Grid Code

All modifications to the Grid Code, tracked through their lifecycle. Administered by NESO.

How Grid Code modifications work

The Grid Code sets the technical rules for connecting to and using the GB transmission system. It covers voltage, frequency response, fault ride-through, protection, metering, and data submission. Every generator, interconnector, and demand user connected to the transmission network must comply. NESO administers the code.

The modification process

Anyone can propose a Grid Code modification. Once raised, it goes to the Grid Code Review Panel (GCRP), which assigns it to a Workgroup of technical experts. The Workgroup develops the solution and produces a report. NESO then runs a Code Administrator Consultation (CAC) so all affected parties can respond. After consultation, a Final Modification Report goes to the Panel, which votes and recommends to Ofgem. Ofgem makes the final decision unless the modification qualifies as Self-Governance, in which case the Panel decides.

Key concepts

  • Self-Governance applies when a modification will not materially affect consumers, competition, or system security. The Panel decides; parties can appeal within 15 working days.
  • Urgent modifications can skip normal timelines if Ofgem agrees the issue is time-critical. Ofgem determines urgency and sets the timetable.
  • Cross-code impact means the modification affects other industry codes (CUSC, BSC, STC). When this happens, the codes must be changed in coordination.
89 shown
GovernanceStageRaised
StandardRaised10 Feb 2026
GC0186Proposed Grid Code Changes - Post Electricity System Restoration Standard (ESRS)
Open pagealso affects STC and DCODE
StandardRaised12 Nov 2025
GC0184Increasing Reactive Power Requirements for PPMs when Operating below Maximum Active Power
Open pagealso affects N/A
UrgentImplementation9 Jul 2025
GC0183Generator and Interconnector Availability During a Severe Space Weather Event
Open pagealso affects Other
StandardWorkgroup7 Jul 2025
GC0182Standardisation of Power Flow Metering Polarity
Open pagealso affects STC
StandardWorkgroup26 Jun 2025
GC0181Enhance the Effectiveness of System Incidents Reporting
Open pagealso affects N/A
Fast TrackImplemented3 Apr 2025
GC0180Corrections to the Grid Code following implementation of GC0175
also affects N/A
StandardWorkgroup12 Mar 2025
GC0178Temporary Overvoltage - Specification of Limits and Clarification of Obligations
Open pagealso affects STC
StandardReport12 Mar 2025
GC0179Removal of Balancing Code No.4 and Balancing Code No.5 from the Grid Code
Open pagealso affects BSC
Self-Governance (direct)Implemented13 Jan 2025
GC0177Planning and Operational Compliance Contacts
also affects N/A
StandardRaised7 Jan 2025
GC0185Grid Code Changes for Mandatory Frequency Response (MFR) replacement
Open pagealso affects CUSC
StandardWorkgroup11 Nov 2024
GC0176Introduction of Demand Control Rotation Protocol within Operating Code 6 of the Grid Code
Open pagealso affects DCode
Standard (direct)Implemented8 Oct 2024
GC0175Removing references to “Fax” or “Facsimile” within the Grid Code
also affects CUSC and STC
Self-GovernanceImplemented11 Jun 2024
GC0174Review of obligation to provide EU Transparency Availability Data as specified in OC2.4.7
also affects BSC
StandardDecision22 May 2024
GC0173Consistency of Technical and Compliance Requirements between GB and European Users
Open pagealso affects DCode
Standard (direct)Implemented3 May 2024
GC0172Replacing References to Electricity Supply Industry Arbitration Association
also affects CUSC, STC & BSC
Self-Governance (direct)Implemented28 Mar 2024
GC0171Improving the clarity and transparency of the Compliance Process for Small Generators with a Bilateral Embedded Generator Agreement (BEGA)
also affects NA
StandardDecision6 Mar 2024
GC0169Material changes arising from Grid Code Modification GC0136
Open pagealso affects DCode
Fast TrackImplemented6 Mar 2024
GC0170Typographical and formatting updates following the implementation of GC0156: Facilitating the Implementation of the Electricity System Restoration Standard
also affects N/A
