NESOOFGEMDESNZ
feed

NESO Updated QM Guidance DEC 2025

NESO·guidance·high·6 Mar 2026·source document

Summary

NESO updates queue management guidance with new milestone calculation methods and evidence requirements for transmission connections. The guidance incorporates recent code changes CMP434 and CMP435 that implement connections reform, establishing eight mandatory milestones that developers must meet or face termination. Projects must now demonstrate progression through planning, land rights, construction planning, financial commitment, and construction initiation phases with specific evidence requirements and timelines calculated backwards from completion dates.

Why it matters

This formalises NESO's termination powers over non-progressing projects, creating real consequences for speculative applications that have inflated the transmission queue. The milestone structure forces developers to commit capital and secure permits on fixed timelines rather than warehousing connection rights indefinitely. However, the extensive exceptions process and discretionary termination rights for later milestones may limit effectiveness — NESO retains administrative discretion precisely where automatic enforcement would clear the queue most efficiently.

Key facts

  • Eight mandatory milestones from planning application to construction initiation
  • Automatic termination for failing conditional milestones M1-M3
  • Discretionary termination for construction milestones M5-M8
  • 60-day rectification period after milestone default notice
  • 10 business days for NESO evidence assessment
  • Original Red Line Boundary compliance requires 50% of capacity within designated area
  • Planning regime thresholds: Section 36 over 50MW onshore, DCO over 50MW/100MW offshore
  • G2tWQ Exception allows extensions for CMP435 delays calculated from 31 December 2025

Areas affected

grid connectionstransmissionrenewablesgeneratorsplanning

Related programmes

Connections ReformCfDCapacity Market

Memo

## What this is about

NESO has updated its queue management guidance to reflect recent code changes CMP434 and CMP435 implementing connections reform. The guidance establishes a mandatory eight-milestone framework that transmission-connected projects must meet or face termination. This formalises NESO's ability to terminate construction agreements for projects that fail to progress, addressing the chronic problem of speculative applications inflating the transmission connection queue.

The updated guidance creates real consequences for developers who secure connection rights but fail to advance their projects. For the first time, NESO can automatically terminate projects that miss early milestones around planning and land rights, while gaining discretionary termination powers for later construction phases. This represents a fundamental shift from the previous system where connection rights could be warehoused indefinitely with minimal progression requirements.

## Key points

Milestone Structure: Projects face eight mandatory milestones divided into two categories: - Conditional Progression Milestones (M1-M3): Automatic termination for non-compliance - M1: Initiated planning applications (technology-dependent: 2-5 years from Gate 2 offer) - M2: Secured planning consents (calculated backwards from completion date) - M3: Secured land rights (ongoing compliance required) - Construction Progression Milestones (M5-M8): NESO discretionary termination rights - M5: Contestable design works submission - M6: Agreed construction plan with transmission licensee - M7: Project commitment (FID, binding contracts, or capital contributions) - M8: Construction initiation

Calculation Method: Milestone dates are calculated backwards from the contracted completion date using lookup tables based on project lead times. M1 uses forward calculation from Gate 2 offer date based on planning regime type (2 years for Town & Country Planning, 3 years for Section 36/DCO, 5 years for offshore projects).

Evidence Requirements: Each milestone requires specific documentation uploaded to the Connections Portal. NESO performs independent verification including checks against planning portals and statutory authority records. Users receive 60 and 30-day advance notices before milestone dates, with 10 business days for NESO to assess submitted evidence.

Land Rights Compliance: M3 introduces ongoing compliance measured against the Original Red Line Boundary from Gate 2 applications. Only 50% of installed capacity can be located outside this boundary, with potential for relaxation where justified by planning authority directions or environmental constraints.

Exceptions Process: Users can apply for milestone extensions for exceptional issues outside their control, with different processes for delays under/over 6 months. A specific "G2tWQ Exception" applies to CMP435 users who can demonstrate delays from the Gate 2 to Whole Queue process impacted their progression.

Termination Process: Non-compliance triggers a 60-day Default Milestone Remedy Period. For M1-M3, automatic termination follows if evidence isn't provided. For M5-M8, NESO exercises discretion after internal escalation and stakeholder engagement, considering likelihood of meeting completion dates.

## What happens next

The guidance takes immediate effect for all Gate 2 agreements, though Gate 1 contracts include milestone provisions that only activate upon Gate 2 upgrade. Projects currently in the connections queue under CMP435 must comply with these milestone requirements as they receive Gate 2 modification offers.

Users approaching milestone dates should begin evidence preparation immediately, particularly for M1 planning applications given the verification requirements against statutory planning portals. Early engagement with NESO connections managers is essential for projects at risk of missing milestones.

The exceptions process for CMP435 users affected by Gate 2 to Whole Queue delays requires applications within 28 days of signing Gate 2 modification offers. Users should document any project delays attributable to the extended CMP435 implementation timeline.

NESO will publish anonymised examples of insufficient evidence submissions to help developers understand compliance requirements. The first wave of terminations under these provisions is likely within 12-18 months as projects approach their calculated milestone dates.

The effectiveness of queue management will depend heavily on NESO's enforcement approach for Construction Progression Milestones M5-M8, where discretionary termination rights may be exercised conservatively. Industry will watch closely whether NESO applies these powers rigorously enough to achieve meaningful queue reduction or whether extensive administrative discretion undermines the policy's objectives.

