Consultation on the onshore electricity transmission Early Competition commercial framework
Summary
Ofgem consultation on the onshore electricity transmission Early Competition commercial framework. Sets out the commercial terms under which CATOs will design, finance, build and operate transmission assets.
Why it matters
Commercial-framework consultation in the CATO regime sequence. Companion to the September 2024 draft Regulations and December 2024 first project consultation. Determines what CATOs are paid for, what risks they bear, and how performance is measured.
Areas affected
Related programmes
Memo
What this is about
Ofgem is consulting on the commercial framework for the Early Competition regime, the third strand of the onshore competitive transmission package that runs alongside the September 2024 draft Regulations and the December 2024 first-project consultation. The framework determines what a Competitively Appointed Transmission Owner (CATO) is paid for, what risks it carries, and how its performance is measured across the preliminary works, construction and operational stages of a project.
The trigger is NESO's Early Competition Implementation Update (ECI-Update), which set out a set of design choices that need regulatory endorsement before tenders can be run. The CATO route is meant to introduce competitive pressure into transmission delivery, which has historically been built by incumbent TOs under the RIIO price control. The commercial terms in this consultation are the substance of that reform: a strong post-award security obligation, narrow cost pass-through and clear performance incentives produce something close to a fixed-price tender; weak versions of these produce something closer to incumbent RIIO economics with a different counterparty. The decision shapes whether Early Competition actually lowers consumer cost or simply rebadges the existing model.
Options on the table
The consultation is structured as a set of design choices rather than discrete A-or-B options. The substantive choices are:
Post-award security obligation
NESO proposes that the CATO post security after award to cover preliminary works and construction. The size of the bond, the triggers for drawdown and the duration are the live questions. A larger bond filters out bidders who cannot stand behind their tender price, which raises bid quality and reduces the option-value problem that has bedevilled the connections queue. A smaller bond widens the bidder pool but transfers more delivery risk to consumers, because a CATO that walks away with limited consequences leaves the project to be re-tendered or absorbed back into the incumbent TO at consumer cost. The trade-off is bidder pool size against credibility of the tender price.
Payments during the preliminary works stage
The CATO incurs design, consenting and pre-construction costs before any asset earns revenue. The framework has to decide whether these costs are paid as they are incurred, paid on milestone completion, or rolled into the operational revenue stream. Pay-as-you-go reduces CATO financing costs and therefore bid prices, but transfers timing risk to consumers and weakens the discipline on the CATO to manage the preliminary works efficiently. Milestone payments preserve some discipline but require the milestones to be specified tightly enough that they cannot be gamed. Rolling preliminary works costs into the operational tariff puts the full financing burden on the CATO and produces the strongest cost discipline, at the price of a higher headline bid.
Post preliminary works cost assessment
After preliminary works, Ofgem proposes to assess the costs incurred and confirm the construction cost allowance. The question is how prescriptive this assessment should be. A light-touch assessment that largely accepts the tendered figure preserves the competitive tension created at bid stage. A detailed RIIO-style cost assessment effectively re-opens the bid and converts a competitive tender into a regulated price review, which is what Early Competition is meant to displace. Where the line is drawn here is the difference between a real competition and a procurement exercise that becomes a price control by another route.
Operational stage payment and performance incentives
The CATO earns revenue across the operational period. The framework needs to specify the fixed component (availability-based), the variable component (output-linked) and the incentive properties (rewards and penalties for performance against defined metrics). The harder a CATO is held to delivered availability, the more its incentives align with system value rather than capital deployment. The Averch-Johnson critique of rate-of-return regulation applies directly: a CATO paid on capital deployed will deploy capital; a CATO paid on delivered availability and throughput will optimise for delivery. The incentive design here matters more than the headline strike.
Additional works obligation
A live tension in any competitive transmission regime: what happens when the network need changes after award, or the CATO's asset needs to be extended or modified for a reason that was not foreseen at tender. NESO proposes that the CATO carry an obligation to deliver additional works on defined terms. The design choice is between a broad obligation (which preserves system flexibility but exposes the CATO to scope creep and therefore raises bid prices) and a narrow obligation (which keeps bids low but creates a future renegotiation problem every time the system evolves). This is the classic Williamson holdup problem, and the contractual answer matters because the alternative is a re-tender every time scope shifts.
