Wellington Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Fulwood Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mannington Energy Centre Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Geddington Road) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Common Side Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mercia Power Response (Manners Avenue 2) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Scope Energy Solutions Ltd applies for an electricity supply licence. Routine administrative notice.
Ofgem Request for Information to monitor requirements for derogated renewable standard variable tariffs.
Ofgem is issuing its routine annual Request for Information to suppliers that hold a derogation from the default tariff cap for renewable standard variable tariffs, covering the period 1 April 2023 to 31 March 2024. Derogated suppliers must return a quantitative and qualitative cost template by 6 January 2025 to renewablederogations@ofgem.gov.uk. This is a compliance monitoring exercise under an existing derogation regime, not a change to the cap or the derogation criteria.
DESNZ proposes reforms to Scotland's electricity infrastructure consenting under the Electricity Act 1989, targeting projects over 50MW onshore and 1MW offshore within 12 nautical miles. The consultation seeks to modernise consent processes and strengthen community involvement requirements. Both UK and Scottish governments agree that removing inefficiencies from the 1989 Act is the primary route to accelerating deployment for Clean Power 2030.
Ofgem notice: Loudwater Bess Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Basildon Bess Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem consultation on the onshore electricity transmission Early Competition commercial framework. Sets out the commercial terms under which CATOs will design, finance, build and operate transmission assets.
Ofgem notice: Coulomb Energy Supply Limited applies for a restriction of an electricity supply licence. Routine administrative notice.
Ofgem notice: SIMEC Uskmouth Power Limited has had an electricity generation licence revoked. Routine administrative notice.
Ofgem notice: Swangate Energy Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Alcemi Storage Developments 4 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Damsongreen Energyfarm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Holmston Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Whitebirk Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Orsted Power Sales (UK) Limited has had an electricity supply licence revoked. Routine administrative notice.
Ofgem notice: Field Drum Farm Ltd has been granted an electricity generation licence. Routine administrative notice.
DESNZ proposes changes to the Capacity Market to maintain security of supply while enabling unabated gas plants to decarbonise. The consultation combines proposals for rule changes with a call for evidence on future market design. No specific mechanisms or parameters are detailed in this announcement.
Ofgem notice: Gridsource (Woburn Rd) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: RWE Renewables UK Onshore Wind Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Net Zero Teesside Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Cowley Baldon Green Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Walpole Green Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: MarramWind Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: KXP Immingham Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Ecotricity (Alveston Storage) Limited applies for an electricity generation licence. Routine administrative notice.
CMP442 allows generators to fix their TNUoS charges against NESO's forecasted tariffs, converting variable transmission charges into predictable costs. The modification follows standard governance through workgroup process, with first workgroup meeting planned for 16 December 2024. CUSC Panel initially prioritised this as high but downgraded to medium priority in February 2025 following Ofgem's transmission charging modification prioritisation guidance.
Ofgem consultation on further detailed regime parameters for the Offshore Hybrid Asset pilot scheme. Predecessor to the April 2025 decision.
DESNZ/Ofgem consult on the draft Electricity (Early-Model Competitive Tenders for Onshore Transmission Licences) Regulations 2024. These Regulations are the statutory underpinning for the CATO (Competitively Appointed Transmission Owner) regime.
Ofgem notice: Conrad (Cleveleys) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lytham) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Neston) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: EP UK Power Development II Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Witham) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Battery Monk Fryston Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Staythorpe Power Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Grain) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Bhlaraidh Extension Wind Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Ferrybridge Battery Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Fiddlers Ferry Battery Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Halesworth) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Putnoe) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Oldbury) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Stevenage A) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sandon) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Stevenage B) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Rochester) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Newark) Limited has been granted an electricity generation licence. Routine administrative notice.
CMP441 proposes to align the timing for de-energising non-embedded hydrogen electrolysers with embedded ones, addressing a credit risk discrepancy. The modification was unanimously recommended by the CUSC Panel in December 2024 but was sent back by the Authority in July 2025 for reconsideration. The Panel has now deprioritised it to low priority status.
Ofgem notice: Conrad (Lillyhall) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Redbourn) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lowestoft) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Crewkerne) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Fleetwood) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem proposed changes to the Request for Information used to monitor requirements for derogated renewable standard variable tariffs.
Ofgem notice: Conrad (Castle Bromwich) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bishopstoke) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bletchley) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bridgwater) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Middleton Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bilsham) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Indaver Rivenhall Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Yaxley) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sundon) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Wootton) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: C & S Energy Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Runcorn) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Priestgill Wind Farm Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Minehead) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: OTM Power Generation Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sittingbourne) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bispham) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Middlewich) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Billericay) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Melksham) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Moorfield) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sudmeadow) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Plymouth Rock) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Rake Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Water Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Trafalgar Park) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Redfield) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Drove) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem determinations on Tier 2 Contracts for Difference disputes arising from Allocation Round outcomes.
DESNZ will publish AR6 CfD allocation results on 3 September 2024, following National Grid ESO notification to applicants. The bulletin provides administrative details about stakeholder mailing list management and GDPR compliance.
Ofgem notice: Conrad (Letchworth) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lester Way) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Zenobe Eccles Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Barton Hill) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Goose House Lane) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Down Barn Farm) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Alcoa) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Dowlais) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Wrexham) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Enderby Battery Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Yeovil) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Plymouth) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sandycroft) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Redscar) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Purfleet) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Middleton Junction) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Langage) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Matching) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Loudwater BESS Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lower Dunton) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Basildon Bess Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Calne) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Heybridge) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Flint) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Chatterley) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Caernarfon) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Hawarden) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem statutory consultation on proposed electricity transmission licence modifications for the Accelerated Strategic Transmission Investment (ASTI) framework.
Ofgem conclusion and assessment of annual monitoring requirements for derogated renewable standards.
Ofgem notice: Conrad (Bilston) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Arncott) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Benfleet) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Gatwick Electric Forecourt Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Ampthill) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Flexion Energy SPV 2 Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Lime Down Solar Park Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem publishes its decision on draft guidance for the Future Energy Pathways (FEP) that NESO must produce. FEP is the scenario-modelling framework that feeds into network planning.
Ofgem decision on Early Construction Funding for the North London Hackney Waltham Cross Upgrade Project (HWUP) and corresponding transmission licence modifications.
Ofgem consultation on Early Construction Funding and licence modification for the North West Wales transmission upgrade (NOA codes PTC1 and PTNO).
Ofgem finalises guidance requiring NESO to produce strategic 'Future Energy Pathways' instead of illustrative scenarios, with pathways showing what must happen to meet net zero by 2050. The guidance mandates whole-system modelling including gas constraints, network limitations in the short term, and granular regional data. NESO must publish major pathways every three years to inform the Centralised Strategic Network Plan, with methodology subject to Ofgem approval.
The sealed bid window for AR6 CfD allocation has closed and NESO will run the auction process. Results will be notified to applicants on 3-4 September 2024, followed by public release on GOV.UK. The allocation process will be followed by an independent audit.
Ofgem notice: HEIT PW2 Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: HEIT PW Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: HEIT RH Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: National Grid Nautilus Limited applies for an Electricity Interconnector licence. Routine administrative notice.
National Grid ESO has opened the sealed bid window for CfD Allocation Round 6, running from 5-9 August 2024. This follows the formal notice of auction being issued to qualifying applicants.
Ofgem notice: Net Zero Teesside Power Limited applies for an electricity generation licence. Routine administrative notice.
The government increased AR6 CfD budget to over £1.5 billion, up 50% from the March allocation. Offshore wind receives £1.1 billion (£300m increase), established technologies get £185m (£65m increase), and floating offshore wind and emerging technologies receive £270m (£165m increase) including £15m ringfenced for tidal stream.
