NESOOFGEMDESNZ

Offshore Transmission Owner (OFTO) Tender Regulations

Networks and charging·Instrument·2 min read

Page type: primary-anchored (mirrors Electricity (Competitive Tenders for Offshore Transmission Licences) Regulations 2015, SI 2015/1555)

Offshore Transmission Owner (OFTO) Tender Regulations

The OFTO tender regime creates the competitive framework for awarding licences to own and operate offshore electricity transmission assets. Offshore wind developers must connect to the onshore grid via transmission assets. This SI governs the competition to select who owns and operates those assets for a 25-year revenue period.

Source file: sources/legislation/uk/si-2015-1555-ofto-tenders.md


Two models

Generator build (the dominant model): the offshore wind developer builds the transmission assets during construction, then transfers them to the winning OFTO bidder after commissioning. Ofgem calculates the economic and efficient cost of the assets (Reg. 4), and bidders compete on the annual revenue they need to own and maintain them.

OFTO build: a third-party OFTO designs, finances, and builds the transmission assets from scratch. Ofgem estimates preliminary works and construction costs (Reg. 6). This model has been used rarely.


Five-stage tender process (Reg. 13)

  1. Pre-qualification (Regs. 14-15): Ofgem publishes documentation, bidders submit questionnaires, Ofgem determines qualifying bidders
  2. Qualification to tender (Regs. 16-17): qualifying bidders sign confidentiality agreements, receive project data, further evaluation
  3. Invitation to tender (Regs. 18-19): formal bids submitted (each constituting a licence application), Ofgem selects preferred bidder or proceeds to stage 4
  4. Best and final offer (Reg. 20): selected bidders refine offers
  5. Preferred bidder (Regs. 21-22): resolution of outstanding matters, developer supports asset transfer, Ofgem grants licence (Reg. 28)

Cost structure

Developers and bidders bear Ofgem's costs, not GB bill-payers directly (Regs. 5, 7, 10, 30). Developers must provide security approved by Ofgem (Reg. 10). If a bidder is disqualified, all payments and security are forfeited (Reg. 27).


Key provisions

  • Exclusive route (Reg. 35): normal licence application procedures under EA 1989 ss.6A-6B are disapplied. The tender framework is the only route to an offshore transmission licence.
  • Developer cooperation (Reg. 22): the developer must use reasonable endeavours to support the preferred bidder's resolution of matters and asset transfer.
  • Information to bidders (Reg. 29): Ofgem must provide evaluation criteria, reasons, and results within 10 working days.

Cross-references

Related instrument Connection
Electricity Act 1989, ss.6C, 6D Enabling powers for competitive tenders
EA 1989, Schedule 2A Transmission asset definition
Transmission Licence The licence type awarded to the winning OFTO
SI 2013/175 (2013 Regulations) Revoked predecessor
Energy Act 2023 Created co-ordination licence (s.6(1)(da)), added to definitions Oct 2024

Character positions

No character positions recorded yet.


Last updated: 2026-04-05