Connections Reform design documents and methodologies | National Energy System Operator

NESO·guidance·medium·19 Mar 2026·source document

Summary

NESO published updated Connections Reform methodologies in March 2026, extending the Evidence Submission Window closure beyond July 29, 2025 due to portal issues and query response delays. The methodologies cover the Gate 2 Two-way Queue (G2TWQ) process, including network design criteria, project designation rules, and gate progression requirements.

Why it matters

This extension acknowledges implementation problems with NESO's digital infrastructure, creating uncertainty for projects already preparing Gate 2 submissions. The reform fundamentally shifts from first-come-first-served to readiness-based queue management, but delivery challenges suggest the transition may be more complex than initially designed.

Key facts

  • Evidence Submission Window extended beyond July 29, 2025
  • Consultation on methodology updates closes April 21, 2026
  • G2TWQ replaces chronological queue with readiness-based progression
  • Protected Projects designation available for certain existing connections
  • Methodology updates published monthly since November 2025

Timeline

Consultation closes21 Apr 2026

Areas affected

grid connectionsrenewablesstoragetransmissiondistribution

Related programmes

Connections ReformClean Power 2030

Memo

What this is about

NESO has published updated Connections Reform methodologies following the first six months of Gate 2 Two-way Queue (G2TWQ) operations. The methodologies cover network design criteria, project designation rules, and gate progression requirements for the reformed connections process that shifted from first-come-first-served to readiness-based queue management in July 2025.

The publication includes a critical extension to the Evidence Submission Window, originally scheduled to close on 29 July 2025. NESO has extended this deadline by at least five working days due to portal malfunctions and slow query response times, creating uncertainty for projects preparing Gate 2 submissions. This extension signals delivery challenges in NESO's digital infrastructure at a crucial implementation phase.

Key points

Portal Extension and Implementation Issues - Evidence Submission Window closure extended beyond 29 July 2025 with minimum five working days' notice of new deadline - Extension directly attributed to Connections Portal technical problems and NESO's delayed query responses - Subsequent EA timeline dates may require further revision following this initial delay

G2TWQ Process Refinements The methodology updates incorporate six months of operational experience since July 2025 implementation: - Process improvements for more efficient G2TWQ delivery developed through work with Transmission Owners and Distribution Network Operators - Enhanced clarity for different technology types and project configurations within the queue system - Refined project designation criteria based on practical application feedback

Methodology Structure Three core methodologies govern the reformed system: - Connections Network Design Methodology (CNDM) - technical network planning standards and capacity allocation rules - Gate 2 Criteria Methodology - readiness assessment frameworks and progression requirements - Project Designation Methodology - classification rules determining which projects qualify for different treatment pathways

Protected Projects Framework NESO and the three GB Transmission Owners submitted a joint request regarding protected projects under the CNDM, with Ofgem responding on connection date delays for some TMO4+ protected projects. This suggests ongoing tension between reform objectives and existing contractual commitments.

Annual Review Process NESO has launched its annual connections methodology consultation (open until 21 April 2026) seeking stakeholder feedback on proposed updates. The consultation covers marked-up versions showing CMP435 text removals, illustrating potential changes for future application windows.

What happens next

Immediate Timeline Pressure Projects with Existing Agreements must navigate the extended Evidence Submission Window while preparing comprehensive readiness evidence. The portal issues and delayed responses suggest NESO's delivery capability remains under strain during this critical transition period.

Methodology Evolution NESO continues refining the three methodologies based on operational experience. The December 2025 updates show the system remains in active development rather than steady-state operation. Further clarifications and process improvements appear likely as more projects progress through G2TWQ.

Regulatory Oversight Ofgem's involvement in protected projects decisions and methodology approvals indicates continued regulatory scrutiny of reform implementation. The annual consultation process provides a formal mechanism for stakeholder influence, but also suggests the methodologies lack stability six months post-implementation.

CMP435 Implications The marked documents removing CMP435 text suggest potential code modification changes affecting existing contracted projects' treatment within the reformed queue. This creates additional uncertainty for developers already navigating the transition from first-come-first-served to readiness-based allocation.

Infrastructure Reliability Concerns The portal extension exposes fundamental digital delivery risks that could undermine reform credibility. If NESO cannot reliably operate the technical infrastructure supporting queue management, the reformed system's efficiency gains remain theoretical. Industry confidence in the new process depends on resolving these operational failures quickly and comprehensively.

The reform represents a fundamental shift in GB connections philosophy, but delivery challenges suggest the transition complexity exceeds initial design assumptions. Projects face continued uncertainty while NESO works through implementation problems that should have been resolved before launch.