Ofgem notice: Bhlaraidh Extension Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem decision allowing National Grid ESO to submit the Network Options Assessment methodology by 31 March 2025 and publish the updated NOA report by 31 January 2026. Followed by the December 2025 further-extension decision.
Ofgem notice: GNNR Ltd has been granted an Electricity Generation licence. Routine administrative notice.
Ofgem notice: NPower Commercial Gas Limited has been granted restriction of electricity supply licence. Routine administrative notice.
Ofgem has completed the appeals process for CfD Allocation Round 6, notifying applicants of final outcomes on their eligibility challenges. Projects that remained non-qualifying after National Grid ESO's initial review could appeal to Ofgem. The process now moves to scenario 5 in the AR6 timeline.
Ofgem notice: Field Holmston Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Whitebirk Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Field Drum Farm Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem describes its 2024/25 audit programmes for the Renewables Obligation (RO), Renewable Electricity Guarantees of Origin (REGO) and Feed-in Tariffs (FIT) schemes. Together these provide nearly £10bn of support for renewable generation. Audits run a targeted and a statistical programme under both RO and FIT.
Ofgem notice: Pulse Clean Energy SPV Johnson 3 Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Johnson 1 Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Johnson 2 Limited has been granted an electricity generation licence. Routine administrative notice.
NESO publishes 0-14 day ahead wind forecasts for all wind farms providing real-time operational metering data. Forecasts use evaluated operational capacity based on recent actual production levels from SCADA telemetry rather than nameplate capacity. The dataset covers both national and individual wind farm level predictions.
Ofgem notice: SSE Staythorpe Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Ferrybridge Battery Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Fiddlers Ferry Battery Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: SSE Battery Monk Fryston Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: ADV 003 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Watchet) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Carrog Storage Facility Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem consults on changes to the Initial Project Assessment of the Nautilus Offshore Hybrid Asset (interconnector + offshore wind combined project).
Ofgem notice: Feckenham Storage Facility Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: AVE 002 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Cleveleys) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lytham) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Witham) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Cilfyndd Grid Services Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Neston) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Grain) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Priestgill Wind Farm Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Swangate Energy Storage Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Halesworth) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: OTM Power Generation Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Minehead) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Runcorn) Limited applies for an Electricity Generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sittingbourne) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Eccles Energy Centre Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Kilmarnock Energy Centre Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Middlewich) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Green Generation Energy Networks Cymru Limited has been granted an electricity distribution licence. Routine administrative notice.
Ofgem notice: Conrad (Melksham) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Wootton) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Yaxley) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Redbourn) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Rochester) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bispham) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sundon) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Billericay) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Stevenage A) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sandon) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Wharfside Power Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Stevenage B) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Fleetwood) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Newark) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lowestoft) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lillyhall) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Putnoe) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Oldbury) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: East Claydon Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Loch Kemp Storage Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bishopstoke) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bletchley) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Castle Bromwich) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Crewkerne) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bilsham) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bridgwater) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Water Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Rake Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sudmeadow) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Drove) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Trafalgar Park) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Redfield) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Barton Hill) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Dowlais) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Alcoa) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Goose House Lane) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Moorfield) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Plymouth Rock) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lester Way) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Down Barn Farm) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Letchworth) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Yeovil) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Wrexham) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Plymouth) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Purfleet) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Matching) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Middleton Junction) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Redscar) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Sandycroft) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Calne) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Caernarfon) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Langage) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Chatterley) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Flint) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Lower Dunton) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Hawarden) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Heybridge) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: HEIT PW2 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: HEIT PW Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: HEIT RH Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Ampthill) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Arncott) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Benfleet) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Bilston) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Zenobe Eccles Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Doncaster Power (10MW) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Gatwick Electric Forecourt Ltd applies for an electricity generation licence. Routine administrative notice.
AR6 CfD allocation round extends to maximum timeline (scenario 5) after Ofgem received appeals from non-qualifying applicants between 12-18 June. Ofgem will consider appeals until 24 July 2024, with ESO observations due by 26 June.
Ofgem notice: GNNR Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Flexion Energy SPV 2 Ltd applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Balbougie Energy Centre II Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Conrad (Watchet) Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Aldustria (Launceston) Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem decision on guidance under the Transmission Constraint Licence Condition (TCLC). TCLC restricts generators from exploiting market power during constrained periods.
Ofgem notice: Cilfynydd Grid Services Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Mossy Hill Shetland Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: HD777FRY Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: HD144WHI Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: HD639LEG Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Johnson 1 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Johnson 2 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Johnson 3 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Flexion Energy SPV 1 Ltd has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Flexion Energy SPV 3 Ltd has been granted an electricity generation licence. Routine administrative notice.
AR6 CfD allocation round runs to timeline scenario 3 after one or more non-qualifying applicants requested review by 28 May 2024. National Grid ESO will complete reviews by 11 June 2024. General election on 4 July 2024 may affect timeline for round conclusion scheduled for summer.
Ofgem opinion that Beatrice Offshore Windfarm is compliant with the Transmission Connection and Use of System Code (TCLC) requirements.
Ofgem notice: RWE Renewables UK Solar and Storage Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ proposes integrating greenhouse gas removals (GGRs) into the UK Emissions Trading Scheme, allowing carbon removal credits to offset emissions within the carbon pricing system. The consultation covers engineered removals and potentially nature-based solutions, with decisions on cap policy, allowance design, and permanence requirements. This extends the UK ETS beyond direct emissions to include negative emissions technologies.
DESNZ proposes expanding the UK ETS to cover waste incineration facilities, adding carbon costs to energy-from-waste operations. The consultation closes 2 August 2024 and seeks views on scope, thresholds, monitoring requirements, and cap adjustments. This affects waste-to-energy plants that generate electricity as a byproduct of incineration.
Ofgem notice: Lightsource SPV 192 Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Kilmarnock Energy Centre Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Eccles Energy Centre Limited applies for an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Franklin Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Rubin Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Stargoose Clean Energy Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Watt Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Anderson Limited has been granted an electricity generation licence. Routine administrative notice.
Ofgem notice: UC Energy Ltd has been granted an electricity supply (non-domestic) licence. Routine administrative notice.
Ofgem notice: Pulse Clean Energy SPV Bell Limited has been granted an electricity generation licence. Routine administrative notice.
DESNZ begins scoping for a new Fusion Energy National Policy Statement to streamline planning consent for commercial fusion facilities. This is the first of two consultations, focusing on policy approach before drafting the actual NPS. The consultation runs for 8 weeks from May 2024.
NESO proposes requiring Transmission Owners to provide detailed Electromagnetic Transient (EMT) and Root Mean Square (RMS) models for grid stability analysis as inverter-based resources replace synchronous generation. The modification addresses control interaction risks and oscillation threats from the changing power system characteristics. Workgroups are paused pending approval of related CUSC modification GC0168.
Ofgem statutory consultation on adding Section F to the Generation Licence Standard Conditions. Section F introduces additional obligations on licensed generators.
NESO releases historical and forecast profile dates used to convert Cardinal Point forecasts into half-hourly demand forecasts from 2018 to 14 days ahead. Profile dates match forecast dates based on weather, embedded generation, seasonal patterns, and special events. These dates update as weather forecasts improve closer to real time.
Ofgem consultation on Early Construction Funding for the North London Hackney Waltham Cross Upgrade Project (HWUP). Predecessor to the August 2024 ECF decision and February 2026 Project Assessment.
The CfD AR6 application window closed on 19 April 2024, with National Grid ESO now reviewing submitted applications against qualification criteria until 20 May 2024. This is a routine procedural update on the allocation round timeline.
Ofgem consultation on initial proposals for an OFTO Build model to deliver non-radial offshore transmission. Predecessor to the OFTO build model policy update decision.
OpTIC replaces the Transport component of TNUoS with an economic market model that creates transmission charges based on assumed optimal network investment in a zonal market structure. The proposal aims to charge generators and suppliers as if they operated in a zonal wholesale market rather than the current uniform pricing system. Workgroup activity starts Spring 2025 after the CUSC Panel prioritised it as Medium.
