Rampion 2 Offshore Wind Farm Order 2025: correction of errors, Planning Act 2008

DESNZ·decision·LOW·23 Apr 2026·source document

Summary

The Secretary of State has issued corrections to the Rampion 2 Offshore Wind Farm Development Consent Order (1,200 MW). The publication contains only the fact of the correction with no detail on what was changed. This is a routine administrative tidying of an already-granted DCO.

Why it matters

No material change to the consenting regime or project economics. The DCO is already granted; error corrections are procedural.

Key facts

  • Rampion 2 maximum output: 1,200 MW
  • Decision date: 23 April 2026
  • Applicant: Rampion Extension Development Limited
  • Correction under Planning Act 2008 error correction provisions

Timeline

Effective date23 Apr 2026

Areas affected

renewablesplanning

Related programmes

Clean Power 2030CfD
Memo

Decision by the Secretary of State to make corrections to the Rampion 2 Offshore Wind Farm Order 2025. Date of decision 23 April 2026 Company / location Rampion Extension Development Limited Swindon Wiltshire Maximum output 1200 MW