What is being proposed

The process regarding ‘Fast Track’ connections has been revised by the DNOs and originated from stakeholders needs to be able to connect distributed energy resources in domestic scale installations. The limit for fast track connections is proposed to be raised from its current maximum registered capacity of 3.68kW (16 A) per phase, to 7.36 kW (32 A) per phase, provided certain conditions are met.DCRP/21/08/PC - Consultation PackDCRP/21/08/PC - RTADCRP/21/08/PC - Decision Letter

Details

Analysis

Distribution Code code modification. See the codes page for full details.