DESNZ proposes rule changes to prevent emissions verification deadlines from reducing Capacity Market auction liquidity. The changes include conditional deadline extensions for generators required to submit verified emissions declarations at prequalification. This addresses administrative bottlenecks that could force viable capacity out of auctions due to paperwork delays rather than economic merit.
Ofgem launched a call for input on AI use in the energy sector, seeking views on how AI should be deployed responsibly to encourage innovation while managing risks. The consultation closed on 17 May 2024 and forms part of Ofgem's response to government AI regulatory principles. This represents regulatory guidance development rather than rule-making.
Ofgem summarises stakeholder responses to its proposal for a Future Regulation Sandbox (FRS), a new policy instrument to test regulatory changes before implementation. The FRS would complement existing innovation tools including the Energy Regulation Sandbox, Fast Frank Feedback, and Strategic Innovation Fund. This is not a decision document but sets out next steps based on feedback received.
Ofgem launches a call for input on AI use in the energy sector, proposing regulatory guidance and collaboration frameworks rather than new rules. The regulator concludes existing regulation is adequate to capture AI use but wants to produce risk-based guidance tools. Responses close after an unspecified consultation period.
The RO scheme issued 108.3 million certificates in 2022-23, supporting 80.3 TWh of renewable generation equivalent to 31.8% of UK electricity supply. Suppliers presented 107.7 million ROCs (88.4% of obligation) and paid £748.6 million in buy-out funds to cover the shortfall. The scheme transferred approximately £6.4 billion from electricity bills to renewable generators through certificate values of £59.76 each.
Ofgem and DESNZ propose new licences for the National Energy System Operator (NESO), which will combine electricity system operation and gas system planning functions. NESO will hold both an Electricity System Operator licence and a Gas System Planner licence when designated as the Independent System Operator and Planner (ISOP). The consultation also proposes modifications to transmission, distribution, generation, supply, interconnector, smart meter communication, and gas transporter licences to accommodate NESO's expanded role.
Ofgem classified transmission assets for the HND South Cluster following National Grid ESO's impact assessment. The decision determines which assets are regulated under different frameworks, affecting cost recovery mechanisms for offshore transmission infrastructure. This follows the established Offshore Transmission Network Review framework for asset classification.
The sixth CfD allocation round opened on 27 March 2024. The notice provides only administrative details about the round opening and mailing list management. No specific auction parameters, budget figures, or technology-specific changes are disclosed.
Ofgem approves revisions to the Relevant Balancing Services Guidelines proposed by the Capacity Market Delivery Body for 2024. The decision letter outlines which specific changes have been accepted to the technical guidelines that determine which balancing services are relevant for capacity market participation.
Ofgem approves BSC Modification P451, updating Black Start provisions and compensation arrangements in the Balancing and Settlement Code. The modification changes how backup power restoration services are procured and paid for when the grid fails. This is a technical update to existing emergency procedures rather than a structural reform.
Ofgem has summarised responses to its October 2023 open letter on regulating independent distribution network operators (IDNOs) and set out priorities for reviewing these arrangements. The document packages stakeholder feedback into themes and establishes the regulator's agenda for potential reforms to IDNO regulation. This follows concerns about IDNO operating standards and customer service compared to traditional distribution network operators.
Ofgem announces the repayment of excess funds collected during the Offshore Transmission Tender Round 6 (TR6) aggregation exercise. The authority has decided how to return overpayments made by offshore wind developers for transmission assets. This is an administrative outcome following the TR6 procurement process.
Ofgem has approved CMP427, introducing a landowner Letter of Authority requirement for new onshore transmission connection applications under the Connection and Use of System Code (CUSC). The change takes effect from 28 March 2024. This adds a documentation requirement to the application process rather than changing substantive connection terms or costs.
Ofgem mandates Data Best Practice (DBP) Guidance integration into industry codes, targeting Central System Delivery Bodies, Code Panels, Code Administrators, and licensed entities. The guidance aims to surface, share, and make interoperable data held across the energy sector. Entities handling significant data portions face specific implementation expectations.
DESNZ finalises AR6 contract changes, barring generators supplying offshore oil and gas facilities from Private Network CfD agreements. The Milestone Delivery Date definition expands to allow extensions when Ministry of Defence radar interference mitigation confirmation is delayed. For AR7, the Sustainable Industry Reward becomes a competitive process six months before the main auction, offering extra revenue for UK supply chain investment or sustainable production methods.
DESNZ launches second REMA consultation with narrowed options for fundamental electricity market redesign. The consultation runs until May 2024 and follows the first consultation's identification of market failures in current arrangements. This represents the most significant potential reform to GB electricity markets since BETTA, with options including central dispatch, locational pricing, and enhanced market-based coordination.
DESNZ proposes amending the CfD supplier obligation regulations to enable the electricity supplier levy to fund Dispatchable Power Agreements (DPAs) for power CCUS projects. The amendment would use the existing CfD cost recovery mechanism to collect payments for a new support scheme targeting gas generation with carbon capture. This extends the supplier obligation beyond its original CfD remit.
DESNZ extends the consultation response deadline for Allocation Round 7 CfD amendments from 7 March to 11 March 2024. The extension follows the earlier-than-usual publication of AR6 statutory notices, which affected internal sign-off procedures for consultation responses. The consultation content remains unchanged.
Government sets £1 billion budget for CfD Allocation Round 6, the largest allocation round budget to date. The budget was announced in the Chancellor's Spring Budget on 6 March 2024. AR6 will support renewable energy projects through strike price guarantees.
Grid Code modification GC0168 will require certain generators and network operators to provide electromagnetic transient (EMT) models to NESO for analysis of system stability as inverter-based resources displace synchronous generation. The modification follows standard governance through a workgroup process, with high impact on generators, transmission operators, distribution networks, interconnectors and transmission owners. Timeline has been repeatedly delayed, with workgroup report submitted June 2025 but Panel requesting further legal text review.
Ofgem determinations on Tier 2 Capacity Market disputes for delivery year 2023-24. Resolves contested penalty or non-delivery charges against CM agreement holders.
Ofgem's initial project assessment of Offshore Hybrid Asset pilot projects. OHAs combine offshore wind connections with interconnector functionality, allowing cross-border power flows on the same infrastructure.
DESNZ launches a call for evidence on hydrogen and CCUS supply chains under the £960 million Green Industries Growth Accelerator fund. The consultation seeks input on manufacturing capacity and supply chain bottlenecks in these sectors. GIGA forms part of a wider £4.5 billion manufacturing package targeting strategic clean energy sectors.
NESO publishes daily forecasts of balancing reserve requirements for its 08:15 auction that procures firm positive and negative reserve from BM units for delivery between 23:00 same day and 23:00 next day. The dataset includes both medium-term approximations and detailed daily forecasts refined with wind and solar data, providing half-hourly volume requirements for each service window. Data is overwritten daily with previous entries archived, and all forecasts published after 27 February are live demand forecasts.
Ofgem rejected two Capacity Market rule change proposals (CP365 and CP366) without consultation, following review by the Capacity Market Advisory Group (CMAG). This is a procedural rejection using CMAG's new triage function, not a substantive policy decision.
Ofgem has completed its cost assessment of the Moray East offshore transmission assets as part of OFTO Tender Round 7. The assessment determines what costs 'ought to have been incurred' in developing and constructing the transmission connection, which sets the transfer value the winning OFTO bidder will pay. Grant Thornton conducted both ex-ante and ex-post reviews of the developer's actual costs.
National Grid ESO published AR6 guidance covering application processes, common errors, and allocation methodology. AR6 opens for applications on 27 March 2024. The bulletin also contains standard GDPR compliance information for the stakeholder mailing list.