Source text7,404 words

OFFICIAL Queue Management Guidance OFFICIAL OFFICIAL Contents Introduction ............................................................................................................................................................................... 4 1. 2. Overview of the Transmission Queue Management process ................................................................. 4 General objectives and application ................................................................................................ 4 Queue Management Milestones ........................................................................................................ 5 Milestone calculation method ............................................................................................................. 6 Queue Management Milestones and Modification Applications ............................... 7 3. Population of User Construction Agreement Appendix Q and interaction with Appendix J 2.1. 2.2. 2.3. 2.4. 8 4. Evidence Requirements, Submission and Checks ....................................................................................... 8 4.1. Overview of evidence required from Users to demonstrate progression against milestones .......................................................................................................................................................... 8 Milestone 1 Adjustment Exception Evidence ............................................................................. 12 4.1.1. 4.1.2. M3 Ongoing Compliance relating to Original Red Line Boundary ........................... 12 Additional evidence checks performed by NESO ................................................................. 13 4.1.3. Evidence submission ................................................................................................................................. 14 4.1.4. 5. Exceptions process .......................................................................................................................................................... 17 6. Termination process ...................................................................................................................................................... 20 7. Disputes process ............................................................................................................................................................... 21 Appendix 1 –M1 specific additional exception ....................................................................................................... 22 OFFICIAL 2 OFFICIAL Version Author Date Changes 0.1 0.2 0.3 2.0 3.0 Kavita Patel September 2023 First draft Kavita Patel November 2023 First published Kavita Patel January 2024 Izzie Sunnucks June 2025 Removal of the calculator link and updated links for reference materials. Update to reflect CMP 434 and 435 and to remove outdated sections Ruth Matthew December 2025 Update of exceptions OFFICIAL 3 OFFICIAL 1. Introduction On 13 November 2023, code change CMP376: Inclusion of Queue Management process within the CUSC was introduced to manage Transmission Construction Agreements. The code changes apply across Great Britain, including . CMP 376 introduced the right for the National Energy System Operator (NESO) to terminate Construction Agreements with Users which are not progressing against User Progression Milestones via the Queue Management process. It aims to enable full use of network capacity, to support more robust network investment decisions, and to allow projects which are progressing the best chance to connect. Queue Management was then aligned with Connections Reform by CMP434: Implementing Connections Reform, and the changes also apply in respect of CMP 435 (HYPERLINK "https://www.neso.energy/industry- information/codes/cusc/modifications/cmp435-application-gate-2-criteria-existing- contracted-background"Application of Gate 2 Criteria background). This updated guidance reflects the current arrangements. to existing contracted There are similar, but separate, arrangements already in place for Distribution Connections (link to the ENA guidance can be found here). 2. Overview of the Transmission Queue Management process 2.1. General objectives and application The key components of the Transmission Queue Management process are: • A set of eight prescribed User Progression Milestones to be added into Users’ Construction Agreements by the addition of an Appendix Q; • Associated timescales by which each of the eight User Progression Milestones must be met by the connecting User; • The acceptable forms of evidence that Users must provide to NESO to confirm User compliance with their eight User Progression Milestones, and associated checks that will be carried out; • Requirements for ongoing compliance, including evidence and process; and • Outcomes for resolving non-compliance, including an Exceptions process and powers for NESO to terminate Agreements where one (or more) of the User Progression Milestones has not been met. Detailed provisions are set out in CUSC Section 16. Each User’s Construction Agreement Appendix Q sets out project-specific User Progression Milestone dates. The Transmission Queue Management process in CUSC does not apply to parties embedded in a distribution system as they are subject to the (separate) Distribution Queue Management process through their arrangements with the DNO. This Transmission Queue Management process only applies to projects connected to the National Electricity Transmission System. This includes Offshore wind farm projects and other Offshore projects, but not any Offshore Transmission, including where being built by that wind farm (i.e. the ‘OTSDUW’) which will, on transfer to an Offshore Transmission Owner (OFTO), form part of the National Electricity Transmission System. Applicants that apply for a Gate 1 Offer or do not meet the Gate 2 Criteria will receive a Gate 1 Agreement to Vary or Gate 1 Offer (depending on whether CMP434 or CMP435) and will not be required to meet User OFFICIAL 4 OFFICIAL Progression Milestone compliance1 until (if and when) they subsequently meet the Gate 2 Criteria and sign a Gate 2 Agreement. The Gate 2 Agreement will include the User Progression Milestones. 