Source text6,174 words

[](#main-content) [![Home](https://www.neso.energy/themes/custom/neso_theme/logo.svg)](/) Please enable JavaScript to use the search interface. An error has occurred while loading the search interface. Please refresh the page. ## Data Portal * [Data Portal](/data-portal) ## User account menu * [Sign in / Register](/saml-login) Show/Hide Menu Toggle ## Main navigation * [What we do](/what-we-do) [What we do](/what-we-do) ![Solar panels in field](/sites/neso.energy/files/styles/medium_cropped/public/2024-06/Solar%20panels%20in%20field-GettyImages-1408864765.jpg?h=1ecad531&itok=KF7_t8Yo) We bring together eight activities required to deliver the plans, markets and operations of the energy system of today and the future. Bringing these activities together in one organisation encourages holistic thinking on the most cost-efficient and sustainable solutions to the needs of our customers. Back [What we do](/what-we-do) [View](/what-we-do) + [Strategic Planning](/what-we-do/strategic-planning) The SEP team work in partnership with governments, Ofgem, industry and wider stakeholders to guide Great Britain on what infrastructure and sources of electricity are required to securely accelerate the transition away from fossil fuels into new energy technologies, including renewable energy. + [Security of Supply](/what-we-do/security-supply) Security of Supply analyses where the energy we need over the short, medium and long-term will come from. In doing so it assesses a wide range of factors that could affect our supply of energy, enabling early actions and decisions to ensure we can meet future demand. + [Systems Operations](/what-we-do/systems-operations) From hospitals to households, telecoms to transportation, our society relies on electricity. Our control centre makes sure there is always a reliable and safe supply as we move megawatts around the country. + [Connections Explained](/what-we-do/connections-explained) We will deliver efficient system access for Generation and Demand projects, so that those projects that are first ready can be first served – delivering the energy system to meet net zero and facilitating economic growth by connecting new and existing industries. + [Resilience & Emergency Management](/what-we-do/resilience-emergency-management) Our energy system is complex, with an increasing number of interconnections. This means that disruption to one part can have implications for another. But this complexity also provides us with more options to mitigate problems. + [Energy Insights](/what-we-do/energy-insights) We will develop comprehensive and independent insights across the entire energy system, offering clear recommendations to policy makers, industry decision makers and leadership across our organisation on how to accelerate energy transition progress. + [Energy Markets](/what-we-do/energy-markets) Whether you’re interested in the innovation underway in the Markets team or are looking to brush up on market fundamentals, you’ve come to the right place. + [Data & AI](/what-we-do/data-ai) NESO will bring together data from multiple sources in a way that enables the modern digitalised energy system needed for a low carbon, flexible and affordable future. + [Helping our customers get ready for NESO](/what-we-do/post-neso-launch-support) * [Energy 101](/energy-101) [Energy 101](/energy-101) ![Smiling lady working at laptop](/sites/neso.energy/files/styles/medium_cropped/public/2024-06/Smiling%20lady%20working%20at%20laptop-GettyImages-1140358859.jpg?h=06f6671c&itok=JWQxbNG-) We’re experts in all things energy – how much we use, where it comes from and how it moves around Great Britain. And we want to share all that knowledge with you. Back [Energy 101](/energy-101) [View](/energy-101) + [Net zero explained](/energy-101/net-zero-explained) Confused about carbon? Need knowledge on net zero? Interested in EVs? You’ve come to the right place. + [Great Britain’s Monthly Energy Stats](/energy-101/great-britains-monthly-energy-stats) Ever wonder how much gas and electricity we use in Great Britain? View our monthly insights into which generation sources provide Great Britain's electricity and learn how much we use each month. + [Electricity explained](/energy-101/electricity-explained) We're the experts in electricity – how much we use, where it comes from, and how it travels into homes and businesses. Understanding how much electricity we consume, and which devices are most power-hungry is no easy task. + [Hydrogen explained](/energy-101/hydrogen-explained) Hydrogen is a growing part of the energy system. As NESO, we have been building our hydrogen expertise during our journey to being NESO and we would love to share it with you. + [Gas explained](/energy-101/gas-explained) Gas has been a part of Great Britain’s energy mix since the Victorian Era. At NESO, we have been supporting the UK Gas system for many years through our supply and demand forecasts. We are building our expertise in gas as we strategically plan the gas system of the future. + [Balancing the Grid - Interactive game](/energy-101/balancing-grid-interactive-game) To give you some insight into the world of balancing the grid, we’ve developed a game where you can attempt to keep the grid stable while facing some of the challenges our control room operatives experience daily. * [Industry information](/industry-information) [Industry information](/industry-information) ![Wind turbine in the sea](/sites/neso.energy/files/styles/medium_cropped/public/2024-06/Wind%20turbine%20in%20the%20sea-GettyImages-852092910.jpg?h=d1cb525d&itok=rwMAnuOI) Are you a balancing provider looking to supply services to us, trying to find the latest Grid Code, or TNUoS charging guidance? Find all the information you need including our operational data, forecasts, and reports designed to help you make efficient decisions. Back [Industry information](/industry-information) [View](/industry-information) + [Balancing costs](/industry-information/balancing-costs) Balancing costs are those costs associated with (A) the Balancing Mechanism, (B) balancing services, and (C) energy trading. + [Balancing services](/industry-information/balancing-services) We procure services to balance demand and supply and to ensure the security and quality of electricity supply across Britain's transmission system. + [Charging](/industry-information/charging) All users of the electricity transmission system pay to use it. This brief overview looks at who pays, for what, and how the charges are calculated. + [Codes](/industry-information/codes) Our team of code administrators oversees all aspects of the code modification processes and related meetings. So whether you’re new to the process, or experienced in the way it all works, we’ll help you get to the information you need. + [Connections](/industry-information/connections) In this section, we’ve got everything you need to understand the connections process. Including what you need to do to connect to, or make use of the National Electricity Transmission System (NETS). + [Connections Reform](/industry-information/connections-reform) The UK’s energy system is undergoing a fundamental transformation. To achieve the government’s Clean Power 2030 ambition and support the transition to net zero, we must reform the way projects connect to the electricity network. + [Flexibility](/industry-information/flexibility) We believe that demand side flexibility has a key role to play in operating a fully decarbonised electricity system which is reliable, affordable and fair + [Market Monitoring](/industry-information/market-monitoring "The Market Monitoring team is engaged in continuous oversight of electricity market activities to identify and address potential non-compliance issues.") + [Industry data and reports](/industry-information/industry-data-and-reports) These