StandardWorkgroup5 Mar 2024
GC0168Submission of Electro Magnetic Transient (EMT) Models
Open pagealso affects CUSC
TBCWithdrawn10 Jan 2024
GC0167Material and Non Material Grid Code Changes
also affects N/A
StandardImplemented29 Nov 2023
GC0166Introducing new Balancing Mechanism Parameters for Limited Duration Assets
also affects BSC
Fast TrackImplemented6 Oct 2023
GC0165Typographical and formatting changes to the Grid Code
also affects N/A
StandardConsultation4 Oct 2023
GC0164Simplification of Operating Code No.2
Open pagealso affects N/A
Self-GovernanceImplemented2 Oct 2023
GC0163GB Grid Forming (GBGF) - Removal of Virtual Impedance restriction
also affects N/A
UrgentImplemented20 Jul 2023
GC0162Changes to OC6 to amend the operational timings for the delivery of the additional demand reduction above 20%, with a focus between 20% and 40%
also affects Distribution Code
UrgentImplemented17 May 2023
GC0161Changes to OC6 to allow for site protection
also affects Distribution Code
UrgentImplemented28 Sept 2022
GC0160Grid Code Changes for BSC Mod P448: "Protecting Generators subject to Firm Load Shedding during a Gas Supply Emergency from excessive Imbalance Charges"
also affects BSC (P448)
StandardImplemented13 Sept 2022
GC0159Introducing Competitively Appointed Transmission Owners
also affects CUSC (CMP403 and CMP404), STC (CM086 and CM087), SQSS (GSR031)
Self-Governance (direct)Implemented10 Aug 2022
GC0158Reversing unimplemented aspects of GC0068
also affects BSC
Self-Governance (direct)Implemented13 Jun 2022
GC0157Grid Code Housekeeping Modification
StandardImplemented8 Feb 2022
GC0156Facilitating the Implementation of the Electricity System Restoration Standard
also affects Grid Code (GC0148), CUSC (CMP398 and CMP412), SQSS (GSR032), STC (CM089 and STCP PM0128), BSC (P451) and Distribution Code/G99 and European Network Codes
StandardWorkgroup1 Dec 2021
GC0155Clarification of the Fault Ride Through Technical Requirements
Open page
StandardImplemented24 Nov 2021
GC0154Incorporation of interconnector ramping requirements into the Grid Code as per SOGLA119
also affects European Network Codes (SOGL)
StandardImplemented14 Jul 2020
GC0148Implementation of EU Emergency and Restoration Code Phase II
also affects Distribution Code, STC, European Network Codes
StandardWorkgroup11 Mar 2020
GC0140Grid Code Sandbox: enabling derogation from certain obligations to support small-scale trials of innovative propositions
Open pagealso affects CUSC (CMP341)
StandardImplemented11 Mar 2020
GC0141User Compliance Processes and Modelling following 9th August Power Disruption
also affects STC
StandardWorkgroup10 Feb 2020
GC0139Enhanced Planning Data Exchange to Facilitate Whole System Planning
Open pagealso affects STC (STCP19-5)
StandardImplemented10 Feb 2020
GC0138Compliance process technical improvements (EU and GB User)
StandardWorkgroup1 Jun 2018
GC0117Improving transparency and consistency of access arrangements across GB by the creation of a pan-GB commonality of Power Station requirements
Open pagealso affects CUSC, STC & BSC
StandardReport1 Jul 2017
GC0103The introduction of harmonised Applicable Electrical Standards in GB to ensure compliance with the EU Connection Codes
Open pagealso affects STC
Implemented
GC0097Grid Code Processes Supporting TERRE
Implemented
GC0100EU Connection Codes GB Implementation – Mod 1 PLS ALSO REFER 101 &102
Implemented
GC0101EU Connection Codes GB Implementation – Mod 2 PLS ALSO REFER 100 &102
Implemented
GC102EU Connection Codes GB Implementation – Mod 3 PLS ALSO REFER TO 100 &101
Implemented
GC0110LFSM-O compliance requirements for Type B PGMs
Implemented
GC0104EU Connection Codes GB Implementation – Demand Connection Code
Implemented
GC0098Using GB Grid Code data to construct the EU Common Grid Model in accordance with Regulation (EU) 2015/1222 (CACM) and Regulation (EU) 2016/1719 (FCA)
Implemented
GC0099Establishing a common approach to interconnector scheduling consistent with the single intraday market coupling processes set out within Regulation (EU) 2015/1222 (CACM).
Implemented
GC0108EU Code: Emergency & Restoration: Black start testing requirement
