I0284: Updates to Schedule 14 Measurement Transformers Commissioning Timescales
What is being proposed
The current timescales in Schedule 14 section 15.6 and section 30.6 where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 need to be reviewed before the settlement timetable changes from RF being 14 to 4 months to ensure they are still fit for purpose.
Details
Proposed byCode Manager
Decision byPanel (Self-Governance)
GovernanceSelf-Governance
Impact onElectricity Suppliers, Electricity DNOs, Supplier Agents, Other
Timeline
Proposal raised25 Sept 2025✓
Analysis
REC code modification. See the codes page for full details.