pages contain data and support for users of the National Electricity Transmission System (NETS). Here you will find the latest operational data, forecasts, and reports. + [Network access planning](/industry-information/network-access-planning) Our Network Access Planning engineers are responsible for assessing, co-ordinating and sanctioning the planned release of assets from the National Electricity Transmission System. + [Reformed National Pricing](/industry-information/reformed-national-pricing "Effective markets are key to delivering and operating the most efficient energy system, and it is critical that those markets are efficiently designed and implemented to deliver affordable, secure and clean energy") Effective markets are key to delivering and operating the most efficient energy system, and it is critical that those markets are efficiently designed and implemented to deliver affordable, secure and clean energy + [System Access Reform](/industry-information/system-access-reform) * [News and events](/news-and-events) [News and events](/news-and-events) All the latest news from the heart of Great Britain's electricity system. Find out how we balance the grid, how we’re innovating for the future, and who the people are that are working on Britain's energy system around the clock. Back [News and events](/news-and-events) [View](/news-and-events) * [Publications](/publications-library) [Publications](/publications-library) ![Man doing woodwork in his workshop](/sites/neso.energy/files/styles/medium_cropped/public/2024-06/Man%20doing%20woodwork%20in%20his%20workshop-GettyImages-548417453.jpg?h=dbe779b6&itok=xPIAVWwI) We've got a wide range of publications offering energy insights and analysis. Download our reports and data to see the innovative ways we are transforming the future of Great Britain’s energy. Back [Publications](/publications-library) [View](/publications-library) + [View all of our publications](/publications-library) Find a wide range of publications that provide energy insight and analysis right here, as well as information about how we're shaping the future of energy in Great Britain. + [Beyond 2030](/publications/beyond-2030) The Beyond 2030 report builds on top of the Holistic Network Design and makes a set of network recommendations throughout the 2030s. + [Future Energy Scenarios (FES)](/publications/future-energy-scenarios-fes) Future Energy Scenarios (FES) represent a range of different, credible ways to decarbonise our energy system as we strive towards the 2050 target. + [Transitional Centralised Strategic Network Plan (tCSNP)](/publications/transitional-centralised-strategic-network-plan-tcsnp) We have been enhancing our approach to planning the GB electricity transmission network through a series of transitional CSNPs. + [Clean Power 2030](/publications/clean-power-2030) Achieving clean power by 2030 whilst keeping the system secure and affordable for consumers would be a world-leading achievement. + [Electricity Ten Year Statement (ETYS)](/publications/electricity-ten-year-statement-etys) The Electricity Ten Year Statement (ETYS) is our view of future transmission requirements and the capability of Great Britain’s National Electricity Transmission System (NETS) over the next 10 years. + [GB Reduced Model](/publications/gb-reduced-model "The GB Reduced Model is a simplified representation of the National Electricity Transmission System of Great Britain, developed using DIgSILENT PowerFactory.") The GB Reduced Model is a simplified representation of the National Electricity Transmission System of Great Britain, developed using DIgSILENT PowerFactory. + [North Hyde Review](/publications/north-hyde-review "NESO publishes its interim findings from the review into the North Hyde Substation outage which took place on 20 March and led to the closure of Heathrow Airport.") NESO publishes its interim findings from the review into the North Hyde Substation outage which took place on 20 March and led to the closure of Heathrow Airport. + [Operability Strategy Report and Electricity Markets Roadmap](/publications/markets-roadmap) We are developing new ways to balance electricity supply and demand and manage a low carbon electricity system, helping to meet net zero targets and minimise costs for consumers. + [Summer Outlook](/publications/summer-outlook) Summer Outlook reports are designed to inform the energy industry and support its preparations, we also outline Great Britain’s projected electricity needs for the summer ahead. + [Winter Outlook](/publications/winter-outlook) The Winter Outlook Report presents our view of security of supply for the electricity systems for the winter ahead. + [Whole electricity system](/publications/whole-electricity-system "The journey to creating an energy system fit for the future wouldn’t be possible without close collaboration with industry partners to help the transition.") The journey to creating an energy system fit for the future wouldn’t be possible without close collaboration with industry partners to help the transition. + [System Operability Framework (SOF)](/publications/system-operability-framework-sof) The System Operability Framework (SOF) takes a holistic view of the changing energy landscape to assess the future operation of Britain's electricity networks. + [Regional Development Programmes](/publications/regional-development-programmes-rdps) RDPs look across the whole electricity system to unlock more network capacity, reduce constraints and open new revenue streams for market participants. * [Careers](/careers) [Careers](/careers) Back [Careers](/careers) [View](/careers) * [About](/about-neso) [About](/about-neso) ![Dad and son working on kitchen table](/sites/neso.energy/files/styles/medium_cropped/public/2024-07/Dad%20and%20son%20working%20on%20kitchen%20table-GettyImages-1149030800.jpg?h=9a8607c3&itok=WtMtexJg) We ensure that Great Britain has the essential energy it needs by making sure supply meets demand every second of every day. Back [About](/about-neso) [View](/about-neso) + [Strategic priorities](/about/strategic-priorities) As a new organisation we recognise our responsibility to deliver right from the start. The strategic priorities that we are driving towards can be found on this page. + [Our people](/about/our-people) We work with a whole range of experts, including engineers, academics and industry professionals so that we can safely deliver affordable and clean energy to customers. As we build a greener electricity system of the future our people know they are shaping the future for generations to come. + [A whole system challenge](/about/whole-system-challenge) + [Operational information](/about/operational-information) Want to know how we're regulated or how we're organised? Interested in our compliance statements and consultation responses? Our operational information page is where you can find all of this and more. + [European engagement](/about/european-engagement) NESO’s ongoing work with European political and industry stakeholders + [Innovation](/about/innovation) Innovation is critical to helping us meet the challenges of transitioning to a zero carbon future. As we sit at the very heart of the energy system, we play a central role in overcoming these challenges. + [Our progress towards net zero](/about/our-progress-towards-net-zero) Read the story of how the we have decarbonised the electricity system to date, offering a blueprint to other countries around the world to help them reduce emissions. + [Our projects](/about/our-projects) All of our projects contribute towards our effort to make the grid ready to operate with 100% zero carbon electricity by 2025. ## Breadcrumb 1. [Home](/) 2. [Industry information](/industry-information) 3. [Connections Reform](/industry-information/connections-reform) 