DESNZ opens the registration window for AR6, the sixth CfD allocation round, with applications opening 27 March 2024. Companies must register with National Grid ESO before applying for contracts. This is a routine administrative step in the quarterly CfD allocation cycle.
DESNZ announces an online event on 22 February 2024 to brief prospective applicants on Allocation Round 6 of the CfD scheme, which opens for applications on 27 March 2024. The event runs from 10am to 1.30pm and covers round overview, contract terms, and allocation process. Registration closes 20 February at 12pm with advance questions accepted until 15 February.
DESNZ proposes a transitional support mechanism for large-scale biomass generators converting to BECCS, covering gaps between existing support ending and future BECCS contracts beginning. The mechanism would apply in specific circumstances where generators face interim periods without revenue support. No details provided on mechanism design, duration, or funding source.
DESNZ published the Exemptions Request Notice for CfD Allocation Round 6, setting out procedures for excluded generators to apply for exemption from temporary site exclusion. Generators must follow specific procedures to become eligible for AR6, which opens in March 2024. The Low Carbon Contracts Company maintains the Register of Temporary Site Exclusion.
NESO Wind Bid-Offer Acceptance (BOA) Volumes data. Operational balancing market data tracking how much wind generation has been curtailed via the balancing mechanism.
DESNZ opens consultation on CfD scheme amendments for Allocation Round 7 (opening 2025) and future rounds. Key AR7 proposals include enabling onshore wind repowering projects to bid, extending phased CfDs to floating offshore wind, and streamlining appeals processes. Longer-term considerations cover floating wind foundation innovation support, offshore transmission coordination, and inflation indexation updates.
DESNZ has opened consultation on contract drafting amendments to CfD Standard Terms and Conditions and Private Network CfD Agreement for the sixth allocation round opening March 2024. The consultation closes 30 January 2024. This affects contract terms that generators will sign following successful bids in AR6.
DESNZ issued a survey seeking feedback on whether to hold an in-person engagement event for CfD Allocation Round 6, with responses required by 5 January 2024. The previous two allocation rounds used remote engagement events. This is an administrative notice about event planning, not policy development.
DESNZ published AR6 parameters raising offshore wind strike prices and separating offshore wind into its own pot, alongside launching consultation on sustainable industry rewards for AR7. The ASP increases address the failed AR5 auction where no offshore wind projects bid. DESNZ also proposes additional CfD revenue for projects demonstrating supply chain sustainability from AR7.
DESNZ sets deadline of 27 November for developers to notify their intention to submit supply chain plans for CfD Allocation Round 6, with final submissions due 10 December. Assessment begins 11 December with feedback sessions scheduled for January 2024. The process uses Microsoft Teams for document submission and includes receipt confirmation within three days.
CMP423 proposes switching from a demand-weighted to generation-weighted Reference Node for TNUoS charging calculations. The CUSC Panel has recommended approval by majority, with the Final Modification Report sent to Ofgem on 9 December 2025. This changes how transmission charges are calculated and allocated across the network.
NESO publishes daily auction results for balancing services procured through the Enduring Auction Capability platform. The EAC platform now procures response services (Dynamic Containment, Dynamic Moderation, Dynamic Regulation) and reserve services (Balancing Reserve, Quicker Reserve). Historical results remain available through separate portals.
NESO's Grid Code modification GC0164 simplifies Operating Code No.2 to make obligations clearer for grid users. The modification has been under development since October 2023, with workgroup consultations completed and a second code administrator consultation closing March 2026. This is administrative restructuring of existing obligations rather than substantive rule changes.
NESO publishes settlement-period data on the availability and utilisation of Stability Pathfinder contracts, the procured service that supplies synchronous inertia and short-circuit level to a grid losing thermal plant. The dataset records availability and dispatch for all contracted units except Grid Forming Batteries, which deliver stability continuously while connected and so receive no control-room instruction. Long-term stability contracts carry no utilisation payment, so the data is published roughly a week after delivery.
DESNZ publishes results for CfD Allocation Round 5, with 95 clean energy projects securing contracts. The government also announces an indicative timeline for AR6, starting in six months, and publishes its response on non-price factors consultation.
CfD Allocation Round 5 sealed bid window closed, with National Grid ESO running the allocation process followed by independent audit. Results will be announced 7-8 September 2023 and published on GOV.UK. This is a routine procedural update on AR5 timing.
CMP419 proposes to revise generation transmission charging zones to include offshore wind farms connected under the Holistic Network Design, allowing these generators to pay wider transmission tariffs rather than local rates. The modification has been deprioritised from Medium-High to Low as of September 2025, with workgroup activity stalled since 2024. This follows Authority expectations from previous zoning decisions CMP324 and CMP325.
National Grid ESO has opened the sealed bid window for CfD Allocation Round 5, running from 9-15 August 2023. The auction notice has been sent to qualifying applicants who passed pre-qualification. This follows scenario five in the published AR5 timeline.
DESNZ increased the AR5 CfD budget by £22m to £227m total, allocating £20m extra to mature technologies in Pot 1 (now £190m) and £2m extra to emerging technologies in Pot 2 (now £37m). Pot 2 retains £10m ring-fenced for tidal stream projects.
DESNZ revised AR6 CfD supply chain plan scoring criteria to clarify what information constitutes 'comprehensive' supplier selection reasoning. The amendment changes Question 1.1 to require explicit procurement rationale including cost, technical considerations, and delivery feasibility. Maximum points available remain 45 for most technologies, 8 for floating offshore wind.
DESNZ has barred renewable generators supplying offshore oil and gas platforms from receiving CfD payments under Private Network agreements from AR6 onwards. The decision prevents consumer bills from subsidising renewable electricity delivered directly to offshore platforms. AR6 Supply Chain Plans and guidance are now available.
Ofgem's appeals review window for Allocation Round 5 has opened, triggering timeline scenario 5 which extends the auction process. The bulletin provides only procedural updates and GDPR compliance information for the CfD stakeholder mailing list.
LCCC published updated co-location guidance allowing CfD generators to co-locate with battery storage and hydrogen production facilities under existing contracts. The guidance clarifies permitted metering arrangements and configuration scenarios to support government targets of 1GW hydrogen by 2025 and 10GW by 2030. This implements existing CfD contract flexibility rather than changing the scheme structure.
AR5 CfD non-qualification review assessment window opens until 15 June 2023, with NESO assessing non-qualifying applications. This is a routine administrative step in the AR5 allocation round process.
DESNZ opened follow-up discussions with developers on its non-price factors consultation for CfD AR7 and beyond. AR5 applications closed on 24 April 2023, with assessment running until 24 May.
DESNZ opened a call for evidence on introducing non-price factors into CfD allocation, closing 22 May 2023. CfD Allocation Round 5 applications close 24 April 2023. The bulletin provides administrative updates on ongoing CfD processes.
CMP414 seeks to implement the workgroup solution from CMP330/CMP374 by updating CUSC transmission charging methodology. Ofgem rejected the initial proposal in July 2024 due to deficiencies, forcing reconvening of workgroups. The modification is now designated high priority with workgroups beginning October 2025.
CfD Allocation Round 5 opened for applications on 30th March 2023, closing on 24th April 2023. The bulletin provides a 25-day window for renewable generators to submit applications for strike price contracts. This represents routine operation of the established CfD allocation process.
DESNZ published a consultation on AR6 Supply Chain Plan questionnaire, running from 28 March to 2 May 2023. National Grid ESO published final guidance documents for CfD Allocation Round 5. The bulletin also requests feedback on a launch event held on 23 February 2023.
DESNZ confirmed a £205 million budget for CfD Allocation Round 5, with applications opening 30 March to 24 April 2023. The department published the final allocation framework, contract documents, and consultation response alongside the budget notice. This maintains the established CfD mechanism with unchanged fundamental structure.