Implemented
GC0106Data exchange requirements in accordance with Regulation (EU) 2017/1485 (SOGL)
Implemented
GC0115Legal Separation housekeeping: NGET to The Company
Implemented
GC0116Correction to the compliance dates included in modifications GC0100-102 for the Requirements for Generators (RfG) and HVDC European Network Codes
Implemented
GC0112National Grid Legal Separation Grid Code changes to incorporate NGESO
Implemented
GC0120National Grid legal separation changes to clarify Grid Code responsibilities and consequential changes
Implemented
GC0122Amending references to NGET and the Company within the Grid Code following previous modifications
Implemented
GC0114System Operation Guideline: Prequalification Processes
Implemented
GC0118Modification to the Grid Code to accommodate the recent Distribution Code modification to Engineering Recommendation P28 –Voltage fluctuations and the connection of disturbing equipment to transmission systems and distribution networks in the UK
Implemented
GC0111Fast Fault Current Injection specification text
Implemented
GC0124Critical Friend review period for submission of new modifications
Implemented
GC0123Clarifying references to NGET and Relevant Transmission Licensees
Implemented
GC0125EU Code Emergency & Restoration: Black Start testing requirements for Interconnectors
Implemented
GC0127EU Code Emergency & Restoration: Requirements resulting from System Defence Plan
Implemented
GC0128EU Code Emergency & Restoration: Requirements resulting from System Restoration Plan
Implemented
GC0135Removal of Redundant Provisions
Implemented
GC0143Last resort disconnection of Embedded Generation
Rejected
GC0107 GC0113The open, transparent, non discriminatory and timely publication of the generic and/ or PGM specific values required to be specified by the relevant TSO(s) and / or relevant system operator et al., in accordance with the RfG.
Implemented
GC0096Energy Storage
Implemented
GC0105System Incidents Reporting
Implemented
GC0129Updating references to Engineering Recommendation G5
Implemented
GC0132Updating the Grid Code governance process to ensure we capture EBGL change process for Article 18 T and Cs
Implemented
GC0131Quick Win’ Improvements to Grid Code Open Governance Arrangements
Implemented
GC0142Adding Non-Standard Voltages to the Grid Code
Withdrawn
GC0121Grid Code changes in the event the UK leaves the EU without an agreement
Withdrawn
GC0145Updating the Grid Code to include the Manually Activated Reserve Initiative (MARI)
Implemented
GC0136Non-material changes to the Grid Code following implementation of the EU Connection Codes.
Implemented
GC0130OC2 Change for simplifying ‘output useable’ data submission and utilising REMIT data
Implemented
GC0147Last resort disconnection of Embedded Generation – enduring solution
Implemented
GC0144Alignment of Market Suspension Rights to the EU Emergency and Restoration Code Article 35.1(b)
Implemented
GC0149Grid Code changes to reflect the terms of the UK’s departure from the EU
Implemented
GC0109Publication of the various GB electricity Warnings or Notices or Alerts or Declarations or Instructions or Directions etc., issued by or to the Network Operator(s).
Implemented
GC0134Removing the telephony requirements for small, distributed and aggregated market participants who are active in the Balancing Mechanism
Implemented
GC0150Housekeeping change post- GC0147 implementation
Implemented
GC0151Grid Code Compliance with Fault Ride Through Requirements
Implemented
GC0152Updating the Grid Code governance process to ensure we capture network code on electricity emergency and restoration (NCER) change process for Article 4 Terms and Conditions (T&Cs)
Implemented
GC0137Minimum Specification Required for Provision of Virtual Synchronous Machine (VSM) Capability
Rejected
GC0133Timely informing of the GB NETS System State condition
Implemented
GC0153Making the Grid Code Gender Neutral
Implemented
GC0146Solutions for frequency control of Power Park Modules
Implemented
GC0126Implementing Profiled Stable Import and Export Limits, and reversing unimplemented aspects of GC0068