4. Connections Reform design documents and methodologies Add to favourites Close tooltip Sign in to add this page to your favourites [Sign in or register](/saml-login) Show favourites Close Close tooltip Sign in or register to manage your favourites [Sign in or register](/saml-login) [Help](https://www.neso.energy/help-centre) ###### In this section * [About Connections Reform](/industry-information/connections-reform/about-connections-reform) [About Connections Reform](/industry-information/connections-reform/about-connections-reform) Back [About Connections Reform](/industry-information/connections-reform/about-connections-reform) [View](/industry-information/connections-reform/about-connections-reform) * [Advancement fees](/industry-information/connections-reform/advancement-fees) [Advancement fees](/industry-information/connections-reform/advancement-fees) Back [Advancement fees](/industry-information/connections-reform/advancement-fees) [View](/industry-information/connections-reform/advancement-fees) * [Connection Reform Customer area](/industry-information/connections-reform/connection-reform-customer-area) [Connection Reform Customer area](/industry-information/connections-reform/connection-reform-customer-area) Back [Connection Reform Customer area](/industry-information/connections-reform/connection-reform-customer-area) [View](/industry-information/connections-reform/connection-reform-customer-area) * [Connection Reform webinars and archive](/industry-information/connections-reform/connection-reform-webinars-and-archive "For more information join one of our webinars or view our webinar archive videos.") [Connection Reform webinars and archive](/industry-information/connections-reform/connection-reform-webinars-and-archive) Back [Connection Reform webinars and archive](/industry-information/connections-reform/connection-reform-webinars-and-archive) [View](/industry-information/connections-reform/connection-reform-webinars-and-archive) * [Connections Reform Archive](/industry-information/connections-reform/connections-reform-archive) [Connections Reform Archive](/industry-information/connections-reform/connections-reform-archive) Back [Connections Reform Archive](/industry-information/connections-reform/connections-reform-archive) [View](/industry-information/connections-reform/connections-reform-archive) * [Connections Reform Portal Updates](/industry-information/connections-reform/connections-reform-portal-updates) [Connections Reform Portal Updates](/industry-information/connections-reform/connections-reform-portal-updates) Back [Connections Reform Portal Updates](/industry-information/connections-reform/connections-reform-portal-updates) [View](/industry-information/connections-reform/connections-reform-portal-updates) * [Connections Reform Results](/industry-information/connections-reform/connections-reform-results) [Connections Reform Results](/industry-information/connections-reform/connections-reform-results) Back [Connections Reform Results](/industry-information/connections-reform/connections-reform-results) [View](/industry-information/connections-reform/connections-reform-results) * [Connections Reform design documents and methodologies](/industry-information/connections-reform/connections-reform-design-documents-and-methodologies) [Connections Reform design documents and methodologies](/industry-information/connections-reform/connections-reform-design-documents-and-methodologies) Back [Connections Reform design documents and methodologies](/industry-information/connections-reform/connections-reform-design-documents-and-methodologies) [View](/industry-information/connections-reform/connections-reform-design-documents-and-methodologies) * [Connections reform timeline](/industry-information/connections-reform/connections-reform-timeline "Access the interactive connections reform timeline here") [Connections reform timeline](/industry-information/connections-reform/connections-reform-timeline) Back [Connections reform timeline](/industry-information/connections-reform/connections-reform-timeline) [View](/industry-information/connections-reform/connections-reform-timeline) * [Contacting us about connections reform​](/industry-information/connections-reform/contacting-us-about-connections-reform) [Contacting us about connections reform​](/industry-information/connections-reform/contacting-us-about-connections-reform) Back [Contacting us about connections reform​](/industry-information/connections-reform/contacting-us-about-connections-reform) [View](/industry-information/connections-reform/contacting-us-about-connections-reform) * [Evidence handbook and other G2WQ submission resources](/industry-information/connections-reform/evidence-handbook-and-other-g2wq-submission-resources) [Evidence handbook and other G2WQ submission resources](/industry-information/connections-reform/evidence-handbook-and-other-g2wq-submission-resources) Back [Evidence handbook and other G2WQ submission resources](/industry-information/connections-reform/evidence-handbook-and-other-g2wq-submission-resources) [View](/industry-information/connections-reform/evidence-handbook-and-other-g2wq-submission-resources) * [Gated Modification Guidance](/industry-information/connections-reform/gated-modification-guidance) [Gated Modification Guidance](/industry-information/connections-reform/gated-modification-guidance) Back [Gated Modification Guidance](/industry-information/connections-reform/gated-modification-guidance) [View](/industry-information/connections-reform/gated-modification-guidance) * [Interactivity Policy Guidance](/industry-information/connections-reform/interactivity-policy-guidance) [Interactivity Policy Guidance](/industry-information/connections-reform/interactivity-policy-guidance) Back [Interactivity Policy Guidance](/industry-information/connections-reform/interactivity-policy-guidance) [View](/industry-information/connections-reform/interactivity-policy-guidance) * [Material Technology Change Guidance](/industry-information/connections-reform/material-technology-change-guidance) [Material Technology Change Guidance](/industry-information/connections-reform/material-technology-change-guidance) Back [Material Technology Change Guidance](/industry-information/connections-reform/material-technology-change-guidance) [View](/industry-information/connections-reform/material-technology-change-guidance) * [Pipeline Notification Enquiries](/industry-information/connections-reform/pipeline-notification-enquiries) [Pipeline Notification Enquiries](/industry-information/connections-reform/pipeline-notification-enquiries) Back [Pipeline Notification Enquiries](/industry-information/connections-reform/pipeline-notification-enquiries) [View](/industry-information/connections-reform/pipeline-notification-enquiries) * [Preparing to submit evidence: Readiness declaration](/industry-information/connections-reform/preparing-submit-evidence-readiness-declaration) [Preparing to submit evidence: Readiness declaration](/industry-information/connections-reform/preparing-submit-evidence-readiness-declaration) Back [Preparing to submit evidence: Readiness declaration](/industry-information/connections-reform/preparing-submit-evidence-readiness-declaration) [View](/industry-information/connections-reform/preparing-submit-evidence-readiness-declaration) * [Project designation](/industry-information/connections-reform/project-designation) [Project designation](/industry-information/connections-reform/project-designation) Back [Project designation](/industry-information/connections-reform/project-designation) [View](/industry-information/connections-reform/project-designation) * [Readiness declaration template](/industry-information/connections-reform/readiness-declaration-template) [Readiness declaration