DESNZ published materials from the CfD Allocation Round 5 launch event held on 23 February 2023, including slides, Q&A responses, and webinar recording. LCCC separately published guidance on applying for minor and necessary modifications to CfD Standard Terms. The EMR Delivery Body scheduled an AR5 application readiness webinar for 22 March 2023.
DESNZ announces Allocation Round 5 launch event for 23 February 2023, ahead of the round opening in March 2023. This marks the first annual CfD round following Round 4's success in 2022. The online event includes presentations from delivery partners and Q&A, with registration required by 22 February.
National Grid ESO opens registration for CfD Allocation Round 5, allowing renewable generators to register for the competitive auction process. The registration window provides access to guidance and support materials through the EMR Delivery Body Portal. This is a routine administrative step preceding the main AR5 allocation process.
DESNZ published the Exemptions Request Notice for CfD Allocation Round 5, setting procedures for generators to request exemption from temporary site exclusions. The round opens in March 2023, with exemption requests required by a specified deadline to remain eligible. Sites currently excluded are listed on the LCCC website.
DESNZ opened a consultation on proposed changes to CfD Standard Terms and Conditions for Allocation Round 5, covering six areas of contract adjustments. Changes include clarifying generator flexibility on start date delays, simplifying data requirements, updating Private Network Agreement definitions, revising interest rate calculations post-Brexit, removing BSUoS charge clauses following Ofgem's decision to stop levying these on generators, and adding supply chain plan requirements for floating offshore wind. The consultation closes 5 February 2023.
DESNZ published Allocation Round 5 parameters and a consultation on future CfD rounds. AR5 opens March 2023 with pot structure, Administrative Strike Prices, and delivery years now confirmed. The consultation on AR6 and beyond closes 7 February 2023.
DESNZ sets Supply Chain Plan application window for CfD Allocation Round 5 from 5-12 December 2022. Projects ≥300MW or floating offshore wind of any size must submit plans. Independent assessors will evaluate submissions with feedback sessions in January 2023.
CMP402 would modify CUSC Section 15 to implement Ofgem's October 2022 anticipatory investment principles for offshore generators connecting to shared transmission networks at different times. The modification has been deprioritised to low priority by the CUSC Panel as of September 2025, with no active workgroup meetings scheduled.
CMP405 proposes to separate TNUoS demand charges into year-round locational signals and peak security signals, charging storage that imports outside Triad periods while rewarding it during other times. The modification has been deprioritised as low priority by CUSC Panel despite proposer requests for urgency, with Ofgem rejecting urgent treatment in January 2025. Panel confirmed low priority status in March and September 2025, effectively stalling progress.
NESO proposes reviewing restrictions on loss of power infeed risk for offshore DC converter outages under SQSS modification GSR030. The modification has been in workgroup since October 2022, with the latest workgroup scheduled for March 2026. The proposal was split in November 2025, with defect 1 becoming separate modification GSR034.
DESNZ published a draft timeline for CfD Allocation Round 5, scheduled to begin March 2023. This implements the February 2022 commitment to run CfD auctions annually instead of every two years. The timeline remains indicative pending final confirmation.
CMP397 makes technical changes to CUSC exhibits to support CMP316's co-located generation rules. The modification received unanimous panel support in May 2024 and awaits Ofgem decision by September 2025. This is administrative housekeeping required to implement the substantive co-location framework.
DESNZ announced two seminars on CfD Supply Chain Plans for August and September 2022, covering the assessment process and questionnaire changes for AR5. The seminars target developers, suppliers and investors involved in CfD projects. Registration closes at 12pm on 19 August for the first session and 2 September for the second.
The fourth CfD auction allocated contracts to 93 projects totalling nearly 11GW of capacity, almost double the previous round in 2019. Offshore wind strike prices have fallen 70% since the first auction in 2015. Technologies included offshore wind, onshore wind, solar, and for the first time tidal stream and floating offshore wind.
NESO proposes reviewing demand connection criteria in the transmission network security standards (NETS SQSS) to align with distribution network security standard EREC P2/7. The review covers how embedded generation, demand side response, storage and active network management contribute to demand security. The workgroup process has been running since June 2022 with next meeting scheduled for March 2026.
DESNZ published a routine administrative notice about CfD stakeholder communications, including data protection requirements and mailing list management. The notice contains no policy content — only procedures for opting in and out of the CfD stakeholder contact list. An update on Allocation Round 4 progress was published separately on the dedicated microsite.
DESNZ published a routine administrative update directing CfD stakeholders to an Allocation Round 4 progress report on a separate microsite. The bulletin contains standard data protection notices for the CfD stakeholder mailing list.
DESNZ issued routine administrative notices for CfD Allocation Round 4, including a progress update and a webinar announcement on Initial Conditions Precedent scheduled for 7 July 2022. The bulletin provides no substantive policy or procedural changes to the CfD scheme.
Ofgem removes BSUoS charges from generators from 1 April 2023, shifting system balancing costs entirely to demand. CfD projects in Allocation Round 4 will have strike prices adjusted downward from that date to reflect the removal of this cost. The change implements code modification CMP308.
DESNZ issued an administrative bulletin updating the CfD Allocation Round 4 microsite. The bulletin consists entirely of data protection notices and contact list management instructions.
NESO publishes 4-day forecasts of Dynamic Containment requirements for frequency response services, using demand, inertia and loss forecasts. The methodology estimates both high and low frequency response volumes needed to secure the largest credible system loss. Actual day-ahead requirements may differ based on real-time optimisation and interconnector flow changes.
DESNZ issued a routine CfD stakeholder bulletin providing an update on Allocation Round 4 progress and requesting feedback on the AR4 microsite. The bulletin contains no substantive policy content or market changes. Survey responses are requested by 11 April 2022.
National Grid ESO completed qualification assessment for CfD Allocation Round 4 on 25 February 2022, with non-qualifying applicants having until 25 March to request review. If all applications qualify after review, sealed bid invitations will be issued by 5 April 2022. Appeals to Ofgem can be submitted 28 March to 1 April for upheld non-qualification decisions.
DESNZ published all five potential timeline scenarios for CfD Allocation Round 4 after stakeholder feedback. The qualification assessment window runs until 25 February 2022, when National Grid ESO will inform applicants whether they qualify to participate. Timeline after this point depends on whether any applications are rejected.
CfD allocation rounds will be held annually from March 2023, replacing the previous two-year cycle. The fifth allocation round will open in March 2023. The government made this decision following an internal review that concluded annual auctions accelerate deployment and increase market confidence.
DESNZ launched a consultation on technical changes to the CfD scheme for Allocation Round 5, focusing on strengthening Supply Chain Plan requirements and wider regulatory aspects. The consultation closes on 15 March 2022, with a parallel call for evidence on longer-term supply chain policy closing on 29 April 2022. This represents preparation for the next CfD round rather than immediate rule changes.
DESNZ announces a six-week consultation on technical changes to CfD scheme and Supply Chain Plan process for Allocation Round 5, launching in the next few weeks. A parallel 12-week call for evidence on longer-term Supply Chain Plan reforms will run alongside. Live Q&A session scheduled for 9 February 2022.
CfD Allocation Round 4 application window closed on 14 January 2022 with National Grid ESO now conducting qualification assessments until 25 February 2022. Non-qualifying applicants can request reviews from 28 February for five working days. This is a routine procedural update on an existing allocation round.
DESNZ opened CfD Allocation Round 4 to applications on 13 December 2021. The department clarified that flexible bids in AR4 may have different capacities and target dates from the original application, subject to existing regulations and allocation framework rules. The FAQ section was updated to remove ambiguity.