2.2. Queue Management Milestones The Queue Management Milestones can be divided into two categories based on NESO’s termination rights: NESO will terminate projects that do not meet Conditional Progression Milestones, unless there is a valid exception in place (see Section 5 below). NESO has the right to terminate projects that do not meet Construction Progression Milestones. Milestone Detail Milestone type Conditional Progression Milestone Milestone 1 Initiated Statutory Consents and Planning Permission - Milestone 2 - Secured Statutory Consents and Planning Permission Milestone 3 - Secure Land Rights Where statutory consents are needed for the construction of the User’s project, the User must start the process of obtaining these consents, including Planning Permission, within the specified timescales and must be able to provide the necessary evidence of this. Where statutory consents are required for the construction of the User’s project, the User must have secured including the specified Planning Permission, within timescales and must be able to provide the necessary evidence. these consents, The User must have secured the necessary land rights to enable project construction. This means the owner/occupier of the land or have the required agreement from the owner/occupier. the User may either be Milestone 4 - N/A This milestone does not apply for Transmission Milestone 5 - Contestable Design Works Submission This milestone will apply where a User has gone down the contestable route for connection. Construction Progression Milestones Milestone Construction Plan 6 - Agree The User must have agreed on a construction plan for the detailed User’s Works with NESO they will be which demonstrates how progressing the User’s Works to achieve the Completion Date. 7 Milestone Commitment - Project This milestone demonstrates that the project has the necessary commitment or backing for it to proceed. Milestone 8 Construction - Initiate Project construction is the phase from when a User begins the site works to carry out the 1 As per CUSC Clause 16.1 “Although provision for this process is included within Gate 1 Agreements the process and provisions within this Section will only be actively applied in Gate 2 Agreements.” OFFICIAL 5 OFFICIAL construction of its project until the completion of the User’s Works. Table 1 - Queue Management Milestone types and details 2.3. Milestone calculation method User Progression Milestones: The dates of the User Progression Milestones will be included in the Construction Agreement (Appendix Q). The dates for these will be calculated (except in the case of User Progression Milestone M1, as set out below) by working backwards from the contract Completion Date. Milestone duration time is determined from the look-up table as per CUSC Section 16. Milestone 0 – 2 years (729 days) Bilaterally Negotiated M1 – Initiated Statutory Consents and Planning Permission (see also below) M2 – Secured Statutory Consents and Planning Permission M3 – Secured Land Rights M5 – Contestable Design Works Submission M6 – Agree Construction Time M7 – Project Commitment M8 – Initiate Construction 2 -3 years (730 – 1094 days) 18 months 3 – 4 years (1095 – 1459 days) 24 months 4 – 5 years (1460 – 1824 days) 36 months 5 years (1825 days) + 48 months 12 months 18 months 24 months 30 months 21 months 27 months 39 months 51 months 12 months 15 months 18 months 21 months 9 months 12 months 15 months 18 months 6 months 9 months 12 months 15 months 3 months 6 months 12 months 15 months Table 2 – Queue Management Milestone backwards calculation Where durations are referred to as being “bilaterally negotiated”, NESO, the Relevant Transmission Licensee and the User will aim to agree the milestone durations during the Offer preparation period. If these have not been agreed, Appendix Q will reflect the durations proposed by NESO and Relevant Transmission Licensee and discussions will continue with a view to agreeing these during the Offer acceptance period. User Progression Milestone M1: Relevant Planning Regime / Technology Type Timescale from Gate 2 Modification Offer date (CMP435) or Gate 2 Offer date (CMP434) to User Progression Milestone M1 Town and Country Planning (England, Scotland and Wales) 2 years OFFICIAL 6 OFFICIAL Section 36 (England/Scotland) Development of National Significance (Wales) NSIP / DCO (England and Wales) Offshore (including Offshore Wind, Interconnectors and OHAs) Nuclear Novel technologies 3 years 3 years 3 years 5 years Case by Case Case by Case Table 3 – Queue Management Planning Regime and Technology Types Where a specific technology type is referenced in Table 3, the M1 timescale associated with that technology type will take precedence over the planning type timescale. For example, for an offshore wind farm subject to Section 36 planning, the duration will be 5 years, even though the duration for Section 36 planning is 3 years. All durations for milestones other than User Progression Milestone M1 are calculated back from the contract Completion Date. M1 Adjustment Exception Process: Unless M1 has already been met at the time of the Gate 2 Modification Offer date (CMP435) or Gate 2 Offer date (CMP434), the durations will be the earlier of: (a) the date calculated forwards from the Gate 2 Modification Offer date (CMP435) or Gate 2 Offer date (CMP434) to M1 as set out in Table 3; or (b) the date calculated back from the contract Completion Date. If the forward calculated date is the earlier of the two, the User has (under CUSC Section 16) the possibility of an adjustment exception process. This process allows the User to demonstrate with evidence that a forward calculated M1 would have a detrimental impact on the project. If the evidence is accepted by NESO, the customer will be able to propose a new M1 date no later than the backwards calculated M1. Further detail is provided below at 4.1.2. For an example of how the calculation will work in practice, please see Appendix 1. 2.4. Queue Management Milestones and Modification Applications Once Queue Management Milestones have been added to Construction Agreements, Modification Applications made by a User to realign the construction programme will not automatically change the User Progression Milestone Dates. This section lists example Modification Application scenarios and the consequences to Appendix Q. This list is non-exhaustive. Scenarios resulting in no adjustment to the contracted queue management milestone dates: • As per NESO’s Material Technology Change Guidance and Gated Modification Guidance, where an agreement includes an additional technology (or technologies) and/or Transmission Entry Capacity (TEC) which later meets the Gate 2 Criteria, will be provided with a new queue position and so will be provided with a new Appendix Q in respect of the additional technology (or technologies) and/or TEC. Therefore, the existing contracted queue management milestones for the existing technology (or technologies) and/or TEC will not be adjusted. • Where the User requests a delay to the completion date of more than one year the contracted queue management milestones will not be adjusted (unless there is an exception in place – see below). Scenarios resulting in an adjustment to the contracted queue management milestone dates: OFFICIAL 7 OFFICIAL • As per NESO’s Material Technology Change and Gated Modification Application guidance, certain changes result in a new queue position being allocated and this will result in a new