Ofgem consults on National Gas Transmission's re-opener application to modify outputs, delivery dates, and allowances for the Peterborough compressor emissions programme under RIIO-GT2 Special Condition 3.11. Consultation closes 5 May 2026.
Why it matters
Gas transmission price control re-opener affecting the cost of compressor emissions compliance. Re-openers adjust the regulatory settlement mid-period, changing what consumers pay for gas transmission infrastructure.
Key facts
- •NGT re-opener application June 2025
- •Modifies Special Condition 3.11
- •Consultation closes 5 May 2026
Timeline
Areas affected
Related programmes
Memo
What this is about
National Gas Transmission (NGT) applied in June 2025 to reopen the Peterborough compressor emissions programme under RIIO-GT2 Special Condition 3.11. This is the mechanism that allows a network company to come back to Ofgem mid-price control and ask for changes to what it has to deliver, when it has to deliver it, and how much it gets paid. NGT wants to modify the outputs, delivery dates, and allowances originally set for compressor emissions compliance work at the Peterborough site.
Ofgem is now consulting on its assessment of NGT's application and its minded-to position. The context is gas transmission compressor stations that need upgrading or replacing to meet emissions standards — the same programme that produced the King's Lynn and Peterborough Huntingdon decisions previously. These are large, long-lived assets on the national transmission system. The costs flow through to gas consumers via transmission charges. The consultation closes 5 May 2026.
Re-openers exist because price controls are set years in advance and some costs are genuinely uncertain at the time. Compressor replacement programmes are a reasonable candidate: environmental compliance deadlines shift, engineering scope changes, and cost estimates evolve as detailed design progresses. The question for respondents is whether the revised scope, timeline, and allowances that NGT is requesting — and that Ofgem is minded to accept — represent efficient costs that consumers should bear.
How to respond
Deadline: 5 May 2026
Method: Email submission to Graham.Craig@ofgem.gov.uk
Who should respond: Network companies, gas shippers, consumer groups, environmental groups, and the public.
The full consultation document is available as a PDF (493 KB) on the Ofgem consultation page. Ofgem states that responses received will be considered before the final decision is issued.
Source text
Peterborough Compressor Emissions: re-opener application | Ofgem Please enable JavaScript in your web browser to get the best experience. BETA This site is currently in BETA. Help us improve by giving us your feedback . Close alert: Peterborough Compressor Emissions: re-opener application Publication type: Consultation Publication date: 7 April 2026 Closing date: 05 May 2026 Status: Open Topic: Gas shipping Get emails about this page Print this page Related links Decision - King's Lynn Compressor Emissions and Peterborough Huntingdon Compressor Emissions, Final Preferred Options Share the page Share on Facebook Share on Twitter Share on LinkedIn Consultation description In June 2025, National Gas Transmission submitted an application for a direction to modify the outputs, delivery dates, and allowances set out in Appendix 2 of Special Condition 3.11, Compressor Emissions Re-opener and Price Control Deliverable. This consultation sets out our assessment of the evidence presented in the application and the various factors we have considered in reaching our minded-to position. Who should respond We are seeking views on our minded-to decision and several specific questions from: network companies gas shippers consumer groups environmental groups the public The responses we receive will be considered before our final decision is issued. How to respond Submit your response by 5 May 2026 by emailing Graham.Craig@ofgem.gov.uk . Consultation documents Peterborough Compressor Emissions: re-opener application [PDF, 492.90KB] Get emails about this page Print this page Related links Decision - King's Lynn Compressor Emissions and Peterborough Huntingdon Compressor Emissions, Final Preferred Options Share the page Share on Facebook Share on Twitter Share on LinkedIn Close Notify me Would you like to be kept up to date with Peterborough Compressor Emissions: re-opener application ? subscribe to notifications: Email Submit Close