CMP465: Construction Progression Milestones (M5-M8) Neutrality | National Energy System Operator

NESO·regulation·medium·16 Jan 2026·source document

Summary

CMP465 proposes to allow affected generators to reset their construction progression milestones (M5-M8) back to what they would have been without the G2tWQ (Gate 2 to the West Queue) extension granted until 2026. The modification follows NESO's decision to extend G2tWQ connection offers beyond their original 2025 deadline. It proceeds under urgent modification procedures with Authority decision pending.

Why it matters

This creates a limited remedy for generators disadvantaged by queue management decisions, allowing them to recover lost milestone positions but only for specific construction stages. The modification addresses administrative queue changes rather than fundamental connection reform, as such it maintains the queue-based allocation system while trying to preserve pre-disruption positions.

Key facts

  • G2tWQ connection offers extended from end-2025 to 2026
  • Only affects construction milestones M5-M8, not earlier stages
  • Classified as urgent modification requiring Authority decision
  • Low impact designation for affected parties

Areas affected

grid connectionsgenerators

Related programmes

Connections Reform
Memo

CMP465: Construction Progression Milestones (M5-M8) Neutrality | National Energy System Operator Show/Hide Menu Toggle Add to favourites Close tooltip Sign in to add this page to your favourites Sign in or register Show favourites Close Close tooltip Sign in or register to manage your favourites Sign in or register Help You are now signed in Visit My NESO account to view and manage your dataset subscriptions. Maybe later Go to your account CMP465: Construction Progression Milestones (M5-M8) Neutrality This modification aims to deal with the extension given on the G2tWQ Connections offers until 2026 (from the end of 2025) and give affected Users the option to be placed back to the position they would have been (in terms of M5-M8 milestones only) had this extension not occurred. Modification status: Current - Awaiting Panel Next Steps Last updated: 21 January 2026 Code Administrator Contact: [email protected] Governance Route: Urgent modification to proceed under a timetable agreed by the Authority (with an Authority decision) Impacts: Low impact ​ on Generators and Demand Code modification proposed by: Garth Graham [email protected] Documents Proposal Documents Terms of Reference Workgroup Meetings and Summary Documents Workgroup Consultation Workgroup Report Code Administration Consultation Draft / Final Modification Report Decision Urgency Name CMP465 Proposal Form Annex 1 - CMP465 Legal Text Name CMP465 Urgency Decision CMP465 Urgency Request Letter logo--facebook