NESOOFGEMDESNZ

Grid Code -- Connection Conditions (CC)

Industry code·Instrument·4 min read

Page type: primary-anchored (mirrors Grid Code Connection Conditions, CC)

Grid Code -- Connection Conditions (CC)

The Connection Conditions are the section of the Grid Code that specifies the minimum technical, design and operational criteria that must be met by every User connected to or seeking connection with the National Electricity Transmission System. CC.6 is the heart of the section: it sets the performance standards that generators must meet and the system characteristics that NESO must maintain.

Source file: grid-code.md Parent page: Grid Code

Scope (CC.3)

The CC applies to NESO and to: - Generators (except those with only Embedded Small Power Stations) - Network Operators - Non-Embedded Customers - DC Converter Station owners - BM Participants and Externally Interconnected System Operators (for CC.6.5 Operational Metering only)

CC.6.1 -- System performance characteristics NESO must maintain

These are the parameters NESO guarantees (subject to plant availability and User compliance):

Frequency (CC.6.1.2--CC.6.1.3)

Parameter Value Clause
Nominal frequency 50Hz CC.6.1.2
Normal operating range 49.5--50.5Hz CC.6.1.2
Extreme range (exceptional) 47--52Hz CC.6.1.3

User withstand obligations (CC.6.1.3): all Users' plant must be designed to operate across the full 47--52Hz range with the following time limits:

Frequency band Minimum operation time
51.5--52Hz 15 minutes per occurrence
51--51.5Hz 90 minutes per occurrence
49--51Hz Continuous
47.5--49Hz 90 minutes per occurrence
47--47.5Hz 20 seconds per occurrence

Frequency/speed-based relay disconnection is not permitted in the range 47.5--51.5Hz unless agreed with NESO under CC.6.3.12.

Voltage (CC.6.1.4)

Voltage level Normal operating range Notes
400kV +/-5% of nominal Max +10%, min -10%; +5% to +10% limited to 15 minutes
275kV +/-10% of nominal
132kV +/-10% of nominal
Below 132kV +/-6% of nominal

Under fault conditions, voltage may collapse transiently to zero at the point of fault.

Power quality (CC.6.1.5--CC.6.1.8)

  • Harmonics: must comply with Engineering Recommendation G5/4 (CC.6.1.5(a))
  • Phase unbalance (weekly 95th percentile): below 1.5% for E&W above 150kV; below 2% for Scotland above 150kV; below 2% for all GB at 150kV and below (CC.6.1.5(b))
  • Rapid voltage changes: limited by Table CC.6.1.7 (3 categories based on magnitude and frequency of occurrence)
  • Sub-synchronous oscillation: NESO must ensure Users' plant is not subjected to unacceptable conditions (CC.6.1.9)

CC.6.2 -- Plant and apparatus at the connection site

Protection requirements for generators (CC.6.2.2)

Requirement Specification Clause
Fault clearance time at 400kV >= 80ms (minimum) CC.6.2.2.2(a)(i)
Fault clearance time at 275kV >= 100ms CC.6.2.2.2(a)(ii)
Fault clearance time at 132kV and below >= 120ms CC.6.2.2.2(a)(iii)
Back-up protection clearance 300ms (new plant, 400/275kV, 2 main protections) CC.6.2.2.2(b)
System Fault Dependability Index >= 99% CC.6.2.2.2(d)
Loss of excitation detection Must detect and initiate unit trip CC.6.2.2.3.3
Work on protection equipment NESO representative required CC.6.2.2.4
Quality assurance BS EN ISO 9000 series CC.6.2.1.2(d)

Protection requirements for network operators / demand (CC.6.2.3)

Parallel structure to CC.6.2.2 with identical fault clearance time thresholds. Back-up protection obligations also apply.

CC.6.3 -- Generator performance requirements

This is the section most relevant to anyone developing, connecting, or operating a generator in GB. It applies to all Generating Units, DC Converters, and Power Park Modules (but not Small Power Stations or individual Power Park Units).

Reactive power capability (CC.6.3.2)

Plant type Requirement Reference point Clause
Synchronous generators (onshore) 0.85 lagging to 0.95 leading at Rated MW; enhanced 0.9 lag where CEC increased above Rated MW post 1 May 2009 Unit terminals CC.6.3.2(a)
Non-synchronous / PPMs (onshore) Zero reactive transfer at all output levels; tolerance +/-5% Rated MW in MVAr Grid Entry Point CC.6.3.2(b)
Non-synchronous / PPMs (onshore, post 1 Jan 2006) 0.95 lagging to 0.95 leading at Rated MW; P-Q envelope per Figure 1 Grid Entry Point CC.6.3.2(c)

Short circuit ratio (CC.6.3.2(a)): - Synchronous generators <1600MVA: >= 0.5 - Synchronous generators >=1600MVA: >= 0.4

Other generator obligations (CC.6.3.3--CC.6.3.16)

Clause Subject Key requirement
CC.6.3.3 Voltage control AVR or equivalent required
CC.6.3.4 Frequency response Primary, secondary, high frequency response per Appendix 3
CC.6.3.5 Black Start Where contracted via Bilateral Agreement
CC.6.3.6 Operating range Minimum stable generation, start/shutdown times
CC.6.3.7 Fault ride through Withstand voltage dips per Appendix 4 envelope
CC.6.3.8 Power oscillation damping Power system stabiliser requirements
CC.6.3.9 Generator transformers Specification requirements
CC.6.3.10 Negative phase sequence Withstand capability
CC.6.3.11 Short circuit ratio See above
CC.6.3.12 RoCoF withstand Rate of change of frequency ride-through
CC.6.3.13 Control telephony Communication requirements
CC.6.3.14 Information requirements Data provision to NESO
CC.6.3.15 Frequency sensitive mode FSM/LFSM operating modes
CC.6.3.16 Active power during frequency events Output constraints

Appendices

  • Appendix 3: Minimum Frequency Response Requirement Profile and Operating Range
  • Appendix 4: Fault Ride Through Requirements (4A: general; 4B: specific envelopes)
  • Appendix 5: Low Frequency Relay Technical Requirements
  • Appendix 6: Excitation Control (Synchronous Generating Units)
  • Appendix 7: Voltage Control (Non-Synchronous / PPMs / DC Converters)

Covers Operation Diagrams, Site Responsibility Schedules (Appendix 1), site naming conventions, and site common drawings.

CC.8 -- Ancillary services

Covers Mandatory Services Agreements and System Ancillary Services. The commercial terms for ancillary services are in the CUSC and individual contracts; CC.8 sets the technical framework.

European Connection Conditions (ECC)

The ECC mirrors the CC structure (ECC.1--ECC.8) but applies to EU Code Users -- generators connecting under the retained EU Regulation 2016/631 (Requirements for Generators). Key differences: - Generators classified as Type A/B/C/D by MW threshold - Additional Appendix 4EC: Fast Fault Current Injection Requirements - Additional Appendix E8: Voltage Control for Configuration 2 AC/DC connected offshore PPMs - References EU Regulations 2016/1388 (Demand Connection Code) and 2016/1447 (HVDC Code)

The ECC is 137 pages in Issue 5 R25. It is structurally identical to CC but with EU-specific additions.

Character positions

(None yet captured.)


Last updated: 2026-04-05

Related pages