completion date being issued for some or all of the project. Consequently, new queue management milestone dates will be set for the project or relevant project stage(s) (as the associated new completion date(s) will be based on a later queue position). • Where a valid exception allows queue milestone adjustment, as per Section 5 below, when assessing the exception, NESO will determine whether the completion date remains unchanged. If a new completion date is issued, the unmet milestones will be assessed to determine whether new milestone dates should be issued. • As a result of CMP 435, where the contract completion date included within the Gate 2 Modification Offer is not the same as the contracted completion date within the existing agreement, (e.g if Advancement was requested and offered) the Queue Management milestone will be adjusted to reflect that date. 3. Population of User Construction Agreement Appendix Q and interaction with Appendix J The Construction Agreement provides two appendices that specify target dates: Appendices J and Q. These are connected through the calculation method for Queue Management milestones, which are determined by working backwards from the Completion Date specified in Appendix J (except for M1, as detailed above). • Appendix J outlines the construction programme as determined by the Relevant Transmission Licensee in the Transmission Owner Construction Agreement. This programme identifies the completion date, which is crucial for calculating the Queue Management milestones. • Appendix Q provides the User Progression Milestones as calculated in Section 2.3 above. While an agreement can comprise more than one Appendix Q, it cannot have more than one Appendix J, (which can include completion dates for stages if that is how the project/transmission works are designed). Where Users have more than one technology in their Construction Agreement, there will be a separate Appendix Q for each technology (populated for the technology when it meets the gate 2 criteria) but only one Appendix J; however, Appendix J can include staged completion dates in some circumstances. Where Users have multiple stages related to an initial non-firm connection at stage 1 and enduring firm connection at stage 2, with the entire TEC available from stage 1, there will only be one Appendix Q. However, if the project is for multiple technologies, there would be separate Appendix Q for each of the technologies. Although the milestone dates in Appendix Q are calculated based on dates in Appendix J, they will not necessarily always align. Users will need to be mindful of this where they make Modification Applications to change the Construction Programme (as per Section 2 above). Under the changes introduced by Connections Reform, Gate 1 contracts will include Queue Management clauses and a blank Appendix Q (Queue Management Process – User Progression Milestones); however, the milestone dates themselves will be provided only through Gate 2 Modification Offers based on the offered completion date (and, in the case of M1, the Gate 2 Modification Offer date). 4. Evidence Requirements, Submission and Checks 4.1. Overview of evidence required from Users to demonstrate progression against milestones This section sets out the types of evidence NESO requires to verify Users meet each individual User Progression Milestone, as per CUSC Section 16. We also provide guidance on how compliance with M3 (Secure Land Rights) is measured against Users’ Original Red Line Boundary and scenarios for potential exceptions. Evidence will be uploaded by the User to the Connections Portal for NESO approval. OFFICIAL 8 OFFICIAL Milestone Evidence Requirement in Code Examples of acceptable evidence Milestone 1 - Initiated Statutory Consents and Planning Permission Submission of planning application to Planning application reference number, as the relevant Statutory Authority or, if the provided to the User once they have User’s project does not require a submitted their application and it has been statutory consent, a declaration from the validated by the relevant Statutory User to that effect. Authority. The Planning Application accepted will be for full planning permissions rather than outline planning permissions or Planning in Principle. If the User’s project does not require a statutory consent, then the User needs to provide a signed letter from the company’s Director stating that no statutory consent is required. Under the Gate 2 Application process, a User seeking readiness via the planning route may provide their planning reference number later (but before Gate 2 is issued). In these cases, NESO will accept the User providing the application for planning consent under their Gate 2 Application. Further detail on how NESO checks compliance is provided in Section 4.1.3 below. Local Authority issued Secured Statutory Consents and Planning Permission with details of the contracted project (i.e. site, technology and MW). Note: NESO will not accept Meeting minutes, Outline planning permission or Planning in Principle. Further detail on how NESO checks compliance is provided in Section 4.1.3 below. Milestone 2 - Secured Statutory Consents and Planning Permission The planning decision notice confirms planning permission has been granted and that this permission allows the User to meet the terms included in its Construction Agreement. Compliance with this milestone is ongoing. Milestone 3- Secure Land Rights The User shall provide documentation to demonstrate that: (i) the User is an owner or tenant of the land on which the The User shall provide documentation to NESO to demonstrate ongoing compliance with one of the code requirements. Note that Embedded Power Stations’ User Progression Milestones and ongoing land OFFICIAL 9 compliance requirements will continue to be managed by the DNOs and Transmission Connected iDNOs. OFFICIAL (ii) (iii) proposed site is or will be situated; or the User has entered into an agreement to lease (which meets the requirement in the Gate 2 Criteria Methodology) the land from the owner of the land on which the proposed site is or will be situated; or the User has an option to purchase or to lease the land from the owner of the land on which the proposed site is or will be situated and this option meets the requirements and parameters set out in the Gate 2 Criteria Methodology; or (iv) For an Offshore Project, which depending on the type of Offshore Projects (and set out in the LoA Guidance) the land rights are provided by reference to the seabed or Onshore Connection Site (a) the User has entered into an agreement for occupation or use of the seabed upon which the User's project (excluding any OTSDUW) is or will be located or (b) the requirements at (ii) and (iii) above apply. Nb the obligation is to secure and evidence the land right for the site of the installation e.g. Power Station or