LCCC published guidance explaining how BSUoS charge removal would affect CfD Allocation Round 4 strike prices. If Ofgem implements CMP308 to remove BSUoS charges from generation, CfD strike prices would be adjusted downward to maintain generator revenues. The guidance provides worked examples for developers ahead of Ofgem's consultation closing 19 January 2022.
DESNZ published guidance for Allocation Round 4 of the Contracts for Difference scheme, with applications opening 13 December 2021 and closing 14 January 2022. The guidance consolidates final statutory notices including budget confirmation, allocation framework rules, and National Grid ESO technical requirements through a dedicated microsite. This is implementation detail for an already-decided auction round rather than new policy.
Grid Code modification GC0155 proposes to clarify fault ride through technical requirements for generators connecting to the transmission system. The modification has been in workgroup since February 2022 with multiple timeline extensions, now scheduled for early 2026. A cost-benefit analysis is required and the modification will be split into two parts, with a new modification on temporary over voltage expected in March 2025.
DESNZ confirms £285 million budget for CfD Allocation Round 4, launching 13 December 2021. The department published final statutory notices, allocation framework, contract documents and consultation responses. The round allocates long-term revenue support contracts for renewable generation projects.
DESNZ issued a routine administrative bulletin for CfD Allocation Round 4 stakeholders on 16 November 2021. The bulletin promoted launch event materials and reminded recipients about a National Grid ESO webinar on the AR4 application process scheduled for 17 November 2021.
National Grid ESO scheduled webinars for CfD Allocation Round 4 applicants and published draft guidance documents for comment by 15 November 2021. Government opened consultation on LCCC and ESC operational cost budgets for 2022/23 to 2024/25, with levies recovered through electricity supplier charges.
National Grid ESO opened registration for CfD Allocation Round 4, with applications scheduled to open on 13 December 2021. This is a routine administrative bulletin announcing the registration window for renewable developers.
DESNZ opened a consultation on further contract changes to CfD Standard Terms and Conditions for AR4, which opens 13 December 2021. The department also published the AR4 Exemptions Request Notice on 1 October, setting procedures for generators seeking exemption from temporary site exclusions.
DESNZ published a routine stakeholder bulletin for CfD Allocation Round 4, announcing an online launch event on 23 September 2021 and opening the Supply Chain Plan application window from 27 September to 3 October. Projects 300MW or over must submit a Supply Chain Plan to participate in AR4.
DESNZ sets a £265 million draft budget for CfD Allocation Round 4, the largest round to date targeting double the renewable capacity of Round 3. Applications open 13 December 2021, with offshore wind, onshore wind, solar, tidal, and floating offshore wind eligible to compete for 15-year price support contracts.
DESNZ published the timeline for CfD Allocation Round 4, with applications opening 13 December 2021 and closing 14 January 2022. The department provided both shortest and longest possible timescales for the round on a dedicated microsite.
DESNZ published its response to the eight-week Call for Evidence on renewable energy policy design that closed 8 March 2021. The response acknowledges that the CfD scheme faces procurement challenges requiring both short-term incremental improvements and longer-term structural changes. These longer-term changes will be considered as part of wider electricity market reform led by BEIS.
The government finalised the Supply Chain Plan questionnaire for CfD Allocation Round 4, simplifying questions and improving guidance clarity. New regulations came into force adding and removing eligible technologies, strengthening supply chain requirements, and extending delivery years for successful projects. AR4 opens in December 2021, aiming to secure double the renewable electricity capacity of the previous round.
DESNZ announces seminars on 13 and 30 July 2021 to explain Supply Chain Plan requirements for CfD applicants. The seminars cover application processes, monitoring, implementation assessment, and post-build reporting with pass/fail criteria. Government response to recent consultation on Supply Chain Plan questionnaire to be published shortly.
CMP375 proposes changes to how the Expansion Constant and Expansion Factors are calculated in TNUoS charging, affecting how transmission network investment costs are recovered from users. The modification received unanimous Panel support for the Original solution and majority support for WACM2 in January 2024. Ofgem's decision date has slipped repeatedly from September 2024 to February 2025, with the current expected decision date to be confirmed.
NESO publishes constraint breakdown data showing costs and volumes of transmission system actions taken by the ESO. The dataset provides transparency on why specific system actions were taken, with tags that can be retrospectively updated. Data covers transmission network constraints only.
NESO publishes methodology for measuring carbon intensity of balancing actions, comparing emissions from Final Physical Notices versus actual dispatch through Bid Offer Acceptances. The metric tracks how system balancing operations increase or decrease carbon intensity relative to generators' submitted schedules. Data covers dispatchable Balancing Mechanism units but excludes interconnectors and small BMUs.
NESO publishes operational metered wind output data by settlement period for Scotland, England and Wales. The data differs from settlement metering used in wind forecasting metrics due to pre-reconciliation timing. This provides real-time generation visibility for system operation.
DESNZ confirms CfD Allocation Round 4 will open in December 2021. The department also published its consultation response on Supply Chain Plans and contract changes. Both documents are available on the AR4 portal.
DESNZ launched a dedicated portal for CfD Allocation Round 4, centralising guidance, FAQs, and event registration for potential applicants. The portal provides information access and hosts a CfD masterclass webinar on 20 April 2021. This is administrative infrastructure for an existing process, not a policy change.
NESO publishes 14-day ahead wind forecasts at national and Balancing Mechanism Unit level, extending beyond their day-ahead wind forecasts. The forecasts use evaluated Operational Capacity based on recent actual production levels from SCADA telemetry. The data covers all wind farms contributing to NESO's day-ahead incentive wind forecasts.
DESNZ announces a virtual stakeholder event on 26 February 2021 to discuss its Call for Evidence on enabling a high renewable, net zero electricity system. The event runs 15:00-16:00 and aims to clarify questions before the consultation closes in two weeks. Responses will inform the design and evolution of renewable support schemes, particularly the CfD scheme.
DESNZ extended the deadline for responses to its call for evidence on 'Enabling a High Renewable, Net Zero Electricity System' by two weeks to 8 March 2021, citing coronavirus pandemic challenges. The call for evidence will inform the design of the fifth CfD allocation round and longer-term government support for renewable projects.
DESNZ published a consultation on a new Supply Chain Plan questionnaire that CfD applicants must complete, closing 11 March 2021. The department extended the deadline for the related consultation on Supply Chain Plan changes from 18 January to 28 January to allow stakeholders to review both together.
NESO publishes the TEC register showing which projects hold transmission entry capacity contracts to connect to the grid. From November 2025, the register will add a 'Gate' column distinguishing between Gate 1 and Gate 2 agreements under updated CUSC provisions. The register covers existing connections and the pipeline of future projects seeking transmission access.
NESO publishes a register of embedded generation projects in Scotland that are connected or contracted to connect. The register will add a 'Gate' column from 21 November 2025 to distinguish Gate 1 and Gate 2 agreements under the Connections Reform process. Capacity data currently shows aggregated figures across stages and technologies, creating potential duplicates.
Government confirms major changes to CfD scheme for Allocation Round 4, including a third offshore wind pot, administrative strike price for floating offshore wind, and extension of negative pricing rule to stop payments when day-ahead prices go negative. Coal-to-biomass conversion projects are excluded from future rounds. Second consultation runs until 18 January 2021 on implementation details.
DESNZ allowed electricity suppliers to defer part of their CfD obligation increases from Q2 2020 to Q2 2021 due to coronavirus measures. The amendment came into force on 8 July 2020, ahead of LCCC's quarterly reconciliation. This shifts supplier payment timing but does not change the total obligation amount.
NESO publishes System Operating Plans (SOPs) — real-time operational plans produced at demand peaks and troughs that show how the system operator will balance electricity supply and demand. The SOPs reveal expected actions in the balancing mechanism, reserve requirements, interconnector flows, and transmission constraints for each cardinal point throughout the day. This data release makes operational decision-making transparent to market participants who can see NESO's anticipated balancing actions hours ahead of real time.