template](/industry-information/connections-reform/readiness-declaration-template) Back [Readiness declaration template](/industry-information/connections-reform/readiness-declaration-template) [View](/industry-information/connections-reform/readiness-declaration-template) * [Reservation for Network Services Procurement](/industry-information/connections-reform/reservation-network-services-procurement) [Reservation for Network Services Procurement](/industry-information/connections-reform/reservation-network-services-procurement) Back [Reservation for Network Services Procurement](/industry-information/connections-reform/reservation-network-services-procurement) [View](/industry-information/connections-reform/reservation-network-services-procurement) * [Submitting evidence for your project as part of Connections Reform](/industry-information/connections-reform/submitting-evidence-your-project-part-connections-reform) [Submitting evidence for your project as part of Connections Reform](/industry-information/connections-reform/submitting-evidence-your-project-part-connections-reform) Back [Submitting evidence for your project as part of Connections Reform](/industry-information/connections-reform/submitting-evidence-your-project-part-connections-reform) [View](/industry-information/connections-reform/submitting-evidence-your-project-part-connections-reform) * [Understanding your offer and the support available to you](/industry-information/connections-reform/understanding-your-offer-and-support-available-you) [Understanding your offer and the support available to you](/industry-information/connections-reform/understanding-your-offer-and-support-available-you) Back [Understanding your offer and the support available to you](/industry-information/connections-reform/understanding-your-offer-and-support-available-you) [View](/industry-information/connections-reform/understanding-your-offer-and-support-available-you) * [Progression Commitment Fee (PCF)](/industry-information/connections-reform/progression-commitment-fee-pcf) [Progression Commitment Fee (PCF)](/industry-information/connections-reform/progression-commitment-fee-pcf) Back [Progression Commitment Fee (PCF)](/industry-information/connections-reform/progression-commitment-fee-pcf) [View](/industry-information/connections-reform/progression-commitment-fee-pcf) ![my-ESO-account-path](/modules/custom/eso_samlauth/images/first-login-overlay-neso.png) ## You are now signed in Visit My NESO account to view and manage your dataset subscriptions. Maybe later [Go to your account](/user/dashboard) # Connections Reform design documents and methodologies This page acts as a central library for key connections reform relating to the case for change, the solution design an the detailed design and framework changes. ## Existing Agreements (EA) Timeline to support Connections Reform This document confirms the key dates and the specific timings for the various activities in the Gated Process for Projects with Existing Agreements, in particular the start and duration of the EA Request Window when Projects with Existing Agreements can submit their EA Requests (i.e. Readiness Declarations, Original Red Line Boundaries (ORLB) and, where required, Modification Applications) or Gate 1 Notifications. The EA timeline states the closure date for the Connections Reform Evidence Submission Window as 29 July. The Connections Reform Evidence Submission Window will be extended by at least five working days beyond the original deadline day of 29 July 2025. This extension is in direct response to the challenges customers have faced with our Connections Portal and NESO's response times to resolve your queries. NESO will announce a new closure day with a minimum of five working days’ notice. Following the extension, announced on 16 July, subsequent dates may also be subject to change. [Phase 3 – Detailed design, framework changes](#Phase-3-–-Detailed-design-framework-changes) [Phase 2 – Solution design](#Phase2-–-Solution-design) [Phase 1 – Case for change](#Phase-1-–-Case-for-change) [Key documents](#Key-documents) Phase 3 – Detailed design, framework changes Phase 2 – Solution design Phase 1 – Case for change Key documents Phase 3 – Detailed design, framework changes This reform project forms part of our longer-term vision for change to the connections process. We also have a number of short-term initiatives to speed up connections to the grid, through our [five-point plan](/industry-information/connections/our-five-point-plan). Connections Reform Methodology Consultation - March 2026 Protected Projects Request 2026 Connections Reform methodology update January 2026 Connections Reform methodology update December 2025 Connections Reform methodology update November 2025 Connections Reform Final Methodologies (April 2025) Connections Reform Methodologies – March 2025 Connection Reform Methodology Consultation - Non Confidential Responses Connections Reform Methodologies – December 2024 Phase 3: Consultation Documents Land rights request for information analysis Final recommendations report Financial Instruments Connections Reform Methodology Consultation - March 2026 Protected Projects Request 2026 Connections Reform methodology update January 2026 Connections Reform methodology update December 2025 Connections Reform methodology update November 2025 Connections Reform Final Methodologies (April 2025) Connections Reform Methodologies – March 2025 Connection Reform Methodology Consultation - Non Confidential Responses Connections Reform Methodologies – December 2024 Phase 3: Consultation Documents Land rights request for information analysis Final recommendations report Financial Instruments Rich text We are required under our licence obligation to keep the Connections Methodologies under regular review. As part of this process, we are seeking stakeholder feedback on a set of proposed updates and improvements. The consultation is open until 17:00 on 21 April 2026. Consultation responses can be submitted to [[email protected]](/cdn-cgi/l/email-protection#0c6e6374226f636262696f786563627f7e696a637e614c62697f63226962697e6b75). | [Name](?order=title&sort=asc "sort by Name") | | --- | | [Connections Methodologies Consultation Response Template March 2026](/document/378751/download) | | [Connections Methodologies Consultation Overview Document March 2026](/document/378746/download) | | [Connections Network Design Methodology (March 2026) Marked](/document/378756/download) | | [Gate 2 Criteria Methodology (March 2026) Marked](/document/378761/download) | | [Ofgem Letter Statement for Connections Methodologies Updates (March 2026)](/document/378766/download) | | [Project Designation Methodology (March 2026) Marked CMP435 Removals](/document/378781/download) | | [Project Designation Methodology (March 2026) Marked (Consultation)](/document/378776/download) | | [Project Designation Methodology (March 2026) Clean CMP435 Removals](/document/378771/download) | ## Protected Projects Request 2026 Rich text Below is a "Request from NESO and all 3 GB Transmission Owners (i.e. SSEN Transmission, SP Transmission plc and National Grid Electricity Transmission) (“TOs”) in relation to the Connections Network Design Methodology (“CNDM”) Protections" along with Ofgem's response. For Ofgem's response to this letter, please see: [Update on delays to connection dates for some TMO4+ Protected Projects | Ofgem](https://www.ofgem.gov.uk/publications/update-delays-connection-dates-some-tmo4-protected-projects). | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Protected Projects Request](/document/376861/download) | 6 Feb 2026 | ## Connections Reform methodology update January 2026 Rich text In December 2025, we published a ‘Further connections methodologies update’ to accompany the marked‑up and clean versions of the Connections Network Design Methodology (CNDM) and