demand site so the evidence does not relate to rights e.g. easements associated with that site or OTSDUW. Compliance with this milestone is ongoing and additionally measured against the requirements regarding the Original Red Line Boundary as set out in CUSC Paragraph 16.4.9.3. Milestone 4 - N/A for Transmission Milestone 5 - Contestable Design Works Submission This milestone will apply where a User has gone This milestone does not apply for Transmission Queue Management. Written confirmation from the Relevant Transmission Licensee that design obligations as bilaterally agreed in a User-Self Build agreement have been received. Email/Letter confirmation from the Relevant Transmission Licensee (RTL) to the User to state the design obligations are bilaterally agreed (between the RTL and the User). Note: If a User were to submit a Modification Application (to the NESO) to take on contestable works, this User OFFICIAL 10 OFFICIAL Progression Milestone will be included in their revised appendices provided with the Agreement to Vary. Email/Letter confirmation from Relevant Transmission Licensee to the User setting out that the Users Construction Programme has been agreed. The User’s construction plan shall demonstrate how the User will be ready for the Commissioning Programme Commencement Date. This must include a detailed programme for the User’s Works with a fixed start and end date as agreed with the Relevant Transmission Licensee, and be a programme aligned with the Commissioning Programme Commencement Date and Completion Date. One of the following: One of the following: down the contestable route for connection. Milestone 6 - Agree Construction Plan Milestone 7 - Project Commitment • Binding contract issued by the User for main plant equipment; or • Capital contribution payments made to NESO in advance of connection; or • A decision paper from a formal, minuted meeting of the User’s board of directors evidencing Final Investment Decision (FID); or • Award of a governmental or regulatory subsidy which provides financial support or incentive to the User’s project. • A copy of a Binding contract, Civil/electrical or Balance of Plant contracts to show it relates to the specific project; or • A document to show award of a governmental or regulatory subsidy has been achieved for the specific project; or • Capital contribution - Not all projects require these and thus this option to evidence M7 will not be open to all Users. In any case, where it does apply, the understanding is that the User would have to have paid for the full value of all connection assets, pre-connection, and in practice this would mean by the time of milestone 7. This could be in lump sum or instalment, dictated by the Relevant Transmission Licensee; or • A signed paper from the User’s Board of Directors evidencing a Final Investment Decision. Evidence for meeting this milestone will be a letter from the User’s Board of Directors or equivalent to state construction has commenced. Additional evidence which can be provided alongside this letter are detailed below: Examples – Photos of the construction works underway at the site, invoice for Milestone 8 - Initiate Construction Commence construction according to the construction plan agreed under Milestone 6. OFFICIAL 11 OFFICIAL Table 4 – Queue Management Evidence Requirement and Examples contractors for the construction works underway at the site. As per CUSC 16.4.9.3.1, the User is required to confirm at each User Progression Milestone that their project meets the minimum acreage requirements as set out in NESO’s LoA Guidance i.e. that the land is equal to or greater than that provided for the technologies included in the ‘Gate 2 Application’. Confirmation that the minimum acreage requirement continues to be met must be included when submitting evidence for each User Progression Milestone. 4.1.1. Milestone 1 Adjustment Exception Evidence If NESO identifies that the M1 forward-looking date is earlier than the backward-looking date while processing the offer, the offer will be issued with the forward-looking date as M1. It is acknowledged that planning consents are not indefinite. A misaligned timeframe may expose the User to the risk and expenses of facing opposition prematurely, particularly when plans or background circumstances may change. In this case, the User can request for the date to be adjusted to avoid unintended detrimental effects caused by an earlier application for planning. The same mechanism is found in Section 2.3 above and is covered in more detail in Appendix 1. The adjustment depends on NESO being satisfied with the evidence provided by the User, showing how an earlier date would be detrimental to the project; however, please note that any exception under this route only permits the forward-facing milestone to be adjusted to no later than a backwards-facing M1 calculation (unless other exceptions were to apply under CUSC Section 16). 4.1.2. M3 Ongoing Compliance relating to Original Red Line Boundary The Original Red Line Boundary is provided in accordance with CUSC and the Gate 2 Criteria Methodology. As per CUSC 16.4.9.3.3, only 50% of any Installed Capacity built within the Original Red Line Boundary can be located outside of the Original Red Line Boundary. Where this Original Red Line Boundary MW calculation results in a number that is less than the total Installed Capacity, the total Installed Capacity will be reduced accordingly. This may result in a TEC and demand reduction and liability to pay cancellation charges. This requirement is set out further in CUSC, including Schedule 2 Exhibit 3 Clause 7.5 (Onshore) and CUSC Schedule 2 Exhibit 3A Clause 7.4 (Offshore) for directly connected projects. CUSC 16.4.9.3.4 allows a relaxation from the 50% requirement where justified and evidenced by the User in accordance with this guidance. It is at NESO’s discretion whether to allow relaxation of the 50% requirement. Users will need to follow the Exceptions Process set out in this guidance if they wish to seek a relaxation from the 50% compliance requirement. There are several areas that could be considered potentially acceptable exceptions to the 50% Original Red Line Boundary compliance requirement, provided NESO is satisfied with the evidence. These include: • Planning surveys that identify archaeological or environmental risks in specific locations within the Original Red Line Boundary that require avoidance, such as noise or protected species; or • Directions from the relevant Planning Authority to move all or part of the Project Site from within the Original Red Line Boundary; or • Using land within the existing Original Red Line Boundary for community amenity, ecological, and biodiversity enhancements, which may require more capacity to be located outside the Original Red Line Boundary as a result of such enhancements. If a User wants to explore relaxations for Original Red Line Boundary compliance, we recommend contacting NESO as soon as possible to discuss whether such a relaxation may be granted at NESO’s reasonable discretion, including in relation to the above. OFFICIAL 12 OFFICIAL If the User is following the Planning route2 to meet the Gate 2 Readiness Criteria, the ongoing Original Red Line Boundary compliance requirements will apply once the User has met Queue Management Milestone 2 and then provided the necessary Original Red Line Boundary and Installed Capacity information in accordance with the Gate 2 Criteria Methodology. Please note that Users seeking to meet the Gate 2 Readiness Criteria through the Planning route, who have met Queue Management Milestone M2 at the time of submitting the Readiness Declaration (or where they meet it prior to signature of the Gate 2 Modification Offer), only need to provide the Original Red Line Boundary, Installed Capacity and evidence of minimum acreage requirements upon their signature of the Gate 2 Modification Offer. 