NESOOFGEMDESNZ

ENA ER G99 - Generation Connection (Type B/C/D)

Other·Topic·3 min read

title: ENA Engineering Recommendation G99 - Generation Connection (Type B/C/D) tags: [generation-connection, DNO, distribution, ENA, technical-standard, RfG, type-b, type-c, type-d, wind, solar, battery-storage, g99] instrument_row: 108 source_file: sources/energy-networks/ena-er-g99.md


ENA ER G99 - Generation Connection (Type B/C/D)

What it is: The GB technical standard governing how commercial-scale generation and electricity storage connects to distribution networks. Issued by the Energy Networks Association (ENA). Effective 27 April 2019. Current version: Issue 2, March 2025.

Full document (free PDF): https://dcode.org.uk/assets/250307ena-erec-g99-issue-2-(2025).pdf

The core problem it addresses

Any generator above roughly 16A per phase that wants to connect to a GB distribution network must comply with G99. Without a common technical standard, each DNO would impose different requirements, making multi-DNO project development harder and potentially creating inconsistencies that threaten grid stability. G99 implements the EU-derived RfG Regulation (2016/631, row 94) in a practical connection process that DNOs, developers, and equipment manufacturers can follow.

Which projects G99 affects

G99 covers all generation and storage not in scope of the smaller EREC G98 (micro-generators up to 16A per phase). In practice this means:

  • Solar farms and wind farms connecting at HV (all commercial scale projects)
  • Battery storage systems above roughly 50 kW
  • Gas peakers, embedded CHP, run-of-river hydro
  • Vehicle-to-Grid installations
  • Any plant designed for island mode operation, regardless of size

Issue 2 (March 2025) added new mandatory requirements specifically for electricity storage. Those apply from 1 March 2026.

Type A/B/C/D structure

G99 uses the RfG Type classification to scale requirements to generator size.

Type Scale Connection process
Type A Small (roughly up to 50 kW) Installation Document, basic interface protection
Type B Medium (50 kW to 1 MW approx) PGMD required, system studies, fault ride-through, LFSM-O
Type C Large (1 MW to 50 MW approx) Full simulation models, reactive power capability, FSM, full testing
Type D Very large (50 MW+ or HV connection) CUSC contract, Grid Code compliance, NESO involvement

Requirements accumulate: a Type C generator must also meet all Type A and B requirements.

Key technical requirements

Interface protection (all Types): Loss-of-mains detection using Rate of Change of Frequency (RoCoF). Vector Shift protection was banned by Ofgem (DC0079). The RoCoF threshold is set by NESO.

Frequency response: - LFSM-O: required for all G99 plant - reduce output when frequency exceeds 50.2-50.5 Hz - FSM (full frequency sensitive mode): required from Type C - continuous bidirectional frequency response, sustain for at least 15 minutes. This is the technical basis for frequency response ancillary services contracts.

Fault ride-through: Generators must stay connected through a voltage dip profile specified in the Annexes. Required from Type B; more demanding at Type D.

Fast fault current injection: Non-synchronous plant (inverter-based: wind, solar, batteries) must inject reactive current during voltage dips to support system voltage. Required from Type B.

Reactive power: Type C and above must demonstrate reactive power capability within a Q/Pmax envelope. Type C PPMs (power park modules) must achieve Q/Pmax 0.66; synchronous plant 0.95.

Connection process milestones

  1. PGMD (Power Generating Module Document): Applicant submits technical data on the plant.
  2. System analysis: DNO models the proposed connection against G99 and network constraints.
  3. Connection offer: DNO issues offer specifying G99 compliance requirements for this specific site.
  4. Type testing or site testing: Plant complies via type test certificates (ENA Type Test register) or site-specific testing.
  5. Operational Notification: DNO issues FON (Type B/C) or staged EON/ION/LON (Type D) on successful commissioning.

Relationship to other instruments

  • RfG Regulation (row 94): The legal basis. G99 cannot be less stringent than RfG minimums. RfG is the instrument to cite if G99 requirements are challenged.
  • EREC G98 (row 107): The companion standard for smaller plant (up to 16A per phase). G98 and G99 together cover all GB generation connecting to distribution.
  • Grid Code: Type D plant must also comply with the Grid Code Connection Conditions. For very large plant, the Grid Code governs in addition to G99.
  • DCUSA: The distribution connection agreement framework. G99 compliance is a condition of receiving a DCUSA connection.
  • ER G5/5 (row 106): Harmonic assessment runs alongside the G99 process for most commercial-scale projects.
  • ER G100 (row 109): Export limitation, offered as an alternative to network reinforcement for constrained connections.

Version history highlights

Version Year Key change
Issue 1 2018/2019 Original publication, RoCoF requirements, VS protection banned
G99/15 2019 Fast fault current injection requirements for Types B/C/D
G99/16 2020 Reactive capability table, simulation model requirements
Issue 2 2025 New storage requirements (1 March 2026), Anchor Plant, BEGA provisions