Gate 2 Criteria Methodology (G2CM). These follow-up documents are to help NESO and industry prepare for the annual connections methodology review and consultation process starting soon by showing marked and clean versions of the connections methodologies that focus only on the unchanged arrangements for the first CMP434 application window i.e. what they look like with CMP435 text removed, solely for illustrative purposes at this stage. | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Connections Methodologies Update to Remove CMP435](/document/376201/download) | 21 Jan 2026 | | [Connections Network Design Methodology (December 2025) - Clean CMP435 Removals](/document/376206/download) | 21 Jan 2026 | | [Gate 2 Criteria Methodology (December 2025) - Clean CMP435 Removals](/document/376221/download) | 21 Jan 2026 | | [Connections Network Design Methodology (December 2025) - Marked CMP435 Removals](/document/376216/download) | 21 Jan 2026 | | [Gate 2 Criteria Methodology (December 2025) - Marked CMP435 Removals](/document/376211/download) | 21 Jan 2026 | ## Connections Reform methodology update December 2025 Rich text As part of detailed design and delivery of G2TWQ since July 2025, including through working with our delivery partners (Transmission Owners and Distribution Network Operators) we have identified several key process improvements that allow for more efficient implementation of G2TWQ. As part of our engagement with customers and other stakeholders we have also identified several key areas where further clarification of the methodologies is beneficial in order to ensure that the full range of technologies and project types are able to participate fully and with clarity within the G2TWQ process. These documents provides an overview of those key process improvements and key further clarifications. | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Connections Network Design Methodology (December 2025) - Marked](/document/375021/download) | 22 Dec 2025 | | [Connections Network Design Methodology (December 2025) - Clean](/document/375026/download) | 22 Dec 2025 | | [Further connections methodologies update Dec 2025](/document/375006/download) | 22 Dec 2025 | | [Gate 2 Criteria Methodology (December 2025) - Marked](/document/375011/download) | 22 Dec 2025 | | [Gate 2 Criteria Methodology (December 2025) - Clean](/document/375016/download) | 22 Dec 2025 | ## Connections Reform methodology update November 2025 Rich text As part of detailed design and delivery of G2TWQ since July 2025, including through working with our delivery partners (Transmission Owners and Distribution Network Operators) we have identified several key process improvements that allow for more efficient implementation of G2TWQ. As part of our engagement with customers and other stakeholders we have also identified several key areas where further clarification of the methodologies is beneficial in order to ensure that the full range of technologies and project types are able to participate fully and with clarity within the G2TWQ process. These documents provides an overview of those key process improvements and key further clarifications. | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Ofgem Response Connections methodologies update Nov 2025](/document/372036/download) | 13 Nov 2025 | | [Connections methodologies update Nov 2025](/document/371986/download) | 13 Nov 2025 | | [Connections methodologies update Nov 2025 Ofgem letter](/document/371981/download) | 13 Nov 2025 | ## Connections Reform Final Methodologies (April 2025) Rich text Following Ofgem’s approval of our connections reform proposals, we identified some small changes to be made to the proposed methodologies, primarily as a result of the Ofgem Decision and their recommendations. We have now finalised and published the three connections methodologies. We have also published ‘marked up’ versions of these three final methodologies so customers can easily see what has been changed since the proposed March 2025 versions. We have also published an overview of changes which provides details on what has changed in one place. | [Name](?order=title&sort=asc "sort by Name") | | --- | | [Connections Network Design Methodology (April 2025)](/document/359781/download) | | [Gate 2 Criteria Methodology (Marked) (April 2025)](/document/359791/download) | | [Connections Network Design Methodology (Marked) (April 2025)](/document/359796/download) | | [Gate 2 Criteria Methodology (April 2025)](/document/359776/download) | | [Project Designation Methodology (Marked) (April 2025)](/document/359801/download) | | [Project Designation Methodology (April 2025)](/document/359786/download) | | [Connections Methodologies - Overview of Changes (April 2025)](/document/359806/download) | ## Connections Reform Methodologies – March 2025 Rich text We have taken the opportunity to review the three connections methodologies in the context of Ofgem’s consultation and further engagement with a range of stakeholders since 20 December 2024. In that context we have identified some small changes to be made to the three connections methodologies. On 21 March 2025 we published ‘marked up’ versions of our three proposed methodologies, which have been submitted to Ofgem for decision. These also illustrate the changes that would be required if WACM1 is approved. | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Gate 2 Criteria Methodology (March 2025)](/document/357066/download) | 21 Mar 2025 | | [Project Designation Methodology (March 2025)](/document/357071/download) | 21 Mar 2025 | | [Connections Network Design Methodology (March 2025)](/document/357076/download) | 21 Mar 2025 | | [Connections Methodologies – Overview of changes (March 2025)](/document/357081/download) | 21 Mar 2025 | ## Connection Reform Methodology Consultation - Non Confidential Responses | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Connection Reform Methodology Consultation - Non Confidential Responses S-Z](/document/350956/download) | 9 Jan 2025 | | [Connection Reform Methodology Consultation - Non Confidential Responses I-R](/document/350951/download) | 9 Jan 2025 | | [Connection Reform Methodology Consultation - Non Confidential Responses A-H](/document/350946/download) | 9 Jan 2025 | | [Connection Reform Methodology Consultation - Non Confidential Non Confidential Responses Received via Online Form](/document/350961/download) | 9 Jan 2025 | ## Connections Reform Methodologies – December 2024 Rich text Shapefiles: Maps are illustrative only and are not intended to allocate specific projects to specific areas | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [CP30 Zonal Mapping Details](/document/351441/download) | 17 Jan 2025 | | [DESNZ Clean Power 2030 Action Plan Distribution zones shapefile](/document/351451/download) | 17 Jan 2025 | | [DESNZ Clean Power 2030 Action Plan Transmission zones shapefile](/document/351446/download) | 17 Jan 2025 | | [Consultation Summary Report](/document/350251/download) | 20 Dec 2024 | | [Connections Reform Data Impact Assessment Part B - Workbook](/document/350356/download) | 20 Dec 2024 | | [Connections Network Design Methodology (CNDM)](/document/350241/download) | 20 Dec 2024 | | [Gate 2 Methodology](/document/350236/download) | 20 Dec 2024 | | [Project Designation Methodology](/document/350246/download) | 20 Dec 2024 | | [Impact Assessment for Connections Reform](/document/350256/download) | 20 Dec 2024 | ## Phase 3: Consultation Documents We introduced our consultation questions at the start of our [Overview document](https://www.neso.energy/document/346816/download) (pages 9 and 10) and welcome your views on each of these questions. Please use the detailed documents on each of the methodologies to inform your responses. Please provide your feedback by completing this [Connections