4.1.3. Additional evidence checks performed by NESO Milestone 1 Evidence Check NESO will confirm against the Planning Portal (if the site is located in England and Wales) or Scottish Government - Energy Consents Unit - Application Search (if the site is located in Scotland) or alternatively it will confirm with relevant Statutory Authority. Checks will ensure that the application for planning consent is valid and that the site location, technology and capacity are in line with the data submitted to and/ or held by NESO. Where the User has provided the application for planning consent with their Gate 2 Application, NESO will perform the same verification checks on that document as are done where the planning reference number is required. Milestone 2 Evidence Check NESO will validate consents have been secured on the Local Authority website. Checks will ensure that the that the site location, technology and capacity are in line with data submitted to and / or held by NESO. For both Milestones 1 and 2 the capacities checked against the planning portals will adhere to the following rules: • Where the MW capacity is available in the planning documents, the MW will be higher or equal to the contracted TEC; if a range is provided in the planning documents, the upper limit will be used • Where the MW capacity is indicative in the planning documents, the MW will be higher or equal to the contracted TEC, and equal to or lower than the upper MW limit of the relevant planning regime (where applicable) • Where the MW capacity is not available, the MW will be higher than or equal to the TEC, and equal to or lower than the upper MW limit of the relevant planning regime (where applicable). The table below provides the current upper MW limit of various planning regimes to support customer submissions. Planning Regime England Wales Scotland Section 36 Offshore only: 1MW – 100MW + Marine Licence Offshore only: up to 350MW + Marine Licence Onshore: over 50MW Offshore: over 1MW + Marine Licence 2 For information on the ‘Land’ or ‘Planning’ route, please see NESO’s Gate 2 Criteria Methodology OFFICIAL 13 OFFICIAL Town and Country Planning Onshore: under 50MW3 Onshore: under 10MW Onshore: under 50MW Offshore: under 1MW + Marine Licence Offshore: under 1MW + Marine Licence Development of National Significance n/a 10 to 350MW n/a Development Consent Order - used for NSIPs4 Onshore: over 50 MW5 Offshore: over 100MW Onshore and Offshore: Over 350MW n/a Scottish equivalent of a NSIP is Section 36 consent for all over 50MW projects Table 5 – Queue Management Planning Regime and Capacities 4.1.4. Evidence submission NESO will notify the User 60 days before each User Progression Milestone is due if the milestone has not been met6. NESO will also send a reminder 30 calendar days before the milestone is due if it still has not been met. These notifications will be issued via the customer portal. NESO and the User should actively engage during project progression meetings to identify and address any risks where the User feels a User Progression Milestone date may not be met. For each User Progression Milestone, the User must submit the required evidence on or before the milestone due date. NESO will assess the evidence provided and inform the User in writing within 10 business days via the Connections Portal whether or not the evidence submitted is sufficient. If NESO finds the evidence insufficient, it will provide an explanation. If the evidence for the User Progression Milestone has not been provided to NESO by the User Progression Milestone due date, or if submitted by the due date the evidence is not accepted by NESO as sufficient, the Termination Process will be followed unless one of the exceptional issues (as set out in CUSC Section 16 – and above) is met. It is the responsibility of the User to identify, apply for and provide evidence for any exceptions. Example 1 for submission of Milestone 1, Conditional Progression Milestones – Automatic NESO Termination Users are encouraged to submit evidence ahead of the 60- and 30-calendar day reminders being sent. 3 This threshold does not apply to energy storage projects, which are exempt from the NSIP regime (excluding pumped hydro) and are determined under the Town and Country Planning route, regardless of their size 4 https://www.gov.uk/government/consultations/proposed-reforms-to-the-national-planning-policy-framework- and-other-changes-to-the-planning-system/outcome/government-response-to-the-proposed-reforms-to-the- national-planning-policy-framework-and-other-changes-to-the-planning-system-consultation - see responses to questions 76 and 77 5 This will be changed to 100MW for wind and solar later in 2025 when the Infrastructure Planning (Onshore Wind and Solar Generation) Order 2025 comes into force. Other technologies remain unchanged at 50MW and energy storage (excluding pumped hydro) is excluded from the NSIP regime 6 Noting 60 days’ notice will not be issued where a milestone is part of Readiness Declaration submission OFFICIAL 14 OFFICIAL Example 2 for submission of Milestone 5, Contestable Design Works Submission – NESO right to terminate. Users are encouraged to submit evidence ahead of the 60- and 30- calendar day reminders being sent. OFFICIAL 15 OFFICIAL Example 3 for submission of evidence for staged connections. In this example the User has a Battery connecting in 2033 and a Solar project connecting in 2035. Although the completion dates are different for each technology, the same process will be followed for each milestone. In this example we follow the progress of the Battery connection. Users are encouraged to submit evidence ahead of the 60- and 30-calandar day reminders being sent. OFFICIAL 16 OFFICIAL 5. Exceptions process There may be a small number of exceptional issues (set out in CUSC 16.5) outside a User’s’ control, which may