Government amends CfD supplier obligation regulations to protect suppliers from 80% of COVID-19-driven cost increases (up to £100m loan) and defer full cost recovery by an additional quarter to Q2 2021. Regulations laid 4 June with Parliamentary approval expected before 9 July reconciliation process.
NESO publishes real-time instruction data for non-BM ancillary services including Fast Reserve, STOR, and RDP dispatch through its ASDP system. Data is published continuously throughout the day once service providers confirm instructions. Monthly files are created only when new instructions are dispatched for these MW services.
DESNZ extends the CfD Allocation Round 4 consultation deadline by one week to 29 May 2020, citing COVID-19 disruption. The consultation covers proposals including floating offshore wind definitions, delivery year simplification, and Supply Chain Plan strengthening. AR4 remains scheduled to open in 2021 with draft parameters to be published 4-6 months beforehand.
CMP344 fixes transmission owner revenue recovery at the start of each price control period rather than allowing annual adjustments. The modification prevents mid-period revenue changes that currently create unpredictable cost shifts between network users. After multiple Ofgem send-backs since 2021, the CUSC Panel recommended implementation in June 2025, with final decision expected from Ofgem.
BEIS proposes deferring part of electricity suppliers' CfD obligations from Q2 2020 to Q1 2021 while providing a loan to LCCC to maintain generator payments during COVID-19. The consultation closes 19 May 2020 with Parliamentary approval required before 9 July for the reconciliation process. If the proposal fails, suppliers face higher lump sum payments in July's reconciliation.
NESO publishes regional carbon intensity forecasts covering 17 GB regions up to 48 hours ahead, using machine learning to predict demand, generation by fuel type, and power flows between regions. The methodology accounts for transmission losses, interconnector imports, and embedded wind/solar generation within Distribution Network Operator boundaries. Forecasts update every 30 minutes using real-time weather data from the Met Office.
BEIS provides a temporary loan to Low Carbon Contracts Company to cover CfD payments in Q2 2020 after COVID-19 reduced electricity demand and supplier levy contributions. The loan defers supplier payment obligations from Q2 2020 to Q1 2021 through regulatory changes subject to consultation. LCCC will not increase the Interim Levy Rate or Total Reserve Amount for Q2 2020 as previously warned.
DESNZ announces three online webinars for the CfD Round 4 consultation between 30 April and 6 May 2020. Sessions separate established technologies (onshore wind, solar, hydro) from less-established ones (offshore wind, remote island wind, advanced conversion). The consultation closes 22 May 2020.
DESNZ confirms the CfD AR4 consultation will close on 22 May 2020 as scheduled despite COVID-19, with AR4 planned to open in 2021. The department will replace physical stakeholder events with online webinars in late April or early May. Stakeholders can request extensions if COVID-19 prevents response.
CMP341 would create a sandbox for parties to trial innovative technologies by being derogated from specific CUSC obligations on a small-scale, time-limited basis. The proposal has been parked at low priority since 2020 and remains stalled with no active work. The CUSC Panel confirmed in February 2025 it will not prioritise this modification.
GC0140 proposes a Grid Code sandbox allowing parties to be exempted from specific Grid Code obligations for small-scale, time-limited trials of innovative technologies and services. The modification has been in a workgroup since 2020 but remains deprioritised, with meetings subject to Panel prioritisation as of February 2022. It follows standard governance procedures and has cross-code implications through CUSC modification CMP341.
NESO published historical carbon intensity data from January 2009 onwards, measuring CO2 emissions per kilowatt hour of electricity generation. The dataset uses seasonal decomposition to correct for missing or irregular data points and remains subject to ongoing data cleansing.
BEIS opened a twelve-week consultation on proposed amendments to the CfD scheme ahead of Allocation Round 4, scheduled to open in 2021. The consultation runs until 22 May 2020. AR4 will include auctions for both Pot 1 (established technologies like onshore wind and solar) and Pot 2 (emerging technologies like offshore wind and floating solar) technologies.
NESO publishes half-hourly BSUoS charges across three run types (Interim Initial, Settlement Final, Reconciliation Final) with daily updates of actual prices and volume data. A system outage paused billing from 26 April to 27 May 2024, with normal publication resuming 28 May 2024. The data provides visibility into balancing service costs allocated to suppliers and generators.
NESO publishes daily and weekly forecasts of Negative Reserve Active Power Margin (NRAPM), warning when insufficient flexibility exists to balance the system during low demand periods. The forecasts cover 2-14 days ahead daily and 2-52 weeks ahead weekly for both national and Scottish systems. NRAPM warnings indicate risk of Emergency Instructions being issued to generators.
CMP330/CMP374 proposes to allow transmission-connected parties to build their own connection assets longer than 2km, where previously only assets up to 2km could be built contestably. The modification removes the arbitrary 2km length restriction on contestable connection works, requiring only agreement between the transmission owner and connecting party. Decision expected but currently delayed pending resolution of related modifications CMP414 and CM079.
NESO publishes Balancing Services Adjustment Data (BSAD) covering balancing actions taken outside the standard balancing mechanism, updated twice daily. The dataset tracks actions that affect imbalance settlement but fall outside the Balancing Mechanism's Bid-Offer Acceptances.
NESO publishes Balancing Services Adjustment Data (BSAD) twice daily, covering balancing actions taken outside the formal balancing mechanism. This data feeds into the Balancing & Settlement Code for imbalance settlement processes. The dataset provides transparency on system operator interventions that sit outside standard market mechanisms.
NESO publishes real-time data on upcoming electricity trades used for system balancing, refreshed every ten minutes. The dataset shows trades scheduled for delivery to meet forecast balancing requirements at minimum cost. Trade details are provisional and subject to confirmation with counterparties.
NESO publishes half-hourly forecasts for embedded wind and solar generation from same-day to 14 days ahead, updated hourly. The dataset covers distributed renewables connected to distribution networks rather than transmission-connected generation. NESO acknowledges missing archived records and is working to restore them.
NESO publishes day-ahead wind forecasts at national and BMU level, plus the historic archive of prior forecasts. The dataset is intended to help market participants balance supply and demand positions.
NESO publishes historic GB system frequency at 1-second resolution, with the statutory obligation to hold frequency at 50 Hz within a 0.5 Hz limit either side. The dataset records actual frequency deviations rather than changing any rule or charge. Files are large enough that NESO advises downloading the CSV and opening it in Notepad++.
NESO's monthly BSUoS forecast publishes a 24-month-ahead projection of balancing services costs, the charge that recovers the cost of operating the system second-by-second (constraint payments, reserve, frequency response, black start). This is a routine recurring data release giving the next month's forecast plus a rolling two-year horizon, explicitly disclaimed as not binding on indicative or actual tariffs. It tells users what NESO expects to charge, not what changes.
BEIS corrected minor calculation errors in CfD Allocation Round 3 budget impact tables, underestimating negative impacts for 2025/26 and 2026/27. The department also corrected price base years from 2011/12 to 2012 in tables B, C, and D. These revisions do not affect any other published results from the allocation round.
Allocation Round 3 awarded CfDs to 12 renewable projects totalling 5.8GW capacity, 2.4GW more than Round 2 in 2017. Projects include offshore wind, advanced conversion technologies, and remote island wind, delivering by 2025. This represents a substantial expansion of subsidised renewable capacity under long-term price guarantees.
DESNZ announces CfD Allocation Round 3 results will be published on 20 September 2019. National Grid ESO will notify all applicants before 8am, with DESNZ publishing successful applications on GOV.UK. Successful applicants receive notification letters with final strike prices, target commissioning dates, and allocated capacity.