Reform Consultation Response Form](https://forms.office.com/r/Pz7G7XGTJk "https://forms.office.com/r/pz7g7xgtjk") or by completing this [Connections Reform: Consultation Response Proforma](https://www.neso.energy/document/346731/download "https://www.neso.energy/document/346731/download") and sending an electronic copy to [box.connectionsreform@n](/cdn-cgi/l/email-protection#03616c7b2d606c6d6d6660776a6c6d707166656c716e436d66706c2d666d6671647a "mailto:box.connectionsreform@nationalenergyso.com")[es](/cdn-cgi/l/email-protection#0a68657224696564646f697e63656479786f6c6578674a646f7965246f646f786d73)[o](/cdn-cgi/l/email-protection#e4868b9cca878b8a8a8187908d8b8a979681828b9689a48a81978bca818a8196839d "mailto:box.connectionsreform@nationalenergyso.com")[.](/cdn-cgi/l/email-protection#6604091e48050908080305120f09081514030009140b26080315094803080314011f)[energy](/cdn-cgi/l/email-protection#72101d0a5c111d1c1c1711061b1d1c010017141d001f321c17011d5c171c1700150b "mailto:box.connectionsreform@nationalenergyso.com") by 5pm on the closing date of 2nd December 2024. We will publish all consultation responses unless they are marked confidential. If you do not wish your response to be published, please clearly mark it as confidential. Please note even confidential responses will be shared with Ofgem. By responding you agree to our sharing your response with Ofgem. To support you in your response and to answer any questions, we will be holding at least one webinar in November, which we encourage you to attend. | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Draft - NESO Connections Reform Data Impact Assessment](/document/346821/download) | 5 Nov 2024 | | [Great Britain's Connections Reform - Overview Document](/document/346816/download) | 5 Nov 2024 | | [Connections Reform: Consultation Response Proforma](/document/346731/download) | 5 Nov 2024 | | [Connections Network Design Methodology (CNDM)](/document/346666/download) | 5 Nov 2024 | | [Project Designation Methodology](/document/346661/download) | 5 Nov 2024 | | [Gate 2 Criteria Methodology](/document/346656/download) | 5 Nov 2024 | ## Phase 3 updates We are pleased to provide you with a high level overview of our enhanced First Ready, First Connected approach (referred to as ‘TMO4+’). This document summarises significant progress made since our final recommendation report, which was published in December 2023. Our commitment to enhancing the connections process has been worked on through extensive engagement and valuable input from stakeholders, including the Connections Process Advisory Group (CPAG). In response to these collaborative efforts, we are now also recommending the application of the ‘Gate 2’ approach to the existing queue. This is effectively the preferred model we recommended in December 2023 but with this addition and further targeted amendments. This strategic decision is aimed at better meeting our reform objectives and those within the Connections Action Plan, as well as ensuring a smoother and more efficient process in future. [Download the phase 3 update](/document/316446/download) ## Land rights request for information analysis A high-level summary of results has been published from our recent Request For Information (RFI) on land rights held from May to June 2024. The RFI requested contains details from developers holding a signed contract with us about their ability to meet land rights criteria and planning status’. Under proposed code modifications, retaining existing connection dates or being able to accelerate the date is dependent on meeting specified criteria such as having secured land rights. Having an early understanding of projects that can meet these criteria enables us to better assess the impact of proposals [CMP434](/industry-information/codes/cusc/modifications/cmp434-implementing-connections-reform) & [CM095](/industry-information/codes/stc/modifications/cm095-implementing-connections-reform) and [CMP435](/industry-information/codes/cusc/modifications/cmp435-application-gate-2-criteria-existing-contracted-background) & [CM096](/industry-information/codes/stc/modifications/cm096-application-gate-2-criteria-existing-contracted-background), and whether projects can or cannot be accelerated under a reformed queue. Overall, findings were largely in line with the assumptions we made and support changes proposed under Connections Reform [TMO4+](/industry-information/connections/connections-reform), which will potentially halve the size of the queue. [RFI summary analysis](/document/322226/download) ## Final recommendations report We have published our [final recommendations](/document/298496/download) on 5 December 2023. These can be viewed on the key documents tab in the December 2023 Final Recommendations section. We will now start a detailed process design and implementation phase, to conclude in January 2025. [Download the final recommendations summary](/document/298491/download) We hosted a series of events in December to share our final recommendations in more detail and show how it links to wider industry reforms including Ofgem and Department for Energy Security and Net Zero's Connections Action Plan and the ENA 3 point plan. [Watch the webinar - 14 Dec](https://youtu.be/LyJcDHvnx7g) [Download the slide deck](/document/299436/download) ## Financial Instruments There is an urgent need to reform Great Britain’s electricity connection process. NESO is proposing to introduce a Financial Instrument alongside the wider suite of connections reforms. The proposal would require projects in the Gate 2 queue to demonstrate financial commitment for a confirmed connection agreement. On 11 Oct 24, we took this proposal to the Transmission Charging Methodologies Forum and received useful feedback from stakeholders during and after the meeting. We are committed to listening to feedback and working collaboratively with stakeholders, and understand that our proposals will change the landscape for investors and developers. We want to ensure our initial proposal reaches and is understood by the widest range of stakeholders before formally raising the modification. As such, we would like to invite further feedback on the Financial Instrument as we refine our proposal. | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Call for Input - Financial Instrument](/document/346826/download) | 5 Nov 2024 | Phase 2 – Solution design Phase 2 enabled us to co-create the solutions to the challenges we identified in phase 1 by working with industry-wide stakeholder groups to create and test a series of options for implementation. This resulted in the launch of our proposal consultation. Our consultation was live for six weeks between 13 June and 28 July. We want to thank all of our stakeholders for their feedback, which will help shape the future of the connections process. All formal Connections Reform consultation responses received are now under review. We continue to work with our stakeholder governance groups to establish our final recommendations and refine our proposals on how to implement and transition to a new operating model. ### Phase 2 Structure & Timeline This phase will be done in an agile manner via a number of 'sprints' which, when combined, will consider the full breadth of possible options Image ![Connections Phase 2 structure and timeline](/sites/neso.energy/files/styles/wide/public/media/%5Bmedia%3Abundle%3Atarget_id%5D/2024-09/Connections%20Phase%202%20structure%20and%20timeline%20cropped.png?itok=4aOIwLVL) Phase 1 – Case for change We spent phase 1 gathering stakeholder views to understand the current challenges with the connections application process, and articulated the case for change. We’ve met with over 100 customers, stakeholders, and industry participants to hear your views on the current connections process. The case for change report pulls