lead to legitimate project delays and therefore directly impact on compliance with the User Progression Milestone date(s). The following process applies to the exceptions set out in CUSC 16.5: Users are encouraged to apply for an extension on the basis of an exception as soon as they are aware of any risk associated that will cause a delay. In such instances, the User must apply to NESO for an extension of the User Progression Milestone date(s) via the customer portal and specify the below: OFFICIAL 17 OFFICIAL • The reason(s) for missing the User Progression Milestone and milestone for which the extension is requested. • How long is the expected delay, with the User to provide a realistic time frame of when the milestone can be achieved. • Less than 6 months – if accepted, NESO will update the requested User Progression Milestone date and inform the Relevant Transmission Licensee of this change (see process maps above); or • More than 6 months – if accepted, NESO will work with the Relevant Transmission Licensee to agree on an allowable modification application which will contain a new Appendix Q Milestones where applicable. The Modification Application must be submitted within 1 month of the exception being accepted (see process maps above). • Whether this delay creates a knock-on impact on the User’s ability to meet future User Progression Milestones. If so which one(s), the reason for and, and whether it will impact on the User’s project Completion Date. Note, a separate exception will need to be applied for each individual User Progression Milestone, but conversations need to continue with NESO Connections Contract Managers during the progression of the project. • • If NESO accepts that there is an exceptional issue with a User Progression Milestone, and it impacts the Completion Date and requires re-study, this will be managed through the normal CUSC Modification Application process to update the Construction Programme (Appendix J) In this specific circumstance, the User Progression Milestone(s) date (Appendix Q) will be adjusted accordingly. If NESO accepts that there is an exceptional issue with a User Progression Milestone, then the User Progression Milestone(s) date (in Appendix Q) will be updated to reflect the new User Progression Milestone date(s) for the missed Milestone(s). NESO will engage with Users continuously to understand their overall project progress, including in relation to participation in the UK Government funding rounds like Contracts for Difference or the Capacity Market. This ongoing engagement helps NESO make informed and reasonable decisions regarding the application of discretion on the termination of any Users, where NESO’s discretion is engaged. We recommend that Users also engage with NESO proactively. Users at risk of missing any User Progression Milestones should keep NESO regularly informed of this risk in advance of any milestone being missed. This helps NESO make informed decisions regarding possible terminations. NESO will coordinate with the User and, if necessary, the Relevant Transmission Licencee. NESO will have 10 working days to notify the User whether the exceptional issue for a User Progression Milestone is agreed upon after submission. If NESO does not agree that there is an exceptional issue for a User Progression Milestone and the required evidence has not been provided, the Termination process will begin. Termination will only be exercised after completing an internal escalation process within NESO. For Users seeking Gate 2 Readiness through the planning route within the Gate 2 Criteria Methodology, if their M3 milestone is calculated to be in the past (without them having met the milestone), or the near future (to the extent that it cannot realistically be met), when they are provided with their Gate 2 Modification Offer, NESO will not then send the Milestone Default Notice (for a reasonable and appropriate period determined by NESO following discussion with the User). This is so that the 60-day rectification period does not start and so that the User contract does not get terminated for missing the Conditional Progression Milestone M3. This is an interim solution to ensure that the small number of Users who may be in this situation are able to use the planning route to readiness without risk of termination in such circumstances. We will continue to consider the extent to which this interim solution could become the enduring solution or whether a code change is required in future to recognise circumstances where M3 may legitimately follow M1 and/or M2 in sequence. OFFICIAL 18 OFFICIAL In line with the general principle that exceptions apply for events outside of a User’s control, we have included an additional exception reason for Users receiving initial Gate 2 Modification Offers issued as part CMP 435 only (“G2tWQ Exception”). This will apply where Users, that have received a Gate 2 Modification Offer, can evidence that the delay period7, as described below, has negatively impacted on the User’s ability to meet any of the User Progression Milestones M5 – M8 in Appendix Q in its Gate 2 Modification Agreement. To apply for the G2tWQ Exception, a User must first accept the Gate 2 Modification Offer and then apply within 28 calendar days from signature of the Gate 2 Modification Offer and submit evidence that their project’s ability to meet any of the User Progression Milestones M5 – M8 has been impacted due to the delay in issuing CMP 435 offers. The delay period would be considered to be calculated from 31st December 2025 through to the date the User receives their Gate 2 Modification Offer. Where a User can evidence (for example) paused progression of their project, delay due to the Gate 2 to Whole Queue Process an extension to some or all of M5 – M8 User’s Progression Milestones may be sought from this date – even if this date is prior to 31 December 2025. The User Progression Milestones will be extended by a period proportionate to the delay the User has experienced, for example a 30-day delay would result in a 30-day extension. NESO will co-ordinate with the User and adopt a pragmatic approach to the nature and assessment of the evidence provided by the User to demonstrate the delay was as a consequence of the delay in issuing CMP 435 offers (an example could be, confirmation of a pause in works), for a reason out of their control. Provided this is suitably evidenced, the extension will be granted. In relation to evidence assessment, matters will be considered on the facts and on a case-by-case basis. This additional extension of the exceptions will ensure User Progression Milestones remain appropriate to the circumstances. Potential applicants should note that even if an exception is not applied for, the right to terminate would be carefully considered and applied pragmatically taking account of the specific circumstances of that project and the CMP 435 process should a milestone not be met. Example for submission of exception and the appeals process following a delay caused by Third-party. 