Revenue period and end-of-period treatment
The consultation covers how long the CATO earns revenue and what happens at the end. Options range from a defined revenue period followed by hand-back to a system operator or incumbent TO, through extension on regulated terms, to re-competition for the asset's residual life. A defined period with clear hand-back terms keeps the original competition meaningful; open-ended extension converts the CATO into a perpetual incumbent and erodes the case for competition in the first place.
Questions being asked
Ofgem has not published a numbered question list in the publicly visible consultation summary; the substantive questions sit in the main consultation PDF. The themes the consultation invites responses on, as set out on the landing page, are:
Security and risk allocation
Views on the appropriate scale, triggers and duration of the post-award security obligation on the CATO during preliminary works and construction. [In effect: how much skin in the game does the CATO need to make the tender price credible.]
Preliminary works payments
Views on the structure and timing of payments to the CATO during the preliminary works stage. [In effect: who finances the pre-construction period and on what terms.]
Cost assessment
Views on the post preliminary works cost assessment process. [In effect: how prescriptive should Ofgem be in re-checking the tendered cost after the design has matured, and what is the test for accepting or challenging the figure.]
Operational payment and incentives
Views on the structure of payment to the CATO during the operational stage and the design of performance incentives. [In effect: what proportion of revenue is availability-based, what proportion is performance-linked, and how strong are the penalties for under-delivery.]
Additional works
Views on the additional works obligation on CATOs beyond the scope of work originally tendered. [In effect: what is the contractual answer to the holdup problem when system needs evolve mid-project.]
Revenue period and end-of-period
Views on the length of the revenue period and the arrangements that apply when it ends. [In effect: does the asset return to competitive tender, revert to the incumbent TO, or stay with the CATO on regulated terms.]
Respondents are asked to address NESO's proposals as set out in the ECI-Update and Ofgem's own views as expressed in the consultation document.
How to respond
The consultation was published on 21 October 2024 and closed on 3 December 2024. It is now closed, and Ofgem has published a decision and updated policy position alongside the original document; responses received are available in the subsidiary EC Commercial Framework consultation responses bundle.
Contact for queries on the framework:
- Jon Sharvill - Telephone: 020 3263 9623 - Email: OnshoreCompetitionsPolicy@ofgem.gov.uk
Documents:
- Main consultation: Consultation on the onshore electricity transmission Early Competition commercial framework (PDF, 970 KB) - Subsidiary: EC Commercial Framework consultation responses (ZIP, 2.03 MB) - Decision: Decision and updated policy position on the onshore electricity transmission Early Competition commercial framework, published alongside the closed consultation
For follow-up policy work on Early Competition, the relevant companion documents are the September 2024 draft Regulations and the December 2024 first-project consultation, which together with this commercial framework determine the operating economics of the CATO regime.
Source text
Consultation on the onshore electricity transmission Early Competition commercial framework | Ofgem Please enable JavaScript in your web browser to get the best experience. BETA This site is currently in BETA. Help us improve by giving us your feedback . Close alert: Consultation on the onshore electricity transmission Early Competition commercial framework Publication type: Consultation Publication date: 21 October 2024 Closed date: 3 December 2024 Status: Closed (with decision) Topic: Electricity transmission Decision: Decision and updated policy position on the onshore electricity transmission Early Competition commercial framework Print this page Share the page Share on Facebook Share on Twitter Share on LinkedIn This consultation summarises our latest thinking on the National Energy System Operator’s (NESO) proposals on various important elements of the commercial framework for the Early Competition regime, as published in its Early Competition Implementation Update ( ECI-Update ). We want to get feedback on NESO’s proposals and our views on: Post-award security obligation on the Competitively Appointed Transmission Owner (CATO) during the preliminary works and construction stages payments to a CATO during the preliminary works stage post preliminary works cost assessment payment to the CATO and performance incentives during the operational stage additional works obligation on CATOs beyond the scope of work originally tendered revenue period and the next steps following the end of the revenue period Who should respond We want to hear views and feedback from the public and stakeholders with an interest in this consultation, specifically from: potential bidders in Early Competition processes and network companies people with an interest in the development of electricity network solutions, technical and commercial innovation people competing for the design, construction and operation of solutions to solve network problem Respond name Jon Sharvill Respond telephone 020 3263 9623 Respond email OnshoreCompetitionsPolicy@ofgem.gov.uk Main document Consultation on the onshore electricity transmission Early Competition commercial framework [PDF, 970.11KB] Subsidiary documents EC Commercial Framework consultation responses [ZIP, 2.03MB] Print this page Share the page Share on Facebook Share on Twitter Share on LinkedIn Close