all that feedback into one central place. #### GB Connections Reform – case for change report This report pulls all the feedback gathered during phase 1 into one central place to enable us to progress to phase 2, which will investigate options. [Download the report](/document/273021/download) Key documents December 2023 Final Recommendations Publications Governance groups Webinars and events December 2023 Final Recommendations Publications Governance groups Webinars and events ## December 2023 Final Recommendations | [Name](?order=title&sort=asc "sort by Name") | | --- | | [Annex 6 - Non-minimum Viable Product (MVP) Final Recommendations](/document/299371/download) | | [Connections Reform - Final Recommendations Report - Dec 23](/document/298496/download) | | [Annex 4 - Gate 2 Options](/document/298516/download) | | [Annex 3 - Revised Design Criteria Assessment](/document/298511/download) | | [Annex 2 - Target Model Option (TMO) 4 Process Overview](/document/298506/download) | | [Annex 1 - Consultation Question Response Summaries](/document/298501/download) | | [Annex 5 - Connections Process Advisory Group Terms of Reference (draft)](/document/298521/download) | | [Connections Reform - Final Recommendations Summary - Dec 23](/document/298491/download) | ## Connections Correspondence | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Securities Freeze due to the implementation of Connections Reform](/document/375916/download) | 15 Jan 2026 | | [Open letter on connections reform](/document/349496/download) | 10 Dec 2024 | ## Summer 2023 consultation | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Consultation launch events Q&A](/document/283126/download) | 10 Jul 2023 | | [Appendix 3 - International case studies](/document/283121/download) | 12 Jun 2023 | | [Connections Reform Summary](/document/281511/download) | 12 Jun 2023 | | [Appendix 1 - Stakeholder Engagement](/document/281556/download) | 12 Jun 2023 | | [Appendix 2 - Design Criteria Assessment](/document/281551/download) | 12 Jun 2023 | | [Appendix 4 - Initial Recommendations Overview](/document/281546/download) | 12 Jun 2023 | | [Appendix 5 - Case Studies](/document/281541/download) | 12 Jun 2023 | | [Appendix 6 - Target Model Add-ons](/document/281536/download) | 12 Jun 2023 | | [Appendix 7 - Consultation Questions](/document/281531/download) | 12 Jun 2023 | | [Connections Reform Consultation](/document/281561/download) | 12 Jun 2023 | ## Summer 2023 consultation responses | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Response 58 - (SSEND)](/document/290611/download) | 18 Oct 2023 | | [Response 80 - SEAS](/document/290616/download) | 18 Oct 2023 | | [Response 59 - IGP](/document/290606/download) | 18 Oct 2023 | | [Response 65 - Solar Energy UK](/document/290601/download) | 18 Oct 2023 | | [Response 41 - IB Vogt](/document/290596/download) | 18 Oct 2023 | | [Response 78 - Fred Olsen Seawind](/document/287476/download) | 4 Sep 2023 | | [Response 77 - The Crown Estate](/document/287471/download) | 4 Sep 2023 | | [Response 76 - Scottish Renewables](/document/287466/download) | 4 Sep 2023 | | [Response 74 - Research Relay Ltd](/document/287461/download) | 4 Sep 2023 | | [Response 72 - SPR](/document/287456/download) | 4 Sep 2023 | #### Pagination * [Current page 1](?page=0 "Current page") * [Page 2](?page=1 "Go to page 2") * [Page 3](?page=2 "Go to page 3") * [Page 4](?page=3 "Go to page 4") * … * [Next page](?page=1 "Go to next page") * [Last page](?page=5 "Go to last page") ## Steering group documents | [Name](?order=title&sort=asc "sort by Name") | [Published Sort ascending](?order=field_publication_date&sort=asc "sort by Published") | | --- | --- | | [Connections process advisory group 11 minutes - 25 Oct 2024](/document/349406/download) | 9 Dec 2024 | | [Connections process advisory group 10 minutes - 12 Sept 2024](/document/349396/download) | 8 Dec 2024 | | [Connections process advisory group 9 minutes - 22 July 2024](/document/330311/download) | 9 Oct 2024 | | [Connections process advisory group 8 minutes - 19 June 2024](/document/321811/download) | 24 Jul 2024 | | [Connections process advisory group 7 minutes - 9 May 2024](/document/320201/download) | 19 Jun 2024 | | [Connections process advisory group 6 minutes - 18 April 2024](/document/318471/download) | 14 May 2024 | | [Connections process advisory group 5 minutes - 7 March 2024](/document/317291/download) | 25 Apr 2024 | | [Connections process advisory group 4 minutes - 22 Feb 2024](/document/308701/download) | 22 Mar 2024 | | [Connections process advisory group 3 minutes - 8 Feb 2024](/document/303191/download) | 26 Feb 2024 | | [Connections process advisory group 2 minutes - 25 Jan 2024](/document/302581/download) | 14 Feb 2024 | #### Pagination * [Current page 1](?page=0 "Current page") * [Page 2](?page=1 "Go to page 2") * [Page 3](?page=2 "Go to page 3") * [Next page](?page=1 "Go to next page") * [Last page](?page=2 "Go to last page") #### Consultation launch: summer 2023 [Watch the webinar](https://youtu.be/z9DJDuTv_Tw) [Download the slides](/document/282456/download) #### #### Design sprints webinar: spring 2023 | Design sprints documents | | --- | | [Connections Reform design sprint outputs - May 2023](https://players.brightcove.net/867903724001/default_default/index.html?videoId=6327286705112) | #### #### Case for change webinar: winter 2022/23 | Case for change documents | | --- | | [Case for change presentation - 12/13 Dec 2022](/document/273666/download) | | [Case for change webinar recording - 10 Jan 2023](https://players.brightcove.net/867903724001/default_default/index.html?videoId=6318604486112) | | [Case for change FAQs](/document/273671/download) | ### [Mailing list](https://neso.createsend.com/h/d/918820CF9659BD06) [![Man charging his EV car](/sites/neso.energy/files/styles/tile_large/public/2024-07/Man%20charging%20his%20EV%20car-GettyImages-1449024276.jpg?h=06f6671c&itok=5GCDETLg)](https://neso.createsend.com/h/d/918820CF9659BD06) Subscribe to the connections reform mailing list. ### [Connections events](https://www.neso.energy/industry-information/connections/customer-connection-events) [![Dad and his children looking out the sea with his little girl on his shoulders](/sites/neso.energy/files/styles/tile_large/public/2024-07/Dad%20and%20his%20children%20looking%20out%20the%20sea%20with%20his%20little%20girl%20on%20his%20shoulders-GettyImages-682140958.jpg?h=e5aec6c8&itok=9MJ51tLT)](https://www.neso.energy/industry-information/connections/customer-connection-events) Click here to view and book events. ## Footer * [About NESO](/about-neso) + [Who we are](/about/our-people) + [Operational information](/about/operational-information) + [Careers](/careers) + [Applications, portals and APIs](/applications-portals-and-apis) * [Contact us](/contact-us) + [How to report a power cut](/energy-outages) + [Help centre](https://portal.nationalenergyso.com/nesoHelpCentre/s/) + [Media centre](/news-and-events/media-centre) * [Corporate information](/corporate-information) + [Suppliers](/suppliers) + [Freedom of Information and Environmental Information Regulations](/corporate-information/freedom-information-and-environmental-information-regulations) + [Modern Slavery Statement](/corporate-information/modern-slavery-statement) + [Public Sector Equality Duty (PSED)](/corporate-information/public-sector-equality-duty-psed) ## Site * [Accessibility](/accessibility) * [Privacy notice](/privacy-notice) * [Cookie policy](/cookie-policy) * [Terms and Conditions](/terms-and-conditions) * [Security](/security) * [Responsible Disclosure](/responsible-disclosure) ## Social * [Twitter](https://x.com/NESO_energy) * [LinkedIn](https://www.linkedin.com/company/neso-energy) * [YouTube](https://www.youtube.com/%40NESO_energy) ![](/themes/custom/neso_theme/icons/logo-secondary.svg) logo--facebook