7 Original timelines were revised in October 2025 (Connections reform timeline | National Energy System Operator) OFFICIAL 19 OFFICIAL 6. Termination process A User’s Construction Agreement will be classified as “Termination” where: • The required evidence for the User Progression Milestone has not been provided to NESO by the User Progression Milestone due date; or • the evidence provided is considered by NESO to be insufficient8; or • NESO has not agreed there is an exceptional issue with a User Progression Milestone (see section above) NESO will start the Termination Process by issuing a “Default Milestone Remedy Period Notice” to the User. This notice informs the User that the project is classified as “Termination” and provides 60 calendar days to rectify the missed User Progression Milestone evidence. If the User Progression Milestone is not achieved by the end of Default Milestone Remedy Period, the following applies based on the progression of the project. • For User Progression Milestones 1 to 3 inclusive (the Conditional Progression Milestones), NESO will issue a notice to the User terminating the Construction Agreement. 8 To enable other stakeholders to better understand what evidence is considered by NESO to be insufficient (and thus share the ‘lessons learnt’) NESO will provide an anonymised copy of the insufficient evidence that they have ‘rejected’ on their website in a timely manner. OFFICIAL 20 OFFICIAL • For User Progression Milestones 5 to 8 (Construction Progression Milestones), NESO will consider whether it is appropriate to exercise its right to terminate. This decision will be made after internal escalation within NESO and engagement with the User and the Relevant Transmission Licencee to assess the likelihood of progression to the contracted Completion Date. Where a decision to terminate has been reached, NESO will notify the User of its decision and reasoning. Where a decision has been made to not terminate, the project will be categorised as terminated and kept under review until the milestone date is met. Once the milestone date is met, the status will change to ‘on track’. The User will be informed of this categorisation in a timely manner. 7. Disputes process Under CUSC, any dispute in the application of the Queue Management Process will be treated as an Other Dispute under the CUSC disputes process at CUSC Section 7 According to this process, initial discussions between NESO and the User will take place to seek a resolution before raising a dispute. If necessary, either party may then refer the dispute to the London Court of International Arbitration. OFFICIAL 21 OFFICIAL Appendix 1 –M1 specific additional exception An additional adjustment exception has been included in CUSC Section 16 for M1 to mitigate the risk of a User having to submit their application for planning too early in their development cycle. This is: Where a User can demonstrate that a forward looking M1 would have a detrimental impact on developing the User’s project provided that any adjustment cannot be later than the backwards looking M1. Below is an example of how the adjustment exception works for M1. The following Queue Management Milestone Dates have been identified for an offer: • Completion Date of 1st January 2035 • Issued on 1st December 2025 • Subject to consents under Section 36 Milestones Backwards Calculated Forwards Calculated (Section 36 planning, 3 years) M1 M2 M3 M4 M5 M6 M7 M8 01 January 2031 01 December 2028 Not calculated forwards i.e. calculated backwards from Completion Date 01 July 2032 01 October 2030 N/A 01 April 2030 01 July 2033 01 October 2033 01 January 2034 The customer receives an offer with M1 as 1st December 2028, satisfying the criteria set in CUSC Section 16. The Offer Letter will set out the criteria for M1 as the earlier of the backwards or forwards calculated dates and will give the customer (as the forwards calculated date for M1 has been offered in this example): 1. The option to demonstrate, with evidence during the post offer negotiation period, that the earlier date negatively impacts the project; and 2. The ability to propose an alternative M1 milestone date of no later than 1st January 2031 (being the backwards calculated date). If during the post offer negotiations period the customer does not apply for an adjustment and so accepts the offer, the earlier date provided for M1 will become the enduring M1 date, unless the customer applies for an exception through the standard process. As this adjustment exception only applies to M1 the process is as follows: • While processing the offer NESO identifies that the forwards-calculated M1 is earlier than the backwards- calculated M1 date. The Offer Letter will contain extra paragraphs to explain the reason and advise the customer on next steps, while also providing the backwards calculated M1 for information. • Once the offer is issued, the customer can submit evidence of any detrimental effect the forward date would have on the project, and its proposed alternative M1 date. The proposed alternative date cannot be OFFICIAL 22 OFFICIAL later than the backwards calculated M1. The customer will be able to submit evidence up to the last 15 working days of the offer acceptance period. • NESO will evaluate the evidence submitted will decide whether the M1 date should be adjusted and will inform the customer. NESO will have 10 working days to evaluate the evidence and make a decision. • • If NESO determines that the M1 date should be adjusted, Appendix Q will be reissued with a new M1. If NESO determines that the M1 date should not be adjusted, the customer will be informed that the offer will not be amended. • Regardless of NESO’s decision whether to amend the M1 date, the acceptance period is not impacted. • The decision will be communicated to the customer before the last 5 working days of the acceptance period. The customer will then have the final 5 working days to decide whether to accept the offer and return the signed documents to NESO. OFFICIAL 23 OFFICIAL Acronym / key term Meaning ATV BEGA BSC CCM CMP CUSC DG DNO EBGL EBR ENA NETS STC RTL SQSS T&Cs TEC TO NESO Agreement to Vary Bilateral Embedded Generator Agreement Balancing and Settlement Code Connections Contract Manager CUSC Modification Proposal Connection and Use of System Code Distributed Generator Distribution Network Operator Electricity Balancing Guideline Electricity Balancing Regulation Energy Networks Association National Electricity Transmission System System Operator Transmission Owner Code Relevant Transmission Licensee Security and Quality of Supply Standards Terms and Conditions Transmission Entry Capacity Transmission Owner National Energy System Operator OFFICIAL 24