CMP468: Removal of outdated references in CUSC (non-charging)
What is being proposed
Proposal Removes outdated references in CUSC to Seven Year Statement, Offshore Development Information Statement, and Electricity Ten Year Statement.
Current status
Proposal raised on 25 February and will be presented to the CUSC Panel on 27 March.
Details
Timeline
Analysis
NESO proposes removing outdated references to defunct planning documents (Seven Year Statement, Offshore Development Information Statement, Electricity Ten Year Statement) from the Connection and Use of System Code. The proposal will be presented to the CUSC Panel on 27 March 2026. Cross-code impacts affect the System Operator Transmission Owner Code.
Why it matters
Administrative housekeeping that removes regulatory clutter without changing operational requirements. The removal of these references reflects the consolidation of system planning functions under NESO, as such it simplifies the code without affecting charges or connection processes.
Key facts
- •Proposal raised 25 February 2026
- •CUSC Panel presentation 27 March 2026
- •Removes references to Seven Year Statement, Offshore Development Information Statement, Electricity Ten Year Statement
- •Cross-code impact on STC