CMP475 Balancing Services Use of System (BSUoS) urgency decision
Summary
Ofgem has granted urgency status to CMP475, which would allow NESO to reopen fixed BSUoS tariff periods mid-period when the Working Cash Flow (WCF) threshold is forecast to be exceeded, and to introduce a mechanism to recover the WCF position toward neutral within that period. NESO raised the modification on 15 April 2026; the CUSC Panel unanimously backed urgency on 21 April; Ofgem accepted on 29 April. This changes BSUoS from a truly fixed charge to one that can be reset intra-period, shifting forecast risk back onto demand users.
Why it matters
BSUoS was fixed precisely to give suppliers and large consumers cost certainty over defined periods. Reopening tariffs mid-period to manage NESO's cash flow position transfers balancing cost volatility back to demand, undermining the original rationale for fixed BSUoS introduced under CMP361. The urgency route compresses industry consultation, which favours the system operator's cash management over the charging certainty that market participants were promised.
Key facts
- •CMP475 raised by NESO on 15 April 2026
- •CUSC Panel unanimously recommended urgency on 21 April 2026
- •Ofgem accepted urgency on 29 April 2026
- •Modification would allow reopening of fixed BSUoS tariff periods when WCF threshold is forecast to be exceeded
- •Introduces a mechanism to recover WCF position toward neutral within a tariff period
- •BSUoS charges recover NESO's costs of balancing the electricity system
Areas affected
Related programmes
Memo
What changed
Ofgem has granted urgency status to CUSC Modification Proposal CMP475, raised by NESO on 15 April 2026. The modification would allow NESO to reopen fixed BSUoS tariff periods mid-period when its Working Cash Flow (WCF) is forecast to breach the threshold, and to recover that cash flow position back toward neutral within the same period. The CUSC Panel unanimously supported urgency on 21 April; Ofgem accepted on 29 April. The urgency designation compresses the normal modification timeline, limiting the window for industry consultation.
This is a structural change to how BSUoS works. Since CMP361 took effect in April 2023, BSUoS has been set as a fixed tariff over defined periods, giving suppliers and large demand users a known cost for each period. CMP475 introduces a reopener mechanism that makes those fixed periods conditional: fixed unless NESO's cash flow says otherwise. The charge remains notionally fixed, but NESO now holds a unilateral trigger to reset it.
What this means in practice
Demand users pay. BSUoS is levied on final demand. Suppliers pass it through to consumers. Under the current fixed tariff regime, suppliers can price BSUoS into their hedged positions with reasonable confidence. A mid-period reset breaks that hedge. The cost of the reset falls on suppliers who have already committed to customer prices, and ultimately on consumers who have no visibility of the mechanism at all.
Generators on BSUoS exemption are unaffected. Since CMP361, generation is exempt from BSUoS on a final-demand basis. CMP475 does not change this. The entire adjustment falls on the demand side.
NESO's cash flow risk is transferred, not eliminated. The modification does not reduce the underlying balancing costs that drive WCF pressure. It transfers the timing risk from NESO's balance sheet to demand users' bills. When balancing costs spike mid-period, instead of NESO absorbing the cash flow mismatch until the next tariff period (and recovering it then), it can reset tariffs immediately. This is a liquidity management tool for NESO, funded by demand.
The "fixed" in fixed BSUoS now carries an asterisk. CMP361's core promise was cost certainty. The policy rationale was explicit: suppliers and consumers should be able to plan around a known BSUoS charge for each defined period. CMP475 preserves the language of fixed tariffs while introducing a mechanism that can override them. The question is whether "fixed unless we reopen it" is meaningfully different from "variable with advance notice." For any supplier trying to hedge forward costs, the distinction is thin.
Urgency compresses scrutiny. The normal CUSC modification process allows for workgroup assessment, industry consultation, and alternative proposals. Urgency status shortens this timeline significantly. NESO raised the modification on 15 April; the Panel backed urgency six days later; Ofgem accepted eight days after that. The 14-day window from proposal to Panel recommendation is unusually fast for a change that alters the charging basis for all demand users. Industry participants will have limited opportunity to propose alternatives or challenge the WCF threshold calibration.
The WCF threshold itself matters, and it is not public. The trigger for a tariff reset is NESO forecasting that WCF will breach the threshold. The calibration of that threshold, the forecasting methodology, and the tolerance bands all determine how frequently this mechanism fires. A tight threshold with conservative forecasting could trigger resets regularly, making BSUoS effectively variable again. A generous threshold might never trigger. The detail is in the modification proposal, not the urgency decision, but the urgency route means that detail gets less industry scrutiny than it would under normal timelines.
What happens next
CMP475 now proceeds through the urgent modification process. This means a compressed workgroup phase, a shorter consultation window, and an accelerated Panel recommendation to Ofgem for a final decision. Under urgency procedures, the entire process from raising to decision can complete in weeks rather than the months typical of standard CUSC modifications.
Key dates to watch:
- Workgroup meetings will be scheduled imminently, likely within the first two weeks of May 2026. - Industry consultation will be shorter than the standard 15 working days. Participants should prepare responses early; the window may be as short as 5-10 working days. - CUSC Panel recommendation to Ofgem will follow the consultation, potentially by late May or early June. - Ofgem final decision could land before the end of June 2026, depending on whether alternative proposals emerge.
If approved, the reopener mechanism would apply to future BSUoS tariff periods. The implementation date will depend on the final decision, but the urgency designation signals NESO believes the WCF pressure is near-term, not hypothetical.
Related context: this modification should be read alongside CMP361 (the original fixed BSUoS reform) and any ongoing Ofgem work on BSUoS charging methodology. If mid-period resets become routine, the case for revisiting the fixed tariff model entirely becomes harder to avoid.
Source text
CMP475 Balancing Services Use of System (BSUoS) urgency decision | Ofgem Please enable JavaScript in your web browser to get the best experience. BETA This site is currently in BETA. Help us improve by giving us your feedback . Close alert: CMP475 Balancing Services Use of System (BSUoS) urgency decision Publication type: Code modification Publication date: 29 April 2026 Topic: Energy codes, Electricity transmission Subtopic: Connection and use of system code (CUSC) Print this page Share the page Share on Facebook Share on Twitter Share on LinkedIn Outcome of request for an urgent review of proposed changes to Connection and Use of System Code CMP475, Amendment to the BSUoS tariff reset process. Details of outcome On 15 April 2026, the National Energy System Operator (NESO) raised the Connection and Use of System Code CUSC Modification Proposal CMP475: ‘Amendment to the BSUoS tariff reset process’. On 21 April 2026, the CUSC Panel wrote to inform us of its unanimous view that CMP475 should proceed as an Urgent CUSC Modification Proposal. We have decided to accept the request for urgency for CMP475. This letter sets out our reasoning. Code modification description This proposal concerns change to the Balancing Services Use of System (BSUoS) tariff reset process within the Connection and Use of System Code. BSUoS charges are used to recover the costs incurred by the National Energy System Operator in balancing the electricity system and are currently set as fixed tariffs over defined periods. CMP475 to enable the reopening of fixed BSUoS tariff periods where NESO forecasts that the WCF will be exceeded, and to introduce a mechanism to allow recovery of the WCF position toward a neutral level within a tariff period. Documents CMP475: Approval of urgency request [PDF, 203.76KB] Print this page Share the page Share on Facebook Share on Twitter Share on LinkedIn Close