DESNZ extended the sealed bid window for CfD Allocation Round 3 and updated the timeline on the allocation portal. The bulletin provides administrative updates to the CfD AR3 process without changing substantive auction parameters.
DESNZ updated the timeline for Allocation Round 3, with five possible schedules published on 5 July 2019 superseding previous dates from 1 May 2019. The bulletin also contains standard GDPR compliance information for the CfD stakeholder mailing list.
Government launched CfD Allocation Round 3 with £65 million budget for delivery years 2023/2024 and 2024/2025, 6GW capacity cap, and application window from 29 May to 18 June 2019. The round uses unchanged allocation framework rules from the January 2019 draft with minor additions for sealed bids and phased offshore wind. Remote Island Wind projects require new schematic diagrams demonstrating eligibility under Regulation 27A.
CMP315 proposes to review how the transmission network expansion constant is determined, which directly affects locational TNUoS charges paid by generators and large users. The modification has been in development since 2019, with the final decision now expected by February 2025. The Panel recommended the original solution by majority vote in January 2024.
CMP316 establishes charging methodology for co-located generation sites combining multiple technologies at one power station. The modification has been through extensive industry review since 2019, with Panel unanimously recommending WACM1 for implementation in August 2025. The Second Final Modification Report was submitted to Ofgem on 8 August 2025.
The government published final draft CfD contracts for Allocation Round 3, including Brexit-related amendments to remove EU law references and standardised Direct Agreement terms for lender protection. LCCC published Minor and Necessary modification guidance, and National Grid opened AR3 registration. These documents give potential applicants visibility of contract terms before the allocation round commences.
BEIS published exemption procedures for generators at sites excluded from CfD Allocation Round 3 under Non-Delivery Disincentive rules. Excluded sites must apply for exemption certificates by 15 March 2019 to participate in AR3, which will commence by 29 May 2019. Sites that failed to meet Milestone Delivery Dates from previous CfD awards face temporary exclusion unless exempted.
Government published draft Allocation Framework for CfD Allocation Round 3 (AR3), introducing an overall capacity cap applicable to all technologies for the first time. The framework adds Remote Island Wind to Pot 2 (less established technologies) and updates eligibility requirements for fuelled technologies. The round is planned to open by May 2019, with the final framework published no later than 10 working days before.
DESNZ published updated CfD contract terms following August 2018 consultation, implementing changes to advanced conversion technologies definition, lower greenhouse gas thresholds, and new Remote Island Wind category. Supply Chain Plan applications for projects over 300MW open 4-10 February 2019 with decisions by 22 March. Administrative strike price methodology for third allocation round (Pot 2 technologies) also published.
DESNZ published Supply Chain Plan Guidance for CfD Allocation Round 3, requiring projects of 300MW or more to obtain supply chain certificates before bidding. The guidance includes minor changes requiring developers to submit post-build reports and providing more detail on monitoring processes. A new resource portal consolidates information from all CfD delivery partners with query management services.
AR3 will offer £60m for 'less established' renewables (pot 2) delivering in 2023/24 and 2024/25, with auction opening by May 2019. The budget targets around 4GW of capacity, capped at 6GW maximum to increase competitive tension. Administrative Strike Prices for both delivery years have been published in draft.
LCCC announces a training course on CfD processes for potential applicants, lenders, and advisors on 27 November 2018. The course covers bidding strategies and end-to-end CfD procedures. Priority places are free and allocated first-come, first-served.
CMP304 seeks to reform the Enhanced Reactive Power Service but has been repeatedly paused since 2018. The modification was de-prioritised while NESO conducted reactive power market feasibility studies, then moved from low to medium priority in February 2026 following completion of those studies and the raising of related modification CMP457.
NESO proposes removing the Enhanced Reactive Power Service (ERPS) from the CUSC, a tendered commercial service that has attracted no bids in 7.5 years and no contracts in 9 years. Ofgem has delayed decision pending alignment with related proposal CMP304. The removal affects balancing service providers but has low industry impact.
Government announced third CfD auction will open by May 2019, with subsequent auctions every two years using £557 million budget. Published Part B consultation response covering advanced conversion technologies, load factor assumptions, and contract terms. Launched six-week follow-up consultation on implementation details, closing 10 October 2018.
DESNZ published Part A of its response to the December 2017 CfD consultation, implementing three minor changes: defining remote island wind as eligible for Pot 2, updating combined heat and power requirements, and revising the waste fuel definition. A draft Statutory Instrument was laid before Parliament to implement these changes.
GC0117 seeks to harmonise GB power station connection requirements by implementing EU Connection Code obligations within the Grid Code. The modification has been under development since 2018, was sent back by Ofgem in July 2025, and workgroups are now reconsidering DNO feedback on the cost-benefit analysis. The next workgroup meeting is scheduled for March 19, 2026.
BEIS introduces Post Build Reports (PBR) and interim Post Build Reports (iPBR) to monitor whether CfD projects above 300MW deliver on Supply Chain Plan commitments. Projects must submit PBRs within three months of commissioning, with iPBRs required for new applications if previous projects haven't yet submitted final reports. Reports are limited to 10 pages covering competition, innovation, and skills delivery against original commitments.
CMP288 proposes explicit charging arrangements to recover additional transmission costs when users delay grid connection works or require backfeed arrangements. The modification has been low priority since October 2024, with Panel confirming this status in February 2025. The proposal targets cost recovery from developers who cause transmission owners to undertake works early due to user-initiated delays.
National Grid confirmed to BEIS that qualifying CfD applications exceed the available budget, triggering an auction process. Sealed bids will be requested between 14-18 August 2017 following completion of the qualification appeals process on 2 August. An independently audited auction will determine which projects receive contracts at what strike prices.
GC0103 proposes harmonising UK electrical standards with EU Connection Codes within the Grid Code, affecting compliance obligations for generators and network operators. The modification has been in development since 2017 but repeatedly stalled due to low prioritisation, with the Panel requiring further work on Applicable Electrical Standards as of February 2026. It impacts transmission owners, generators, and network operators across medium-scale operations.
The qualification appeal window for CfD Allocation Round 2 closed, with appeals now submitted to Ofgem from currently non-qualifying applicants. Ofgem will assess these appeals and announce decisions on 2 August 2017.
National Grid has concluded the non-qualification review for CfD applicants, with Ofgem opening a qualification appeal window from 7-13 June 2017. Non-qualifying applicants have seven days to appeal their rejection. This is routine procedural administration for the CfD allocation process.
National Grid closed the non-qualification review window for CfD applications and received review requests from applicants. The delivery body will assess these reviews and notify outcomes by 6 June 2017.
DESNZ clarifies that CfD applicants using Advanced Conversion Technologies can choose whether to declare CHP status at application, as they are not required to utilise heat output. Projects converting to CHP mid-contract will not automatically face CHP Quality Mark requirements or other CHP-specific terms for this allocation round.
The second CfD allocation round opens with a £290m budget for delivery years 2021/22 and 2022/23, with applications closing 21 April 2017. This provides 18 days for eligible renewable projects to submit competitive bids through National Grid's allocation process.
DESNZ launches the second CfD allocation round with applications opening 3 April 2017 and closing 21 April 2017. The round sets geothermal's administrative strike price at £140/MWh and introduces new auction rules for interleaving bids to encourage developers to submit larger capacity bids at lower prices. Fuelled technologies face a cumulative 150MW capacity limit.
BEIS published draft CfD contract changes for the second allocation round, preventing payments for projects hampered by foreseeable events and for stored imported electricity. The changes include revised definitions of foreseeable change in law and clarified treatment of storage on CfD sites. The second allocation round opens 3 April 2017 with new auction rules allowing interleaving bids to encourage larger, cheaper capacity submissions.